Every site in the registry with documented opposition or a lawsuit on the public record, by state. Reception is a sourced signal: a filing, a petition, a hearing record, a named report. Sites with no reception on record are not here, so this list is a floor, not a ceiling.

355
sites
62
in litigation
111
organized opposition
182
under active debate
128.8 GW
planned capacity contested
46
states

As of September 14, 2026. Download the data or see the projects that were cancelled.

Alabama

6 contested · 1 in court · 3.1 GW planned

  • Nebius Birmingham AI Factory (BHM01)In litigationBirmingham · Nebius Group · Under construction · 300 MW

    Two lawsuits filed by Oxmoor Valley residents seeking injunctions; the first was dismissed May 29 2026, a second filed June 29 2026.

  • Project Red ClayOpposedCloverleaf Infrastructure · Proposed · 1.5 GW

    Route Fifty (25 Aug 2026): "About 350 people signed the group's petition demanding more transparency from the commission", the group is Protect Lowndes County, which filed an open-records request on 27 July 2026 seeking project documentation and entity lists.

  • Sovereign Gazelle Bitcoin Mining Data CenterOpposedSomerville · Sovereign Gazelle · Proposed · 50 MW
  • QTS Bessemer (Project Marvel)ContestedBessemer · QTS Data Centers · Proposed · 1.2 GW

    Dismissed June 22, 2026 by joint stipulation.

  • Digi Power X Columbiana AI Data CenterContestedColumbiana · Digi Power X · Under construction · 40 MW

    "Since its announcement, residents have expressed disapproval for the data center leading to a town hall in January 2026 that answered questions regarding the facility.

  • Patmos Fairfield Colocation Data CenterContestedFairfield · Patmos · Proposed

    WBRC (13 Aug 2026) reports "Hundreds pack Fairfield town hall over proposed data center inside former Walmart", with residents raising health risks, rising utility bills and community benefit.

Arizona

9 contested · 0 in court · 5.1 GW planned

  • Project BlueOpposedBeale Infrastructure · Under construction · 600 MW

    Dismissed April 2026, appeal expected.

  • Energy Generation and Technology CampusOpposedMaricopa · W Holdings · Proposed

    The Ak-Chin Indian Community, whose southern boundary abuts the site, opposes the location.

  • La Osa Data Center ParkOpposedEloy · Vermaland LLC · Cancelled

    All approximately 60 public comments and 50 emails received by the Pinal County Board opposed the project.

  • Hassayampa Ranch Data CenterContestedTonopah · Arizona Land Consulting · Proposed · 1.5 GW

    Maricopa County Board of Supervisors unanimously approved the industrial rezoning (Dec 10, 2025) despite two resident-led petitions totaling roughly 300 signatures opposing the project over well-water impacts.

  • Luckett Road Data Centers (Fremont Peak Properties)ContestedMarana · Fremont Peak Properties LLC (Beale Infrastructure) · Proposed · 1.5 GW

    Marana Town Council approved rezoning 6-0 after hours of packed public testimony on water, power, and growth concerns.

  • Project BaccaraContestedTakanock, LLC · Permitted · 700 MW

    Board of Supervisors approved 4-1 (May 2026).

  • Project Midway Data CenterContestedCasa Grande · LPI Group · Proposed · 400 MW

    Hidden Valley residents raised concerns about falling water tables and deeper well drilling, with one resident saying 'There needs to be a cap on the water, if any water is used.' A June 2026 opposition letter from a nearby homeowner linked a well pump burnout to lowered groundwater.

  • NTT Global Data Centers Mesa, Pacific Proving Technology ParkContestedMesa · NTT Global Data Centers · Proposed · 360 MW

    Residents packed June 2026 Mesa City Council meeting opposing rezoning, citing water use, heat, and drought.

  • Project RangeContestedBuckeye · Tract · Proposed

    The cities of Buckeye and Goodyear both raised significant concerns over building heights, noise and deviation from surrounding land use, and area residents circulated a petition opposing the project.

Arkansas

8 contested · 2 in court · 1 GW planned

California

8 contested · 1 in court · 694.2 MW planned

  • Imperial Valley Computer Manufacturing AI Data CenterIn litigationImperial · Imperial Valley Computer Manufacturing (IVCM) · Proposed · 330 MW

    Pending, Imperial County Superior Court (filed June 2026); developer is the plaintiff.

  • Coachella Valley Technology CampusOpposedCoachella · Stronghold Power Systems · Cancelled

    Hundreds attended town halls over water use, power costs, air quality, noise, farmland loss, and proximity to Valle del Sol Elementary (about 2 miles).

  • DigiCo LAX1 (1977 Saturn Street)OpposedMonterey Park · DigiCo Infrastructure REIT · Cancelled

    Measure NDC, a permanent citywide data-center ban, passed 88.34% (10,321-1,362) in a June 2, 2026 special election and was implemented via Ordinance 2279; the applicant's withdrawal (March 31, 2026) preceded the vote.

  • CyrusOne AI Data Center at NAS LemooreContestedCyrusOne · Proposed · 100 MW

    Kings County Supervisor Garrett Gilcrease (also Farm Bureau president) opposed the project on water grounds during his 2024 campaign; the project advanced with little public input; no formal legal challenge as of mid-2026.

  • AVAIO Digital PerseusContestedPittsburg · AVAIO Digital Partners · Permitted · 99 MW

    The CBD CEQA lawsuit was settled Dec 2025, but public opposition continues independently: a Change.org petition had roughly 14,000 signatures as of June 2026, and a June 15 2026 City Council meeting drew 200+ attendees with mostly-opposed public comment; the Mayor and Council directed an additional public workshop (held July 30, 2026).

  • Amazon AWS Gilroy Data CenterContestedGilroy · Amazon Web Services · Under construction · 98 MW

    Organized resident opposition active.

  • STACK SVY03AContestedHayward · STACK Infrastructure · Permitted · 67.2 MW

    Approved via a zoning classification (Hayward Municipal Code Section 10-1.1604) that treated data centers as "office use," letting the project bypass City Council-level review and go through Planning Commission alone.

  • Solano County Fairgrounds Data Center (Global Stack proposal)ContestedVallejo · Global Stack LLC · Proposed

    Proposal was on the Solano County Fair Association Board of Directors' meeting agenda for 2026-07-16.

Colorado

6 contested · 0 in court · 2.2 GW planned

  • Granite Renewables Logan County Data Center CampusContestedSterling · Granite Renewables · Proposed · 2 GW

    Logan County declared a moratorium on data centers, battery storage, solar and wind development in October 2025 while it wrote regulations; planning-commission recommendations went to the county commissioners on 2026-01-06.

  • CoreSite DE3ContestedDenver · CoreSite · Under construction · 60 MW

    Elyria-Swansea residents have opposed the project over water use, air pollution and noise since construction began, holding a neighborhood press conference in February 2026; the backlash helped prompt Denver's one-year moratorium on new data center approvals, passed by city council in May 2026, which blocks CoreSite's two additional planned buildings but not the one already standing.

  • Raeden Project TaurusContestedColorado Springs · Raeden · Permitted · 50 MW

    Colorado Springs Planning Commission voted 6-2 (July 2026) to deny five appeals of the project's staff-level administrative approval, filed by a resident and an advocacy group, after a marathon public hearing, attaching conditions (a 50MW power cap and low-frequency infrasound monitoring).

  • Global AI Windsor Data Center (former Kodak/Carestream campus)ContestedWindsor · Global AI · Under construction · 27.5 MW

    Weld County posted stop-work orders on the property on 2026-05-07, 2026-06-11 and again on an unspecified date for un-permitted construction, and issued a formal order to abate on 2026-07-20.

  • BluSky AI Walsenburg (Indian Pool Ranch) Modular Data CenterContestedWalsenburg · BluSky AI Inc. · Proposed · 15 MW

    Walsenburg's mayor and town administrator said they were unaware of the plan when contacted in early 2026.

  • Crusoe Energy Digital Flare Mitigation, Oxbow Well PadContestedWalden · NYDIG DFM · Operating

Connecticut

1 contested · 0 in court · 300 MW planned

Delaware

5 contested · 1 in court · 1.5 GW planned

  • Project Washington (Starwood Digital Ventures)In litigationDelaware City · Starwood Digital Ventures · Proposed · 1.2 GW

    DNREC Secretary denied Coastal Zone Act permit February 4, 2026 citing 516 backup diesel generators and 2.5 million gallons of stored diesel as unprecedented heavy industrial use under Delaware's 1971 Coastal Zone Act.

  • Harrington Data Center Proposal (Maguire Hayden)OpposedHarrington · Maguire Hayden · Cancelled · 24 MW

    Council vote was unanimous against the project despite a proposed $1M community-benefits package; press described the rejection as met with 'cheers and a standing ovation' from residents in attendance.

  • STAR Campus Data Center & Cogeneration Plant (The Data Centers, LLC)OpposedNewark · The Data Centers, LLC · Cancelled

    A UD faculty/administrator review group and Newark-area residents raised sustained concerns on environmental-impact and campus-mission grounds; UD's review concluded the 279 MW plant was unprecedented in scale for a US data center, could not be environmentally assessed absent a comparable precedent, and that TDC had shifted emphasis toward wholesale power sales rather than the university's science/tech mission.

  • St. Georges Business Park & Lighthouse FarmsContestedSt. Georges · Parkway Gravel Inc. · Proposed · 300 MW

    The site includes land hosting Frightland, a well-known Delaware Halloween attraction, which would be demolished.

  • White Clay Corporate Center Data Center RedevelopmentContestedNewark · Shelbourne · Proposed

    A county councilman publicly brokered a pause after community/political pressure, but the arrangement is a non-binding handshake conditioned on a zoning workaround; the councilman acknowledged its fragility ('If I'm not there, there's no promises').

Florida

8 contested · 0 in court · 1.7 GW planned

  • Holder Industrial Park Data Center Expansion (withdrawn)OpposedLecanto · Deltona Corporation · Cancelled

    More than 200 residents attended the Planning and Development Commission's public hearing, the vast majority speaking in opposition, citing water and electricity use, artificial light in a rural area, and a continuous low-frequency hum.

  • Project SwanOpposedLakeland · Ryan Companies (end operator TBD) · Cancelled

    More than 50 residents attended the June 1, 2026 Lakeland City Commission meeting to oppose the proposed 'Project Swan' hyperscale data center, with 18 speaking against it during audience comments.

  • Florida Ecopark AI Data Center CampusContestedFort Meade · Stonebridge (via Florida Ecopark LLC; end tenant undisclosed) · Proposed · 1.2 GW

    Florida Commerce Secretary Alex Kelly called project 'fundamentally flawed' in April 17, 2026 letter citing water, energy, and transportation risks.

