Flexential Parker (Compark) is a data center under construction in Parker, Colorado (Douglas County), operated by Flexential. The public record puts it at 22.5 MW planned, 17 acres, a reported $205 million investment. It has documented public support and no documented opposition.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Under construction
- Operator
- Flexential
- Facility type
- Data center
- Location
- Compark Boulevard, Parker, Douglas County, CO
- Coordinates
- 39.5621, -104.8119 (approximate)
- Power capacity
- 22.5 MW planned
- Land
- 17 acres
- Investment
- $205 million
- Announced
- Not established from a public source
- Utility
- CORE Electric Cooperative
- Power source
- Grid
- Cooling
- Closed loop
- Water use
- Not established from a public source
- Jobs
- 16 permanent
- Public subsidy
- Not established from a public source
- Community reception
- Supported
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- August 11, 2026Under constructionReported under construction in the Compark Village development as Douglas County commissioners prepared to vote on an incentive agreement. Source: Colorado Politics
Opposition and litigation at this site
Not that we can document. Local officials or residents have expressed public support for Flexential Parker (Compark) in Parker, Douglas County, Colorado, and no opposition, petition, or lawsuit appears in the sources this registry tracks as of September 10, 2026. Parker's planning commission (Jan.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: supported means local officials or residents have expressed public support and no opposition is documented.
Parker's planning commission (Jan. 2024) and Town Council (Feb. 2024) both approved the rezoning/data-center overlay district unanimously; no resident opposition to the facility itself is documented in this source. A separate, later debate (checked 2026-08-11) concerns a possible $19M Douglas County tax rebate -- the article covers statewide water/energy-consumption-vs-jobs debate in general terms but records no opposition testimony specific to this rebate or this site; Parker itself is 'not offering tax incentives for the project' per the article, without stated rationale.
Power and water
Closed-loop liquid cooling targeting zero water usage effectiveness, per the county incentive review.
Notes on the record
249,000 sq ft on 17 acres on Compark Boulevard near South Chambers Road. The town of Parker approved rezoning and a data center overlay district in February 2024 after a January 2024 planning-commission approval. A $19.3 million Douglas County business-personal-property tax rebate over 35 years was scheduled for a commissioner vote the week of 2026-08-11; it is not recorded here as a subsidy because the award had not been made as of the source date. County estimate of 16 permanent positions; company representatives suggested 30-50. Coordinates are an approximate Compark Boulevard geocode, not parcel-confirmed. Distinct from Flexential's existing Aurora, Centennial, Downtown and Englewood Denver-market sites.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Tax abatements or other public subsidy
Which document closes each gap
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Flexential Denver - Englewood · Englewood · Flexential1 mi · Operating · 18 MW
- DataBank DEN5, Centennial II · Centennial · DataBank3 mi · Operating · 16 MW
- Flexential Denver - Centennial (DEN05) · Centennial · Flexential3 mi · Operating
- H5 Data Centers Denver (Denver Tech Center campus) · Greenwood Village · H5 Data Centers6 mi · Operating · 17.5 MW
- Flexential Denver - Aurora (DEN03) · Aurora · Flexential7 mi · Operating
- QTS Aurora-Denver Data Center Campus (DEN1) · Aurora · QTS Data Centers11 mi · Under construction · 177 MW · Mixed reception
- CoreSite DE3 · Denver · CoreSite15 mi · Under construction · 60 MW · Contested
- Flexential Denver - Downtown (Champa) · Denver · Flexential16 mi · Operating
Questions people ask about this site
Is there opposition to the Flexential Parker (Compark) data center in Parker?
Not that we can document. Local officials or residents have expressed public support for Flexential Parker (Compark) in Parker, Douglas County, Colorado, and no opposition, petition, or lawsuit appears in the sources this registry tracks as of September 10, 2026. Parker's planning commission (Jan.
Has anyone filed a lawsuit over the Flexential Parker (Compark) data center?
No lawsuit over Flexential Parker (Compark) appears in the record we track as of September 10, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Flexential Parker (Compark) use?
No water withdrawal figure for Flexential Parker (Compark) is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.
Who operates Flexential Parker (Compark), and how big is it?
Flexential is the operator on record. We hold 46 sites for that company across the registry. Capacity on record is 22.5 MW. The site is recorded at 17 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Flexential Parker (Compark)," updated September 10, 2026, https://suedatacenters.org/data-centers/flexential-parker-co.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/flexential-parker-co, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Parker data center could get $19M tax rebate from Douglas County · Colorado Politics · retrieved August 26, 2026
- 2.Parker data center could get $19M tax rebate from Douglas County · retrieved September 10, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us