  1. September 14, 2026

    v1.32.0 · 1,718 sites · 59 added · 1 status moves · 0 reception changes

    Status moves

    Added to the record

  2. September 13, 2026

    v1.32.0 · 1,659 sites · 88 added · 3 status moves · 0 reception changes

    Status moves

    Added to the record

  3. September 12, 2026

    v1.32.0 · 1,571 sites · 8 added · 0 status moves · 0 reception changes

    Added to the record

  4. September 11, 2026

    v1.32.0 · 1,563 sites · 67 added · 4 status moves · 30 reception changes

    Status moves

    Reception changes

    Added to the record

  5. September 10, 2026

    v1.32.0 · 1,496 sites · 83 added · 2 status moves · 7 reception changes

    Status moves

    • Marshall Technology & Energy Center Gas Generation · Marshall, MI : Proposed to Cancelled
    • Bitdeer Massillon Facility · Massillon, OH : Under construction to Operating

    Reception changes

    Added to the record

  6. September 9, 2026

    v1.32.0 · 1,413 sites · 8 added · 1 status moves · 1 reception changes

    Status moves

    Reception changes

    Added to the record

  7. September 8, 2026

    v1.32.0 · 1,405 sites · 0 added · 0 status moves · 0 reception changes

  8. September 6, 2026

    v1.31.0 · 1,405 sites · 21 added · 1 status moves · 0 reception changes

    Status moves

    Added to the record

  9. September 5, 2026

    v1.31.0 · 1,384 sites · 33 added · 0 status moves · 0 reception changes

    Added to the record