  • Cielo Haines City Data CenterContestedHaines City · Cielo Digital Infrastructure · Proposed · 300 MW

    City commissioners Anne Huffman, Kim Downing, and Lekia Johnson have voiced opposition citing infrastructure, energy, water, traffic, and quality-of-life concerns.

  • NextNRG Nassau County Data Center & Energy CampusContestedNextNRG · Proposed · 200 MW

    Nassau County is pursuing a 12-month moratorium in response to the proposal.

  • Iron Mountain MIA-1ContestedWestview · Iron Mountain · Under construction · 16 MW

    Westview residents say they only learned the project was a data center after construction was already underway, and raised concerns about water usage, power-grid strain, and local job access at a town hall with County Commissioner Marleine Bastien; no litigation reported.

  • HostDime Orlando Tier IV Data CenterContestedEatonville · HostDime · Under construction

    Eatonville Town Council members have pushed for transparency and raised water/power/noise/appearance concerns; the town has assessed missed-deadline fines.

  • Project Tango AI Data Center CampusContestedLoxahatchee · PBA Holdings (end tenant undisclosed) · Cancelled

    Over 8,000 Change.org petition signatures opposing project.

Georgia

20 contested · 5 in court · 7.6 GW planned

  • Project Camellia (OpenAI Effingham County Campus)In litigationRincon · OpenAI · Proposed · 3.2 GW

    Three residents, Michelle Finch-Mincey, Lehman Mincey Jr.

  • Project Sail, Prologis Data Center CampusIn litigationNewnan · Prologis · Permitted · 900 MW

    Pending, Coweta County Superior Court.

  • Meta Newton Data Center (Stanton Springs)In litigationSocial Circle · Meta Platforms · Operating

    Pending, filed late August 2026, Gwinnett County.

  • Wallace Jackson Data Center CampusIn litigationGriffin · Wallace Jackson, LLC (developer; end user undisclosed) · Permitted

    Two lawsuits were filed in Spalding County Superior Court against the Board of Commissioners' Jan.

  • White Oak Technology ParkIn litigationAppling · Trammell Crow Company (CBRE subsidiary) · Permitted

    Columbia County unanimously approved the White Oak rezoning with conditions (Feb 3, 2026), but a resident filed a judicial-review lawsuit (Feb 25, 2026) challenging the approval over an outdated traffic study, unverified water/sewer capacity, and an unreviewed access-route change.

  • Lovejoy Data Center Campus (Stillwater Development)OpposedLovejoy · Stillwater Development · Cancelled · 1.3 GW

    Opposition centred on proximity to Michelle Obama STEM Elementary Academy, Eddie White Middle School and New Hope Methodist Church, and on Panhandle Road school traffic cited in the city's own DRI comments.

  • Project Ruby (Upatoi Data Center Campus)OpposedColumbus · Undisclosed end user (site pursued by Choose Columbus / Development Authority of Columbus) · Proposed · 600 MW

    About 5,000 residents signed an online petition against the project, citing environmental, property-value, health and safety concerns; the council vote creating the overlay district was 6-2.

  • Coosa Data Center (Project Gracie)OpposedRome · Atlas Development LLC · Permitted

    A raucous crowd spoke against the rezoning over noise, night lighting and water-draw concerns; commissioners doubled public-comment time.

  • Liberty Road Data Center Campus (EdgeConneX)OpposedVilla Rica · EdgeConneX (applicant East Village Dothan LLC) · Cancelled

    The announced project size drew audible jeers from a packed Citizens Hall; residents cited continuous noise and the site's position in the Dog River Basin, which feeds the county's main drinking-water reservoir.

  • LN Energy Blackshear Bitcoin MineOpposedBlackshear · LN Energy · Cancelled

    Over 150 residents attended the February 2025 Pierce County Commission meeting, with virtually everyone opposing the permit; stated concerns were noise, high energy consumption, and potential property-value declines.

  • Project Bus (Atlas Development Temple Data Center Campus)OpposedTemple · Atlas Development LLC · Proposed

    Sustained resident opposition organised as the Carroll County Anti-Data Center Coalition over roughly two weeks; the Carroll County Board of Commissioners issued a statement opposing annexation of the county property into Temple, and the developer withdrew the proposal on 2026-08-04.

  • Project Oak Data Center (Walt Sanders Road)OpposedNewnan · Undisclosed developer · Cancelled

    Coweta County received 121 letters of opposition from 112 individuals and none in support; the denial drew applause from a standing-room-only crowd.

  • Project Peach (CyrusOne Palmetto Data Center Campus)OpposedPalmetto · CyrusOne (joint venture with North Coweta Investors) · Permitted

    Residents packed the rezoning hearing in opposition; Palmetto's mayor asked commissioners to weigh the long-term cost to quality of life, environment and residents.

  • Microsoft Fairwater Atlanta (Azure AI Superfactory)ContestedFayetteville · Microsoft · Operating · 1.5 GW

    Fayetteville adopted a 90-day moratorium (Jan 29 2026) then unanimously passed Ordinance 26-O-12 (March 5 2026) banning new data centers in all zoning districts; existing Fairwater 1/2 and the Dec 2025 East Campus rezoning are grandfathered.

  • Microsoft Tyrone Campus (Project Rita)ContestedTyrone · Microsoft · Permitted · 96 MW

    2024 rezoning drew limited opposition; by 2026 residents launched a Change.org petition seeking an independent environmental/infrastructure study and a moratorium on future data centers.

  • 1155 Powers Ferry Place Data Center (Prime Storage conversion)ContestedMarietta · Prime Storage (Prime Group Holdings), end user undisclosed · Permitted · 18 MW

    Protesters at the August 2026 council meeting raised noise and pollution concerns, particularly for nearby Rottenwood Creek; the council attached monitoring and independent sound-study conditions.

  • Northern Data Maysville Data CenterContestedMaysville · Northern Data Group · Permitted

    A Planning and Zoning Board informational session was scheduled for 2026-05-18, rescheduled to 2026-06-01 and then cancelled, drawing sustained resident objections about process and transparency.

  • QTS Project EisenhowerContestedAugusta · QTS Data Centers · Under construction

    Organized neighborhood opposition (Haynes Station / Captain's Corner) over transparency, noise, environmental impact, and Savannah River water use; residents spoke at Augusta Commission meetings (May-June 2026).

  • Serverfarm Covington Data Center (Hazelbrand Road)ContestedCovington · Serverfarm · Under construction

    Environmental and community groups (Southern Environmental Law Center and partners) filed an enforcement request with Georgia EPD over unpermitted construction and air-quality concerns.

  • Social Circle Technology ParkContestedSocial Circle · TPA Group (developer; end tenant undisclosed) · Proposed

    Social Circle City Council unanimously approved a special-use permit for SC Infrastructure LLC (June 2025).

Idaho

2 contested · 0 in court

  • Gemstone Technology ParkContestedKuna · Diode Ventures · Proposed

    Kuna City Council approved rezoning the site from agricultural to M-1 light industrial in a 3-2 vote on 2025-04-01, with Mayor Joe Stear breaking the tie.

  • Lex Developments AI Data Center (former Hoku polysilicon site)ContestedPocatello · Lex Developments · Cancelled

    Hearing Examiner Kathleen Lewis denied the conditional use permit after a 2026-05-14 hearing, finding the application did not meet Pocatello Municipal Code 17.02.130(D)'s criteria that the use adequately serve public facilities and not be detrimental to public health, safety, or welfare; critics said the applicant could not answer specifics of the conditions and no tenant was confirmed pending an Idaho Power capacity study.

Illinois

10 contested · 3 in court · 6.9 GW planned

  • Joliet Technology CenterIn litigationJoliet · HW Technology Park (Hillwood Investment Properties / PowerHouse Data Centers) · Permitted · 1.8 GW

    Pending, Will County Circuit Court (filed May 18, 2026); motions heard September 8, 2026.

  • Project Cardinal Data Center CampusIn litigationYorkville · Pioneer Development LLC · Permitted · 1.8 GW

    Two active lawsuits as of July 2026.

  • T5 Chicago IV (CHI IV)In litigationGrayslake · T5 Data Centers · Under construction · 1.6 GW

    A residents' collective and nine Lake County homeowners sued Grayslake, T5 Data Centers and Alter Asset Management on July 31, 2026 in Lake County Circuit Court to void the approvals.

  • Steward Drive Data Center (Rochelle)OpposedRochelle · Midwest Power Investors LLC (LFF Industrial) · Cancelled · 150 MW

    Residents raised concerns about environmental impact and utility bills during a roughly two-year review; the mayor asked the council to vote the development agreement down.

  • Brennan Barrington Hills Data CenterOpposedBarrington Hills · Brennan Investment Group · Cancelled

    A Change.org petition gathered 1,303 signatures citing air pollution, water quality and tax concerns; the village said the matter was closed with no further discussion anticipated.

  • Lutticken Farm Data Center (Pekin)OpposedPekin · Western Hospitality Partners · Cancelled

    The project drew vigorous opposition in Pekin and surrounding communities; the mayor's announcement that the city would not proceed drew applause from a packed council meeting, and a resident group, Protect Pekin, formed to oppose it.

  • Project Kilo Data Center (South Elgin)OpposedSouth Elgin · White Rose Partners · Proposed

    An online petition against the project had 8,347 signatures as of 28 July 2026; the developer launched an informational website in response, characterising the objections as misinformation.

  • Meridian Technology ParkContestedClarksdale · Eagle Rock Partners · Proposed · 1 GW

    Christian County had a pre-existing moratorium on data center construction (imposed Aug 2025); a resident petition with nearly 700 signatures calls for an 18-month moratorium plus independent studies before any approval.

  • CyrusOne Sangamon County Data Center CampusContestedCyrusOne · Permitted · 630 MW

    No lawsuit confirmed from court records; zoning granted 17 to 10 with one abstention on April 7, 2026.

  • Aligned Coal City CampusContestedCoal City · Aligned Data Centers · Proposed

    Local coverage reports pushback over proximity to residential zones, Coal City Middle School and the Early Childhood Center; a Change.org petition opposes the campus.

Indiana

16 contested · 4 in court · 6.3 GW planned

  • Google Project Louie (Morgan County)In litigationMonrovia · Google · Under construction · 390 MW

    Significant opposition.

  • Sabey Decatur Technology ParkIn litigationDecatur Township · Sabey Data Centers · Permitted · 250 MW

    Metro Development Commission approved via a 'variance of use' (bypassing full rezoning) in March 2026; 7 residents sued in Marion Superior Court for judicial review, developer filed a motion to dismiss June 2026, case pending.

  • Metrobloks Martindale-Brightwood Data CenterIn litigationIndianapolis · Metrobloks · Permitted · 75 MW

    Six months of Martindale-Brightwood resident opposition; residents filed suit citing environmental concerns after the April 1, 2026 rezoning approval.

  • Wolcott Data CenterIn litigationWolcott · Blue Ladder Development · Permitted

    Wolcott residents Bart and Amy Snyder sued the commissioners, the White County Redevelopment Commission and the property owners in August 2025 seeking to overturn the rezoning of just over 184 acres near U.S.

  • Meta Jeffersonville Data CenterOpposedJeffersonville · Meta · Under construction · 407 MW

    Community groups pushed back citing water supply burden (up to 5 million gallons/day estimated), energy cost impacts, and tax abatements while investment in local economy seen as insufficient.

  • Bristol Innovation ParkOpposedBristol · The Province Group · Proposed

    More than 500 opponents attended the July 2026 hearing, which was relocated to a church gym to fit the crowd; the plan commission recommended denial 7-2.

  • Hancock County MegaSiteOpposedSurge Development LLC · Cancelled

    Neighbors including the owners of Tuttle Orchards raised concerns ahead of the 2025-05-08 public meeting on rezoning 775 acres of agricultural land in Buck Creek Township.

  • Jefferson Proving Ground Data CenterOpposedMadison · Undisclosed · Permitted

    A formal zoning appeal challenging the project was filed and denied (May 2026) after a ~5.5-hour hearing; opponents raised environmental concerns over proximity to the Big Oaks National Wildlife Refuge and local water/utility strain.

  • Logix Reality Frankfort Data CenterOpposedFrankfort · Logix Reality LLC · Cancelled

    Commissioners cited negative impact on area property owners.

  • New Carlisle Chicago Trail Data Center (rezoning denied)OpposedNew Carlisle · Undisclosed · Cancelled

    Council member Amy Drake said she was voting with the people of New Carlisle against the data center after overwhelming public testimony in opposition.

  • Outrigger Industrial Washington Data CenterOpposedWashington · Outrigger Industrial · Cancelled

    A local petition opposed the project on water/land grounds; the Washington City Council voted unanimously in May 2026 to cease all dealings with the developer and to explore a data-center moratorium.

  • AWS Hobart CampusContestedHobart · Amazon Web Services · Under construction · 2.4 GW

    Active opposition group 'No Data Centers Hobart Indiana'; majority of Plan Commission testimony opposed; concerns include noise, light, water/power use, property values; lawsuit filed in Lake County Court.

  • Amazon Project RainierContestedNew Carlisle · Amazon Web Services · Operating · 2.2 GW

    IDEM cited Amazon and its contractor for unauthorized wetland impacts and halted work in affected areas pending Section 401 water-quality recertification; a April 2025 public hearing drew 100+ residents opposing a pending wetland-fill permit near Bendix Woods County Park, with concerns over aquifer depletion and utility rates.

  • Project ShirleyContestedEagle Creek Township · Sentinel Data Centers · Proposed · 500 MW

    Rezoning vote postponed to May 2026; Board of Zoning Appeals final permitting still required.

  • DC BLOX Warren Township Data CenterContestedWarren Township · DC BLOX · Permitted · 78 MW

    Opponents filed an appeal against the hearing examiner's June 11, 2026 approval recommendation; full City-County Council vote pending, likely August 2026.

  • QLEVR Charlestown Data CenterContestedCharlestown · QLEVR LLC · Proposed · 3 MW

    The site is directly across from the Woodford Drive residential area; residents raised environmental concerns and Mayor Treva Hodges said she wanted higher expectations for developers and suggested delaying approval.

Iowa

10 contested · 1 in court · 250 MW planned

  • Salix Data Center Site (Midwest Capital Group)In litigationSalix · Midwest Capital Group (MidAmerican Energy) · Proposed

    Pending: residents' challenge to the annexation filed 2026, City of Salix moved to dismiss August 21, 2026; Woodbury County's court challenge also pending.

  • The Sept.

  • Simple Mining Cedar Falls (rezoning defeated)OpposedCedar Falls · Simple Mining · Cancelled

    Cedar Falls City Council unanimously rejected the zoning-code changes needed for this project on 2026-05-18, after sustained resident opposition over noise, water, and energy-consumption concerns tied to a paired proposal (Cedar Falls Utilities' 'Viking Energy Center' natural-gas plant, not itself a Compute Atlas facility type).

  • Applied Digital Adair County Data CenterContestedAdair · Applied Digital · Proposed · 200 MW

    At the April 2024 supervisors meeting one resident objected to living beside a 70-foot concrete wall, and Supervisor Jodie Hoadley raised loss of productive farmland and said project officials 'could not answer what was in it for Adair County.' The board determined zoning involvement was needed before the project could proceed and set a public hearing on a setback ordinance for April 24, 2024.

  • LightEdge Ames Edge Colocation Data CenterContestedAmes · LightEdge Solutions · Proposed · 25 MW

    No lawsuit filed; proposal in the hearing stage before the Ames City Council, resident study committee applications close September 9, 2026.

  • PathOne Sioux County Data Center (Hull)ContestedHull · PathOne Data Centers · Proposed · 25 MW

    Sioux County has a one-year moratorium on data centers in unincorporated areas, effective 2026-06-16, and no formal county approval has been granted.

  • Google Palo Data Center CampusContestedPalo · Google · Proposed

    Residents raised water and energy use, noise and light pollution at months of Palo public meetings.

  • QTS Clinton Data Center CampusContestedClinton · QTS Data Centers · Proposed

    ~100 residents packed a May 2026 planning commission meeting opposing the $10B QTS project over water/power impacts, then residents 'swarmed' a July 16, 2026 meeting to protest again; commissioners have twice declined to vote, postponing the decision rather than approving or denying.

  • Tract Norwalk Data Center Park (Project West)ContestedNorwalk · Tract · Proposed

    City hall and a library overflow room were packed for the March 5, 2026 hearing, with more than two hours of public comment focused on water sustainability and environmental impact; the council approved the agreement unanimously with one member absent.

  • Wahawk Power Data CenterContestedWaterloo · Wahawk Power, LLC · Proposed

    Protests at city hall and a push for a data-center moratorium followed the December 2025 development agreement; opponents cite water, power, noise and economic-benefit concerns.

Kansas

6 contested · 2 in court · 600 MW planned

Kentucky

6 contested · 1 in court · 2.2 GW planned

  • TenKey LandCo Project Lionsgate, Franklin Data CenterIn litigationFranklin · TenKey LandCo I LLC · Proposed

    Two active lawsuits: (1) TenKey LandCo sues Simpson County in Simpson Circuit Court challenging a December 2025 county ordinance requiring conditional-use permits for data centers, arguing county lacks zoning authority inside Franklin city limits; (2) Franklin Citizens for Responsible Development sues the Franklin P&Z Commission alleging it lacked authority to approve the preliminary plan, which passed 3-2 in March 2026.

  • Project Lincoln: OC Data CenterOpposedLa Grange · Western Hospitality Partners · Cancelled · 600 MW

    Organized opposition group 'We Are Oldham County' ('Some of the members of the fiscal court today voted to protect your rights', Nate Oberg).

  • PowerHouse Data Centers, Louisville (Camp Ground Road)OpposedLouisville · PowerHouse Data Centers · Under construction · 402 MW

    Strong community opposition from Rubbertown-area residents citing energy affordability burdens on low-income customers, environmental and health equity concerns in a historically underserved West End neighborhood.

  • Panattoni Burgin Data Center CampusOpposedBurgin · Panattoni · Proposed

    National developer Panattoni's proposed hyperscale AI data center on unincorporated farmland near Burgin would require annexation of 1,000+ acres, roughly doubling Burgin's size.

  • Cave Point Commerce CenterContestedCave City · Kentucky Industrial Alliance LLC · Proposed · 1.2 GW

    Cave City enacted a 12-month data-center zoning moratorium 2026-05-20.

  • Carrollton Industrial CampusContestedCarrollton · PowerHouse Data Centers / Poe Companies · Proposed

    Carroll County/Ghent-area residents organized opposition (group 'No Data Center 502') after learning the Carrollton Industrial Campus had reportedly been in development for over a year before its public announcement.

Louisiana

3 contested · 1 in court · 2 GW planned

  • Amazon Web Services Shreveport Campus (Resilient Technology Park)In litigationShreveport · Amazon Web Services · Proposed

    The west Shreveport announcement was pulled from the February 2026 state event after a suit by three plaintiffs and the Sierra Club Delta Chapter; the case remains in the Second Circuit Court of Appeals.

  • MS Solar Grid Data (New Orleans East)OpposedNew Orleans · MS Solar Grid Data · Cancelled

    Residents raised environmental and quality-of-life objections; the New Orleans City Council voted 6-0 on 2026-01-28 for a one-year moratorium on data center construction, and the developer withdrew the zoning permit hours later.

  • Meta HyperionContestedDelhi vicinity · Meta · Under construction · 2 GW

    Police records obtained by the Gulf States Newsroom show 64 crashes on the roads around the site from January to mid September 2025, against nine in all of 2024.

Maine

2 contested · 0 in court · 50 MW planned

  • Wiscasset Data Center (Old Ferry Road Site)OpposedWiscasset · Unnamed developer (NDA with town) · Proposed

    Grassroots group Protect Wiscasset formed by Richard Davis.

  • Loring LiquidCool Data Center (Green 4 Maine Campus)ContestedLimestone · LiquidCool Solutions / Green 4 Maine · Proposed · 50 MW

    Maine LD 307, pending in the Legislature as of March 2026, would bar permits for facilities over 20MW until late 2027, directly threatening this project's 24MW power agreement (developer says it 'can live with' the cap but it blocks the planned 50MW scale-up).

Maryland

7 contested · 0 in court · 2.7 GW planned

  • Brightseat Tech ParkOpposedLandover · Lerner Enterprises / The Tower Companies (Brightseat Associates LLC) · Permitted · 820 MW

    22,500+ petition signatures collected.

  • Dickerson Data CenterOpposedDickerson · Atmosphere Data Centers · Proposed · 360 MW

    Sustained opposition from Montgomery County community and environmental groups.

  • Rowan Digital Infrastructure Frederick Campus (Bauxite I)OpposedAdamstown · Rowan Digital Infrastructure · Under construction · 300 MW

    Neighboring residents raised health concerns over construction dust and traffic in November 2025.

  • Aligned Data Centers IAD-04 FrederickOpposedAdamstown · Aligned Data Centers · Under construction · 72 MW

    Frederick County Data Center Referendum Committee collected 21,000+ signatures opposing overlay zone expansion.

  • TeraWulf Morgantown Generating Station AI CampusContestedTeraWulf · Proposed · 1 GW

    Charles County Planning Commission voted to recommend denial of ZTA in March 2026 and again in June 2026 public hearing (four hours of resident testimony).

  • 1500 Woodlawn Drive Data Center CampusContestedWoodlawn · Security Land and Development LP · Proposed · 150 MW

    Residents raised concerns about water use, home values and utility bills at a December 2025 neighborhood meeting.

  • Globalinx Fastnet Cable Landing StationContestedBerlin · Globalinx (GLX) · Proposed · 5 MW

    Worcester County staff determined the proposed cable landing station does not qualify as a public utility and is not permitted under the site's current C-2 zoning.

Massachusetts

2 contested · 1 in court · 42 MW planned

  • Markley Group One Lowell Data CenterIn litigationLowell · Markley Group · Operating

    Massachusetts' first data center lawsuit filed April 27, 2026 in Middlesex County Superior Court by Honest Future for Lowell (10 plaintiffs) represented by Yale Law School Environmental Justice Clinic, Fitch Law Partners, and Conservation Law Foundation.

  • Servistar Realties Westfield Data Center CampusContestedWestfield · Servistar Realties · Proposed · 42 MW

    Westfield City Council voted unanimously on July 6, 2026 to enact a 365-day citywide moratorium on new data-center permits/construction after residents packed hearings over water and power-strain concerns; the moratorium is framed as not formally targeting Servistar's existing 2021 approvals.

Michigan

20 contested · 4 in court · 4.4 GW planned

  • Stargate The Barn CampusIn litigationSaline Township · OpenAI / Oracle / Related Digital · Under construction · 1.4 GW

    Settled; project proceeding with community benefits package.

  • Hyperscale Data Dowagiac CampusIn litigationDowagiac · Hyperscale Data, Inc. · Under construction · 340 MW

    Pending, U.S.

  • Gibraltar Data Center (former McLouth Steel site)In litigationGibraltar · Raeden (with Cal Realty / Ferragon Corp.) · Proposed · 100 MW

    Gibraltar City Council passed a one-year data-center moratorium on 2026-03-09, after Raeden had already submitted its application.

  • Dafter Township Bitcoin MineIn litigationDafter · Odessa Partners · Operating

    Lake Superior Academy, a school directly across the street, filed suit in July 2025 seeking a preliminary injunction, noise reduction and at least $25,000 in damages; a judge issued a temporary restraining order requiring the mine to shut down during the litigation, and the parties were in mediation as of the source.

  • Allen Park Data CenterOpposedAllen Park · Solstice Data · Cancelled · 26 MW

    The planning commission voted 7-2 on 2026-06-04 to deny the site plan after postponing the decision three times, citing needed zoning-ordinance revisions, missing information and inadequate engineering studies, and a sound study that failed to demonstrate noise mitigation.

  • Howell Township Hyperscale Data CenterOpposedHowell · Stantec Consulting Michigan / Randee LLC · Cancelled

    The Howell Township Planning Commission voted against recommending the rezoning after a seven-hour meeting on 2025-09-23; the Livingston County Planning Commission voted against the project on 2025-11-19; the township board passed a six-month data-center moratorium on 2025-11-20.

  • Kalkaska GoOpposedRocklocker LLC · Cancelled

    A Nov 17, 2025 community forum drew organized opposition over noise, water use, and industrializing public state land; project personnel reportedly received anonymous threats (upnorthlive, WKAR-syndicated coverage).

  • Thor Equities Augusta Township Data Center (Form8tion)OpposedAugusta Township · Thor Equities · Cancelled

    Opposition ran the full course: the Planning Commission recommended denial 5-1 (2025-06), the Board of Trustees approved the rezoning anyway (2025-07), residents gathered 957 signatures to force a referendum (2025-08), and the rezoning was overturned at the ballot on 2026-08-04 by roughly 90% of voters.

  • U-M / Los Alamos Research Computing CenterOpposedYpsilanti · University of Michigan (with Los Alamos National Laboratory) · Proposed

    Ypsilanti Township has passed resolutions against the project and encouraged a year-long pause on data center approvals.

  • Washington Township Technical CampusOpposedWashington · Prologis · Cancelled

    The proposal drew months of discussion and protests from Washington Township and neighbouring residents.

  • Wixom Road Data Center CampusOpposedWixom · Wixom Industrial One / Sansone Group · Proposed

    City council unanimously rejected the developer's request to lift a data-center moratorium early, calling it 'unreasonable as it relates to the potential health, safety, and welfare impacts in the city.' The source reports that during roughly 90 minutes of public comment no speaker expressed support, with concerns centred on proximity to schools, day cares and homes.

  • Alterra Marshall Technology & Energy CenterContestedMarshall · Alterra Development · Proposed · 1.4 GW

    City of Marshall reworking noise ordinances ahead of the project; public concern over noise, emissions, and impact on Stuart Lake and an adjacent city-owned nature preserve.

  • Project CannoliContestedVan Buren Township · Google · Proposed · 1 GW

    Planning commission gave preliminary approval (Feb 2026) for a substation/switching station; full Board of Trustees approval still pending.

  • Metrobloks Southfield Data CenterContestedSouthfield · Metrobloks · Permitted · 100 MW

    Majority of public speakers opposed at the Dec 16, 2025 council hearing ('too many unknowns' -- Council President Charles Hicks); approved anyway 5-2.

  • Buick City Data CenterContestedFlint · Hillwood-Sterling · Proposed

    Flint City Council passed a one-year moratorium on data-center permitting, site plans and construction on June 8, 2026, explicitly while the city studies the issue; WNEM's coverage names the Buick site as one of several under discussion but does not itself name a developer or a filed application.

  • Grand River Power Company Smithville Bitcoin MineContestedEaton Rapids · Grand River Power Company · Operating

    Neighbours reported an all-day high-pitched noise once the facility became operational.

  • Mason / Vevay Township Data Center (unnamed developer)ContestedMason · Undisclosed developer (represented by Dykema Gossett PLLC) · Proposed

    Tax-sharing negotiations between Vevay Township and the City of Mason broke down, with township officials rejecting an offer reported at at least $1 million per year for 30 years; landowners then moved to petition the Michigan State Boundary Commission to annex the site into the city.

  • Microsoft Dorr Township Data CenterContestedDorr Township · Microsoft · Proposed
  • Microsoft Gaines Township Data CenterContestedGaines Township · Microsoft · Proposed
  • Project FlexContestedLyon Township · Verrus (Sidewalk Infrastructure Partners) · Proposed

    Developer (via counsel) threatened injunctions/damages after the township denied a stormwater easement; a $10M community-benefits offer was floated July 2026.

Minnesota

6 contested · 2 in court · 1 GW planned

  • Google Hermantown Data CenterIn litigationHermantown · Google · Proposed · 600 MW

    Two lawsuits are pending against the City of Hermantown: an environmental review challenge by the Minnesota Center for Environmental Advocacy and Stop the Hermantown Data Center (St.

  • Google Project Skyway (Pine Island)In litigationPine Island · Google · Proposed
  • Nobles County Powered Data ParkOpposedWorthington · Geronimo Power (Brookfield Asset Management subsidiary) · Proposed · 400 MW

    Nobles County Board rejected the requested zoning change (~June 2026); no confirmation found of the developer abandoning or appealing the project, so status is recorded as proposed pending further news rather than presumed cancelled.

  • Apple Valley Technology Park (Oppidan/Rockport)OpposedApple Valley · Oppidan Investment Company · Cancelled

    City council unanimously rejected the project 2026-03-26, following the planning commission's denial recommendation, citing conflicts with the city's Comprehensive Plan and inability to fund required water-treatment expansion.

  • Revolve Labs Moose Lake (withdrawn)OpposedMoose Lake · Revolve Labs · Cancelled

    Residents objected at public hearings on two main grounds: noise from the fans used to cool the computing equipment, and the environmental impact of the facility's electricity use.

  • Revolve Labs Windom (withdrawn)OpposedWindom · Revolve Labs · Cancelled

    Roughly 100 residents attended an August 2024 public hearing to object, most commonly over noise pollution and effects on home property values.

Mississippi

3 contested · 1 in court · 3 GW planned

  • xAI SouthavenIn litigationSouthaven · xAI · Operating · 2 GW

    Pending, U.S.

  • AWS Project Atlas, Madison County Mega Site (Canton)ContestedCanton · Amazon Web Services · Under construction · 1 GW

    Canton neighbors report dust, noise and air-quality effects and say they were not consulted; the Southern Environmental Law Center has raised ambient-air-standard concerns over the 700+ diesel generators.

  • Prado AI / PraCon Global AI Industrial CampusContestedRidgeland · PraCon Global Investment Group · Proposed

    Not a residents-vs-site dispute: the documented opposition is regulatory and commercial.

Missouri

6 contested · 4 in court · 3.1 GW planned

  • Google Project Spade CampusIn litigationNew Florence · Google · Under construction · 1.2 GW

    County commissioners unanimously approved; opposition group Preserve Montgomery County filed a Missouri Sunshine Law lawsuit against the commissioners (Feb 2026).

  • Nebius AI Factory (Independence)In litigationIndependence · Nebius Group · Under construction · 1.2 GW

    Reported filed in Jackson County Circuit Court; temporary restraining order reported sought.

  • Festus Data Center CampusIn litigationFestus · CRG (Clayco) · Permitted · 600 MW

    Pending, filed April 2026.

  • Armory Innovation District Data CenterIn litigationSt. Louis · Contour / TerraWatt (with Steadfast City, THO Investments, ARCO, Lewis Rice) · Permitted · 120 MW

    Pending, filed August 28, 2026, St.

  • AWS Project Green CampusContestedNew Florence · Amazon Web Services · Under construction

    Preserve Montgomery County LLC (coalition of local residents, farmers, and business owners) filed a 10-count lawsuit in February 2026 alleging Missouri Sunshine Law violations, specifically that county commissioners conducted negotiations in closed sessions and signed NDAs with Amazon.

  • Project Butterfly (former Emerson campus)ContestedFerguson · SSL Investments / Next Revolution Technologies · Proposed

    No lawsuit filed.

Montana

1 contested · 0 in court

Nebraska

4 contested · 0 in court · 2.8 GW planned

  • Jigowatt Stanton Bitcoin MineOpposedStanton · Jigowatt · Operating · 70 MW
  • ArchGreen Doniphan Data Center (proposed)OpposedDoniphan · ArchGreen Infrastructure · Proposed

    Ten people attended the Oct.

  • Sagebrush Hallam Hyperscale Campus (proposed)ContestedHallam · Sagebrush Infrastructure Partners · Proposed · 1.7 GW

    Thirteen landowners signed purchase options between December 2025 and mid-March 2026; a farmer who declined said the project "caused a bunch of division in the community among neighbors" and objected to turning Hallam from "a small, sleepy farming community" into "an industrial center." Lancaster County commissioners were separately weighing a 12-month data-center moratorium in August 2026.

  • Google Nebraska AI Campus (proposed)ContestedGoogle · Proposed · 1 GW

    Otoe County commissioners passed a one-year moratorium on new data-center permits (May 2026), with the board chair describing sentiment as '50/50'; the Gage County planning commission unanimously recommended an 18-month moratorium (June 2026) to applause.

Nevada

7 contested · 0 in court · 1.6 GW planned

  • Monarch Data CenterOpposedYerington · Copia Power · Permitted · 1 GW

    Nearly 300 people attended the August 2026 commission meeting, a strong majority speaking in opposition.

  • Townsite Solar 2 Boulder City Data CenterOpposedBoulder City · Townsite Solar 2 LLC · Proposed · 167 MW

    Public pushback in Boulder City preceded the applicant's withdrawal of its application for the city-owned parcel on July 6, 2026.

  • Manse Technology CampusOpposedPahrump · Manse Technology Campus LLC · Proposed

    Residents packed a July 2026 Nye County town hall and a subsequent county forum to object; a public petition opposing the project is circulating.

  • Fleet Data Centers Storey County Campus (South Valley & Peru Ridge)ContestedMcCarran · Fleet Data Centers · Under construction · 400 MW

    The Sierra Club Toiyabe Chapter said behind-the-meter self-generation locks the public out of the regulatory process by reducing oversight; Storey County officials described the arrangement as a new development for industrial power generation at the Tahoe Reno Industrial Center.

  • Microsoft Silver Springs Data Center CampusContestedSilver Springs · Microsoft · Proposed

    Nearby property owners objected at the Lyon County Planning Commission over proximity to residential land, structure heights of up to roughly 150 feet, noise and notice.

  • Microsoft Victory Logistics District CampusContestedFernley · Microsoft · Proposed

    Lyon County commissioners approved a 6-month countywide moratorium (Resolution 12-26, effective through Jan 22, 2027) on July 23, 2026 that halts receipt/review/hearing/granting of new data-center applications, amid a wave of county data-center controversy.

  • Switch LAS 19ContestedEnterprise · Switch · Permitted

    The Enterprise Town Advisory Board recommended denial, and Sierra Club and environmental-justice advocates opposed the project at the June 2026 hearing, citing grid strain from AI-driven data center growth.

New Jersey

3 contested · 0 in court · 550 MW planned

  • Nebius Vineland Data CenterContestedVineland · Nebius Group · Operating · 300 MW

    Voluntarily dismissed without prejudice, June 19, 2026 (filed May 26, 2026).

  • CoreWeave NEST CampusContestedKenilworth · CoreWeave · Under construction · 250 MW

    The mayor backs the project as filling the economic gap left by Merck's departure, and CoreWeave is New Jersey-based.

  • Andover HPC Data Center (former Newton Airport Site)ContestedAndover · Andover HPC Development · Proposed

    Residents allege two ordinances (Sept 2025, April 2026) were illegally tailored to benefit a single developer.

New Mexico

5 contested · 0 in court · 3.1 GW planned

  • Green Data Socorro CampusOpposedSocorro · Green Data (Green Data Centers) · Cancelled · 2 GW

    Months of opposition from ranchers and environmentalists; petitions drew thousands of signatures and Socorro County commissioners unanimously adopted a one-year data center moratorium on June 9, 2026.

  • Atterix Raton Advanced Digital HubOpposedRaton · Atterix LLC · Proposed · 50 MW

    More than 100 residents organized as 'Protect Our Resources' to press city leaders to stop or slow the project, citing noise and light pollution and water and electricity use in a town of about 6,000; the City Commission has been weighing a temporary data center moratorium.

  • Green Data Spaceport America Data CenterOpposedGreen Data / Aetherion Inc. · Cancelled · 5 MW

    Residents organized as 'Project Consequences'; the Sierra County Commission unanimously converted a resolution into an 18-month data center moratorium on July 21, 2026.

  • Stargate Project JupiterContestedSanta Teresa · OpenAI / Oracle / STACK Infrastructure · Under construction · 1 GW

    The NM Environmental Law Center sued the Doña Ana County Commission over the incentive approval; Sunland Park City Council asked for a postponement; the commission approved 4-1 amid audience opposition.

  • WestBlock Capital Bitcoin Mine (Shiprock)ContestedShiprock · WestBlock Capital · Cancelled · 15 MW

New York

13 contested · 3 in court · 3.5 GW planned

  • Digihost / Digi Power X, Fortistar North TonawandaIn litigationNorth Tonawanda · Digihost (Digi Power X) · Operating · 120 MW

    Pending, U.S.

  • Greenidge GenerationIn litigationDresden · Greenidge Generation · Operating · 106 MW

    Three years of litigation between NYSDEC and Greenidge over the Title V air permit renewal (denied 2022, overturned by state Supreme Court November 2024) ended in a November 2025 settlement.

  • American Bitcoin, Niagara Falls ("Alpha Site")In litigationNiagara Falls · American Bitcoin (Hut 8) · Operating · 50 MW

    The site (operated as US Bitcoin Corp before the Hut 8 merger) was shut down by a state Supreme Court justice who found the operators in contempt of a prior court order over noise.

  • Treetop East Fishkill Data Center (proposed, no application filed)OpposedEast Fishkill · Treetop Development · Proposed · 1 GW

    The East Fishkill Town Board "voted unanimously to pass" a three-year moratorium on data centers on June 25, 2026, following organised resident opposition; advocacy groups have used the fight to campaign for a statewide Responsible Data Center Development Act.

  • STREAM U.S. Data Centers at STAMPOpposedAlabama · Stream U.S. Data Centers LLC · Proposed · 500 MW

    Organized, documented opposition.

  • TeraWulf AI Data Center Campus, LansingOpposedLansing · TeraWulf · Proposed · 400 MW

    19,700-signature petition (17,000 from NY state) submitted to Lansing Town Board.

  • Ranalli Lysander Data CenterOpposedLysander · Ranalli · Proposed · 300 MW

    Gov.

  • North Country Collocation Services Massena Data Center (former Reynolds site)ContestedMassena · North Country Collocation Services (NCCS) · Proposed · 635 MW

    NCPR reports "about 80 people" attended the May 21, 2026 planning board meeting, that "some shouted their opposition and questions from the audience," and quotes a resident of Akwesasne (the Mohawk territory less than two miles from the site) asking for more community engagement.

  • Riverview Innovation & Technology CampusContestedTonawanda · Riverview Innovation & Technology Campus · Proposed · 300 MW

    Hundreds of residents packed a June 3, 2026 Town of Tonawanda Planning Board meeting to oppose the project; concerns included cooling-system noise, comparisons to the Love Canal environmental disaster, and grid-strain concerns raised by Clean Air Coalition board chair Jim Jones.

  • Brookhaven Digital Infrastructure Facility (WF Industrial / Wildflower, Yaphank)ContestedYaphank · WF Industrial (Wildflower) · Proposed · 176.6 MW

    Sits on a 71-acre site holding three existing empty warehouses, west of Sills Road on the north side of the LIE North Service Road, ~1,000 feet from a residential neighborhood.

  • Blockfusion Niagara Falls Facility (North East Data)ContestedNiagara Falls · Blockfusion · Operating · 100 MW

    A 2021 transformer explosion and an Oct 2022 city cease-and-desist over zoning forced a shutdown; a 2025 zoning amendment plus Niagara Falls Planning Board site-plan approval let it resume.

  • Eco-Yotta Data Center (proposed, County Route 9)ContestedOneonta · Eco-Yotta Inc. · Proposed

    Town of Oneonta (Otsego County) Town Board unanimously passed a one-year moratorium on data centers/crypto facilities on 2026-05-13, in direct response to Eco-Yotta Inc.'s application to rezone the County Route 9 parcel to a Planned Development District.

  • JPMorgan Chase Data Center, OrangeburgContestedOrangeburg · JPMorgan Chase · Operating

    Rockland County IDA approved a roughly $77M sales-tax-exemption package (construction materials/equipment) on 2024-02 for an existing-facility expansion (the facility began construction in 2017 and is already operational), promising exactly one new permanent job; JPMorgan Chase will pay ~$600,000/year in PILOT payments through 2044.

North Carolina

16 contested · 1 in court · 2.4 GW planned

  • Project Delta Data Center, Stokes CountyIn litigationWalnut Cove · Undisclosed (rezoning applicant: Engineered Land Solutions) · Proposed

    Pending, Stokes County Superior Court (filed March 12, 2026).

  • Project Accelerate, Matthews (East John Street)OpposedMatthews · Crosland Southeast · Cancelled · 600 MW

    A petition against the project gathered more than 2,700 signatures; residents raised noise, power, water and neighborhood-character concerns.

  • Natelli New Hill Digital CampusOpposedNew Hill · Natelli Holdings · Cancelled · 300 MW

    Developer withdrew its annexation/rezoning application on March 5, 2026 after months of organized Apex-area opposition (Protect Wake County Coalition citing noise, air-quality, and water-use concerns); an Apex town council member then proposed a one-year moratorium on new data-center applications in the town.

  • Cumberland County commissioners held a public hearing on a proposed data-center moratorium (2026-05-18) at which 21 speakers spoke in favor of a temporary ban, citing PFAS contamination from cooling systems, grid/water-infrastructure stress, farmland/ecosystem impact, rising residential electricity rates, and broken past job-creation promises.

  • Flexential Salisbury (Henderson Grove Church Road)OpposedSalisbury · Flexential · Proposed · 55 MW

    More than 90 residents attended an April 2026 town hall on the proposed Henderson Grove Church Road data center, submitting written concerns ranging from demanding the project be stopped to questions about power/water demand and emergency response; advocacy group Down Home North Carolina criticized the meeting format.

  • Long Ferry Road Data Center Campus (Rowan County)OpposedUndisclosed developer · Proposed

    More than 100 residents spoke in support of a county-wide data center moratorium, driven largely by this project.

  • PrimeBlock Murphy Bitcoin Mine (Harshaw Road)OpposedMurphy · PrimeBlock · Operating

    Neighbors describe a constant hum audible up to a mile away; residents say the operation arrived with no notice.

  • Radius DC Raleigh IOpposedRaleigh · Undisclosed (annexation petitioner: Radius DC Raleigh I) · Proposed

    More than 100 people signed up to comment on the annexation; of 32 registered speakers, 30 opposed.

  • Compass Statesville CampusContestedStatesville · Compass Datacenters · Proposed · 500 MW

    Statesville City Council voted 8-0 to approve the rezoning (Sept 16, 2025) after a roughly two-hour public hearing where 17 residents spoke against the project versus 5 in favor; the Planning Board had likewise recommended approval at an earlier hearing packed with vocal opposition.

  • Digital Realty Moores Chapel Data Center CampusContestedCharlotte · Digital Realty · Permitted · 400 MW

    Charlotte City Council approved the rezoning 7 to 4 in May 2025 over environmental and neighborhood objections (an earlier rezoning of the same parcel drew a ~1,300-signature petition), and metro-wide data-center pushback is intensifying, a comparable Matthews project was withdrawn in Oct 2025 after opposition.

  • PowerHouse Charlotte CampusContestedCharlotte · PowerHouse Data Centers · Under construction · 300 MW

    As of an August 2023 report, Charlotte city staff declined to endorse the project over noise concerns, and Councilmember LaWana Slack-Mayfield said the industrial-scale use 'should be in an industrial area, not around residential homes.' Per subsequent 2026-06 reporting (found via search, not independently re-fetched due to a paywall on the primary Axios/DCD pieces -- treat this paragraph as lower-confidence than the quoted evidence below): Charlotte enacted a 150-day, city-wide moratorium on new data-center construction (around 2026-06-09) to study infrastructure/noise/environmental impact, and PowerHouse Charlotte's first phase was reported as EXEMPT from that moratorium because it already had substantial investment committed.

  • American Tower Reedy Creek Data Center (East Charlotte)ContestedCharlotte · American Tower · Proposed

    Residents protested outside the Charlotte-Mecklenburg Government Center and said they received no direct communication about the project; the petitioner deferred the public hearing to allow more community engagement.

  • Microsoft Person County Mega ParkContestedRoxboro · Microsoft · Permitted

    Advocacy group Clean Water for NC organized a petition and community meeting (Sept 2025) after commissioners said Microsoft had shared no official plans; at a Microsoft-hosted community meeting in June 2026.

  • Natelli Vance County Campus (proposed)ContestedHenderson · Natelli Investments · Proposed
  • Rural Hall Data Center (The Drox Group)ContestedRural Hall · The Drox Group · Cancelled

    Rezoning case F-1669, 129 acres across from Rural Hall Town Hall.

  • Terra Nexus Custer Avenue Data Center (Fayetteville)ContestedFayetteville · Terra Nexus Ventures · Proposed

    The Eastover Town Council wrote to Fayetteville officials opposing the project; residents organised locally around noise, water demand and the diesel generator count.

North Dakota

4 contested · 1 in court · 1.4 GW planned

  • Atlas Power Data Center (Williston)In litigationWilliston · Atlas Power · Operating · 700 MW
  • Applied Digital Polaris Forge 3ContestedHanover · Applied Digital Corporation · Proposed · 430 MW

    Oliver County commissioners enacted, then repealed, a 180-day countywide data-center moratorium (approved ~June 2026, repealed by July 10, 2026) amid resident concerns raised at public meetings.

  • Applied Digital Polaris Forge 2ContestedHarwood · Applied Digital Corporation · Under construction · 280 MW

    Opposition surfaced when the project was announced (Aug 2025): environmental advocates and at least one area farmer argued Minnkota Power Cooperative member-owners (farmers, ranchers, rural residents) could see higher electric rates from the substation/powerline buildout funded to serve the data center; one resident called for a moratorium to allow more planning time.

  • Enerfore Pleasant Valley Data CenterContestedTioga · Enerfore Digital · Under construction · 30 MW

Ohio

25 contested · 4 in court · 5.5 GW planned

  • Bitdeer Clarington HPC/AI CampusIn litigationClarington · Bitdeer · Under construction · 570 MW

    American Heavy Plate Solutions LLC (a neighboring tenant leasing 9.9 of the 100-acre Hannibal Industrial Park) sued Bitdeer subsidiaries (Erie Creek LLC, Whitetail Creek LLC, Bitdeer Inc.) and the Monroe County Port Authority in the Court of Common Pleas of Monroe County, OH (disclosed in Bitdeer's SEC Form 6-K, Feb 2 2026), seeking declaratory and injunctive relief over a restrictive covenant in AHP's 2018 lease; Bitdeer says it will 'vigorously defend' and that construction/power timing 'may be affected.'

  • Amazon Web Services Wilmington Data Center CampusIn litigationWilmington · Amazon Web Services · Proposed

    Pending, U.S.

  • Bristolville 25In litigationLordstown · Bristolville 25 Developer LLC / BHGH Properties · Proposed

    Lordstown Village Council voted 6-0 (Nov 3) to ban future data centers effective Dec 3; the developer (Bristolville 25 Developer LLC / BHGH Properties, whose Oct 20 site-plan submission predated the ban) petitioned the Ohio Supreme Court for a writ of mandamus to compel the village to process its application.

  • Project DazzlerIn litigationFranklin Furnace · Google · Permitted

    A Scioto County resident sued the county commissioners in Common Pleas Court alleging Ohio Open Meetings Act violations (closed executive sessions) in negotiating the Community Reinvestment Area tax agreement tied to the Google project; the suit followed documented resident pushback at a township meeting.

  • East 55th Street Data Center (Slavic Village)OpposedCleveland · Lakeland Equity Group · Cancelled · 150 MW

    Mayor Justin Bibb's administration rejected the building permit on May 14, 2026; a city spokesperson cited serious concerns about hyperscale, standalone data centers in neighborhoods, and City Council was concurrently weighing a moratorium.

  • Ashville CampusOpposedAshville · EdgeConneX · Proposed

    Peremptory writ granted for relators, Ohio Supreme Court, August 7, 2026; referendum reported set for the November 3, 2026 ballot.

  • PRSM Preble County Data Center CampusOpposedMonroe Township · PRSM Group · Cancelled

    The Preble County Planning Commission rejected the rezoning 11-0 and the Rural Zoning Commission 5-0; residents raised electricity-cost and water-supply concerns.

  • Saadia Holding Athens-Dover Township Data CenterOpposedThe Plains · Saadia Holding LLC · Proposed

    Athens Township trustees (Aug 1, 2026), Athens City Council (Aug 3, 2026) and the Athens County commissioners (Aug 4, 2026) each adopted one-year data center moratoria after residents packed July 28 meetings.

  • SR-14 Data Center Proposal (Ravenna)OpposedRavenna · Ray Harner (landowner-developer) · Proposed

    Ravenna City Council's planning committee moved to impose a one-year citywide data center moratorium after public opposition; the moratorium was adopted April 20, 2026.

  • AWS Project Galaxy, Sidney, OHContestedSidney · Amazon Web Services · Under construction · 1.5 GW

    Active opposition from 'Sidney Citizens for Responsible Development' (founded by Kristin Allen, 4th-generation farm family) and 'Sidney Citizens Data Center Watch' (150+ Facebook members).

  • AWS Sprigg Township Data Center Campus (Buck Canyon)ContestedManchester · Amazon Web Services (land held via Buck Canyon Properties) · Permitted · 1.3 GW

    Sprigg Township passed a 12-month data center moratorium (2026-02-26) after residents learned of the project; a resident-founded group (Conserve Ohio) is pushing a statewide ban on large-scale data centers, citing rising electricity costs and water/environmental concerns.

  • Bitdeer Shalersville Data Center CampusContestedShalersville Township · Bitdeer · Proposed · 750 MW

    Standing-room-only town hall meetings; local opposition coverage from Kent Stater and The Portager.

  • Oregon Industrial Park Data Center CampusContestedOregon · Capacity LLC (Vantage Data Centers named as prospective developer) · Proposed · 500 MW

    A citizen group ('United Neighbors of Oregon') is petitioning to force a November 2026 public referendum on the project.

  • Prologis Project MilaContestedTrenton · Prologis · Permitted · 250 MW

    Trenton Planning Commission approved the site plan in a ~10-minute meeting (Mar 30, 2026) taking no public questions despite ~30 residents expecting a hearing; a 500+-member opposition group (W.A.T.E.R.) is petitioning for a Butler County charter amendment to ban data centers over 25MW.

  • Bitdeer Massillon FacilityContestedMassillon · Bitdeer · Operating · 221 MW

    Local opposition petition ("BitDeer Bitmine in Massillon" nuisance petition) circulated via MoveOn; a Massillon city council vote reportedly allowed the project to proceed, though the source for that vote could not be independently fetched/verified this session.

  • Aligned Data Centers, PataskalaContestedPataskala · Aligned Data Centers · Cancelled · 200 MW

    Sustained resident opposition: rallies at City Hall and a citizen petition drive.

  • Cologix COL5ContestedLewis Center · Cologix · Under construction · 75 MW

    The Ohio Tax Credit Authority approved Cologix COL5's $42.3M tax exemption on 2026-06-02, days after Gov.

  • Ardent Technologies Wilmington Data CenterContestedWilmington · Ardent Technologies · Proposed

    Wilmington City Council rezoned the 500 acres on a 5-2 vote on February 19, 2026; one council member urged slowing the process and opponents said they were organizing a ballot-referendum legal challenge.

  • AWS Cosgray Road CampusContestedHilliard · Amazon Web Services · Operating

    Hilliard has asked AEP and Bloom Energy to install carbon-capture technology, citing an air permit that allows emissions of up to 1.45 million pounds of CO2 per day, and the air permit is in administrative-court litigation.

  • AWS Trenton / Madison-St. Clair Township CampusContestedTrenton · Amazon Web Services · Proposed

    Madison Township and St.

  • Hamilton Innovation CenterContestedHamilton · Logistix Property Group · Proposed

    Organized resident opposition on environmental, health, and energy-cost concerns documented since at least fall 2025; the project's power-delivery shortfall (240 MW requested vs.

  • Hanging Rock / Haverhill Data CenterContestedHanging Rock · Strata Expense (backed by Supermicro + Ravel) · Under construction

    A 5,178-signature opposition petition sparked a moratorium push in neighboring Ironton; construction is proceeding.

  • Mount Orab Mega-Site Data Center CampusContestedMount Orab · DB Stu LLC · Proposed

    The mayor and village council members signed nondisclosure agreements before residents learned of the project; council member Eric Lang rescinded his NDA and on February 3, 2026 introduced ordinances for 180-day data center and small-modular-reactor permit moratoria plus a permanent ban on commercial nuclear facilities.

  • Project KlondikeContestedPiqua · Meta · Permitted

    Approved Nov 2025 (emergency resolution under NDA) but drew an opposition petition with 2,500+ signatures.

  • Whitetail Creek Data CenterContestedNiles / Weathersfield Township · Bitdeer · Proposed

    Niles City Council halted annexation talks April 20, 2026 after community backlash; no formal petition, zoning, or building-permit application was ever filed with the city.

Oklahoma

6 contested · 0 in court · 1.5 GW planned

  • Cloverleaf Project Open SkyContestedPiedmont · Cloverleaf Infrastructure · Proposed · 1.5 GW

    Piedmont Planning Commission recommended the City Council DENY the 'Project Open Sky' PUD rezoning pending additional information; Council vote rescheduled to late July 2026, approval not yet granted as of this writing.

  • Beltline Energy Piedmont SiteContestedPiedmont · Beltline Energy · Proposed

    Residents packed Piedmont's Planning Commission meeting over competing data-center proposals; the BLE Landholdings/Beltline vote was deferred (June 1, 2026) for further comprehensive-plan review, the same night a sibling proposal (Cloverleaf) was recommended for denial.

  • Fluidstack Okmulgee County Data CenterContestedOkmulgee · Fluidstack · Proposed

    Residents voiced distrust over transparency and raised water, property-value, public-health and electricity concerns at a July 2026 open house; the county commission established a citizen advisory planning committee on data centers.

  • Google Stillwater Data Center CampusContestedStillwater · Google · Under construction

    All local taxing jurisdictions approved the 25-year incentive agreement, but Payne County Commissioner Rhonda Markum cast the lone dissenting vote, citing water and transparency concerns (officials were required to sign NDAs before learning project details).

  • Meta Project Anthem, TulsaContestedTulsa · Meta · Under construction

    Tulsa City Council passed a 9-month moratorium on new data centers in March 2026 to evaluate ecological impact; Project Anthem was carved out as it was approved before the moratorium vote.

  • Project Spring (Sand Springs)ContestedSand Springs · Google · Proposed

    Protect Sand Springs Alliance filed an annexation-challenge lawsuit (Jan 2026); Land Legacy filed a conservation-easement enforcement suit (Mar 2026) covering 270 of the 827 acres; a recall petition targets the City Council and mayor; Osage Nation raised mineral-estate sovereignty and consultation concerns.

Oregon

5 contested · 0 in court · 126 MW planned

  • Roundhouse Cascade Locks Data CenterOpposedCascade Locks · Roundhouse Digital Infrastructure · Cancelled · 30 MW

    Local opposition, including the successful recall of two officials who had approved the deal, preceded the Port of Cascade Locks' decision to cancel, with concerns centred on utility rate increases.

  • Boxminer La Pine Bitcoin Mining FacilityOpposedLa Pine · Boxminer (Hidden Pines LLC) · Cancelled · 20 MW

    Roughly five hours of public comment preceded a unanimous La Pine City Council vote against the project on 27 May 2026; residents cited power draw, noise, light and the small-town character of the city.

  • Google The Dalles Data Center CampusContestedThe Dalles · Google · Operating · 300 MW

    Settled December 14, 2022, Wasco County Circuit Court.

  • Crane PDX01ContestedForest Grove · Crane Data Centers · Under construction · 76 MW

    Two-round appeal fight: planning staff approved (July 2024); a resident appeal was denied by the Planning Commission (4-2, Sept 3, 2024); a further appeal was denied by City Council (5-0, Oct 14, 2024).

  • CoreSite Hillsboro Data Campus (HI1/HI2)ContestedHillsboro · CoreSite · Proposed

    Neighbouring property owners filed letters of concern over Oregon white oak removal via a fee-in-lieu buyout, wetland and greenway encroachment, and the 92-foot four-storey Phase 2 building.

Pennsylvania

20 contested · 7 in court · 9.6 GW planned

  • TECfusions Keystone ConnectIn litigationUpper Burrell Township · TECfusions · Proposed · 3 GW

    Upper Burrell Township passed a 180-day data-center moratorium in May 2026, but it did not apply to permits already granted to TECfusions for 'Building J', and supervisors approved a land development plan for that building on Aug.

  • Gouldsboro Data Center Campus (Project Gold)In litigationClifton Township · 1778 Rich Pike LLC · Proposed · 1.5 GW

    Clifton Township supervisors unanimously approved a zoning settlement with the developer on January 3, 2026 after the developer appealed a zoning board decision on November 26, 2025; residents said they plan to take the supervisors to court.

  • Sentinel East Whiteland Data CenterIn litigationEast Whiteland Township · Sentinel Data Centers · Under construction · 300 MW

    Original 2018/2024 zoning and final-plan approvals are being challenged; a court called one challenge 'frivolous' (June 2026).

  • Pennhurst Data Center CampusIn litigationSpring City · Penn Hurst Holdings · Proposed

    East Vincent Township supervisors unanimously rejected the conditional-use application on 2026-05-21; developer appealed on 2026-06-26 to the Chester County Court of Common Pleas.

  • Powder Mills Data Center CampusIn litigationStonebridge Associates · Proposed

    North Beaver and Mahoning townships amended their ordinances to impose stricter data-center regulations; Stonebridge has separate lawsuits pending against both townships disputing whether its plans were filed before those ordinance changes took effect (as of July 2026).

  • Project HazelnutIn litigationHazle Township · NorthPoint Development (NP Hazleton Holdings 1 LLC) · Proposed

    Hazle Township denied NorthPoint's land development application; NorthPoint is appealing in Luzerne County Court of Common Pleas and created a $30M fund to offset potential short-term utility rate increases for residents during the appeal.

  • Triboro Industrial Park / Triboro Commerce ParkIn litigationJessup / Olyphant · Ercor Triboro LLC (Sansone Group) · Permitted

    Triboro Commerce Park LLC sued Olyphant Borough after the council moved to invalidate zoning covering the site; the council later voted unanimously to settle via a stipulation that a community group said effectively conceded what a judge would likely have ruled for the developer anyway.

  • Limerick Township Data Center Campus (MCD 7)OpposedLimerick Township · MCD 7 LLC · Proposed · 750 MW

    Limerick Township's Board of Supervisors voted on Jan.

  • Application drew heavy opposition from residents and business owners at the Plymouth Township Zoning Board hearing (June 2026).

  • Renaissance Park and Innovation Data Center CampusOpposedKing of Prussia · MLP Ventures · Proposed

    At the July 23, 2026 Upper Merion planning commission meeting the vast majority of the crowd stood when asked who opposed the project; opposition has grown since the late-May 2026 unveiling.

  • South Annville Township Data Center Campus (withdrawn)OpposedSouth Annville Township · Inch & Co. / Eastern Land & Resources Co. (1235 Martina Drive Owner) · Cancelled

    A community organizer gathered more than 500 petition signatures, described as roughly one third of the township's adult population.

  • Wildcat Ridge AI Data Center CampusContestedArchbald · Cornell Realty Management · Proposed · 1.6 GW

    The Archbald Neighborhood Association submitted a draft ordinance amendment (Oct 2025) to restrict data centers to a single industrial-zoned site, and residents packed fall-2025 hearings demanding restrictions; the borough council approved the enabling zoning anyway on a divided Nov 24, 2025 vote.

  • PAX, Pennsylvania Digital IContestedCarlisle · PowerHouse Data Centers · Under construction · 1.4 GW

    Middlesex Township supervisors voted 3-0 (Ordinance 3-2025, May 30 2025) to create a 694-acre Data Center Overlay District making data centers a by-right use; Protect Cumberland County PA documents organized opposition over water, pollution, utility rates, and private-well impacts (Rep.

  • Breaker Street Data Center CampusContestedJessup · Breaker Street Associates LLC (Catalyst Commercial Development) · Proposed · 600 MW

    Jessup's zoning hearing board unanimously rejected the developer's appeal; the borough has since adopted an ordinance restricting data centers.

  • CoreWeave Lancaster Data CenterContestedLancaster · CoreWeave · Proposed · 300 MW

    Repurposing two former printing plants drew strong resident opposition (about 20 speakers against, none in favor, at one hearing) and a challenge to the zoning classification that bypassed public hearings; the city is drafting a data-center-specific ordinance.

  • Springdale Data Center (former Cheswick Generating Station)ContestedSpringdale · Allegheny DC Property Co., LLC · Permitted · 180 MW

    Residents raised noise, air quality, water use and grid-reliability concerns at planning commission and council hearings; a Change.org petition against the project gathered more than 300 signatures.

  • Big Beaver CampusContestedBig Beaver · Switch · Proposed

    A packed, heavily police-attended June 2, 2026 town hall drew sustained resident criticism over transparency and the loss of the site's former racetrack; a borough council member's public support for the project drew further accusations that officials weren't listening to residents.

  • Cetronia Road Data Center (former Air Products site)ContestedTrexlertown · Air Products · Cancelled

    Substantial local opposition; proposal went before the Upper Macungie Township zoning hearing board.

  • Muncy Data CenterContestedMuncy · Danko Holdings II · Permitted

    Neighbors on John Brady Drive strongly oppose; township is drafting a data center ordinance and seeking legal counsel.

  • York 2 Energy Center Data CenterContestedPeach Bottom Township · Energy Capital Partners · Proposed

    Township officials advanced a data center ordinance while saying no formal plan had been submitted; residents packed a township workshop objecting that they had heard about the project only through rumours and public statements made outside the community.

Rhode Island

1 contested · 0 in court

  • Hanton City Business Park (data center anchor)OpposedSmithfield · Hanton City Investments LLC · Proposed

    Smithfield Town Council voted 4-1 (May 5, 2025) to amend zoning to list data centers as "not permitted" in all districts; Hanton City Investments filed its application May 4, one day before the vote, preserving pre-ban review (a use variance faces "a pretty high bar").

South Carolina

4 contested · 0 in court · 1.0 GW planned

  • Project Altair (Mid-Carolina Commerce Park II)OpposedProsperity · Undisclosed developer (Project Altair) · Cancelled

    Residents at a packed public hearing objected over water-supply strain, electric-rate increases, industrial noise and loss of the county's rural/agricultural character.

  • Project Liberty (Stream Data Centers, Marion County Industrial Park)OpposedMarion · Stream Data Centers (site entity: Eagle Myra, LLC) · Cancelled

    Marion County Council approved the FILOT/incentive package under NDAs across three readings in January 2026, before residents were publicly informed of the project (then code-named Eagle Myra LLC / Project Liberty).

  • Project BoulderContestedEagle Rock Partners · Proposed · 1 GW

    Facing zoning-appeals opposition and a county moratorium reconsideration.

  • Project Alpaca (Midway Green Industrial Park)ContestedUnion · Volt Edge Energy · Proposed · 49 MW

    Union County Council tabled the first reading of the FILOT ordinance for Project Alpaca on 2026-04-28 and cancelled a May 12, 2026 public hearing after resident concerns raised at a community listening session; council said the project would need to be reintroduced, with a public information forum required before any further tax-agreement decision.

South Dakota

2 contested · 0 in court · 550 MW planned

  • Sioux Falls Technology Park (Gemini Data Center)ContestedSioux Falls · Gemini Data Center SD LLC · Permitted · 500 MW

    The city council approved rezoning unanimously despite hours of opposing public testimony; a citizen petition drive is gathering signatures that could force the rezoning to a public vote.

  • Leola Data CenterContestedLeola · Leola Data Center, LLC · Proposed · 50 MW

    McPherson County's Board of Adjustment deferred action on Leola Data Center's conditional use permit application (confirmed via direct fetch of Aberdeen Insider's report, 2026-09-13; the site's own article text was largely paywalled so the exact hearing date could not be independently confirmed this run).

Tennessee

8 contested · 2 in court · 1.3 GW planned

  • ColossusIn litigationMemphis · xAI · Operating · 1.2 GW

    The NAACP (with SELC and Earthjustice) sued xAI over roughly 35 unpermitted methane gas turbines; the county permitted only 15, and the NAACP/SELC appeal to the Shelby County Air Pollution Control Board stays it.

  • CleanSpark Limestone Bitcoin Mining Facility (closed 2026)In litigationLimestone · CleanSpark, Inc. · Cancelled

    Shut down 2026-03-28 under a 2023 Washington County lawsuit settlement over noise/zoning violations.

  • DC BLOX Nashville (Grassmere Park)OpposedNashville · DC BLOX · Proposed · 50 MW
  • CleanSpark Mountain City Bitcoin Mining FacilityOpposedMountain City · CleanSpark, Inc. · Proposed · 30 MW

    WUOT/LPM (2025-08-15) reports Mountain City leaders courted CleanSpark from February 2025 in closed-door meetings and advanced planning proposals without proper public notice; residents did not learn of the plan until April 2025.

  • Hixson Data Center (McMinnville)OpposedMcMinnville · Hixson Data Center · Proposed · 25 MW
  • Jailhouse Studios (former Hamilton County Jail)OpposedChattanooga · Urban Story Ventures · Proposed
  • Fisk University Quantum Leap Innovation & Technology CenterContestedNashville · Fisk University · Proposed · 30 MW

    Two petitions circulated against the plan within weeks of the May 2026 announcement, one on Change.org with more than 4,200 signatures and another with more than 360, and residents and Fisk alumni spoke against it.

  • Project River Data CenterContestedCleveland · Wright Brothers Construction · Proposed

    Residents packed a Cleveland Planning Commission meeting in August 2026 over a separate, nearly-400-acre Wright Brothers proposal, with much of the concern centred on fears a data center could be developed there.

Texas

15 contested · 4 in court · 15.9 GW planned

  • Project AquilaIn litigationRCM Hill, LLC · Proposed · 1.2 GW

    Hill County's 1-year moratorium (passed 3-2, May 12, 2026) was rescinded June 4, 2026 after RCM Hill filed a $100M federal lawsuit, which remains active seeking damages.

  • MARA Granbury FacilityIn litigationGranbury · MARA Holdings · Operating · 300 MW

    Both suits pending; state case filed Oct 2024, federal case filed May 2026.

  • Fort SpunkyIn litigationPacifico Energy · Proposed · 100 MW

    Approval revoked and now contested via developer lawsuit against Hood County.

  • Barrio Energy Tyler Data Center (West Erwin Street)In litigationTyler · Barrio Energy / Barrio Resources LLC (with Vulcan Core) · Proposed · 12 MW

    Tyler's Planning & Zoning Commission denied Barrio's special-use permit in July 2026; the Zoning Board of Adjustment unanimously rejected a separate, untimely-filed Barrio appeal on 2026-09-03.

  • PowerHouse Caldwell County Data CenterContestedUhland · PowerHouse Data Centers · Proposed · 4 GW

    Substantial pushback reported from residents at an open house.

  • Project Merlin (Helios II)ContestedMcGregor · Galaxy Digital · Proposed · 3.5 GW

    Residents launched a recall petition against McGregor's mayor over the closed-session approval of the ~500-acre Galaxy Digital land sale and aquifer/water-supply concerns; enough signatures were collected by mid-July 2026 to advance the recall to the next phase.

  • Comanche CircleContestedTolar · Sailfish Digital Ventures (SDV) · Proposed · 2 GW

    Local opposition (Protect the Paluxy Valley group, aquifer/water concerns); a Feb 2026 county moratorium vote failed 3-2.

  • Crusoe Victoria AI FactoryContestedVictoria · Crusoe · Proposed · 1.5 GW

    Victoria County Commissioners Court heard organized opposition at a public hearing on the Crusoe/Blue Energy project (wastewater/injection-well concerns) alongside a rally by 'Concerned Citizens for Responsible Development' opposing AI data centers in the area (June-July 2026); no vote reported yet.

  • Meta El Paso AI Data Center CampusContestedEl Paso · Meta · Under construction · 1 GW

    Sembrando Esperanza Coalition and environmental groups oppose the proposed natural gas plant, citing air quality and rate equity concerns.

  • Riot Platforms Corsicana FacilityContestedCorsicana · Riot Platforms · Operating · 1 GW

    Organized local opposition (Concerned Citizens of Navarro County; Change.org petition).

  • Nexus Hubbard Data Center & Power CampusContestedHubbard · Nexus Data Centers · Under construction · 612 MW

    Residents raised property-value, transparency, and drought-era water-use concerns at a Feb 24, 2026 Hill County Commissioners Court tax-abatement hearing; Nexus subsequently withdrew its tax-abatement request.

  • Cipher McLennan HPC Data CenterContestedWaco · Cipher Digital · Proposed · 500 MW

    Riesel residents formed a 'Stop the Riesel Data Center' opposition page and the City Council and a McLennan County commissioner publicly criticized the project's lack of transparency (May 2026); no vote, denial, or lawsuit yet.

  • Telios Quinlan CampusContestedQuinlan · Core Scientific · Proposed · 430 MW

    Core Scientific-hosted town halls and multiple protests over its Hunt County data-center plans (which include the ~260-acre Telios Quinlan One acquisition) drew organized resident opposition on water/noise/air-quality grounds.

  • Project MatadorContestedAmarillo · Fermi America · Under construction

    TCEQ air permit process (for 93 planned gas turbines) drew 279+ public comments, majority opposed.

  • Westline Site / Dove Creek Technology CampusContestedSan Angelo (Tankersley area, unincorporated) · Beacon Data Centers (via Westline TX Holdings) · Proposed

    A proposed 12-month data-center moratorium was rejected by county commissioners; local opposition documented.

Utah

3 contested · 0 in court · 9.3 GW planned

  • Volition Spanish Fork Data CenterOpposedSpanish Fork · Volition Industries · Proposed · 250 MW

    At an Aug 19, 2026 Spanish Fork City Council public hearing, nearly two hours of public comment ran almost unanimously against the project over unverified environmental claims, wildlife/water-resource risk, and proximity to residences; the council tabled the Title 15 zoning amendments the project needs to proceed.

  • Summit Ridge Data CenterOpposedSantaquin · Data Center Power Company · Under construction

    Contested locally.

  • Stratos AI Data Center CampusContestedLucin · O'Leary Digital · Proposed · 9 GW

    Community opposition over fast-tracked MIDA process, CO2 emissions (~34M metric tons/year at full build), light/noise pollution, and Great Salt Lake impacts.

Virginia

25 contested · 4 in court · 4.2 GW planned

  • Tuckahoe Technology ParkIn litigationTract · Proposed · 900 MW

    Tuckahoe is the first project filed under Goochland's new Technology Overlay District, which is itself the subject of an active lawsuit by four residents alleging the county violated state notice requirements when adopting it; the overlay's adoption also drew broader resident backlash.

  • Blackwell Road Data Center (Warrenton)In litigationWarrenton · Amazon Data Services · Permitted · 40 MW

    Awaiting ruling, Fauquier County Circuit Court.

  • Bermuda Hundred Data Center (Old Bermuda Hundred Road)In litigationChester · Undisclosed (landowner: Washington Single Family Fund3) · Proposed

    Chesterfield's 2026 ordinance made data centers a conditional use; the planning director ruled the landowner lacked vested rights to build by-right, and the Board of Zoning Appeals unanimously upheld that denial on 2026-06-03.

  • Birchwood Data CampusIn litigationKing George · Amazon Web Services · Permitted

    Rezoning approved Sept 2023; a vested-rights challenge is contested in circuit court.

  • Hunting Hawk Technology ParkOpposedGlen Allen · HHHunt · Cancelled · 900 MW

    Hundreds of residents from Hanover, Henrico and Goochland attended hearings citing traffic, water use, noise and rural-character impacts.

  • Mountain Road Technology ParkOpposedTract · Cancelled · 900 MW
  • 1500 Gateway Data Center (denied)OpposedFredericksburg · 1500 Gateway LLC (Penzance) · Cancelled

    Fredericksburg City Council voted 7 to 0 to deny the rezoning and 7 to 0 again to deny the special use permit after a public hearing that ran past midnight.

  • Etheridge Lakes Data Center (Great Bridge)OpposedChesapeake · Emerald Lakes Estates (Doug Fuller) · Cancelled

    Chesapeake City Council denied the rezoning; project did not proceed.

  • Prince William Digital GatewayOpposedGainesville · QTS / Compass Datacenters · Cancelled

    Concluded: rezonings void, final appeal withdrawn July 2, 2026.

  • Project Flash (Summit View Business Park)OpposedRocky Mount · Crusoe · Cancelled

    More than 100 residents gathered at the Scruggs Volunteer Fire Department over water, electricity and quality-of-life impacts; residents learned of the project only through FOIA requests and demanded answers from the county.

  • Remington Technology ParkContestedRemington · PointOne Holdings Inc. · Permitted · 600 MW

    Fauquier Planning Commission recommended DENIAL of the project's private power plant 3-2; at the July 10, 2026 Board of Supervisors hearing residents spoke against it and one supervisor cast the sole dissenting vote citing grid strain, but the Board approved it 3-1.

  • Wise Innovation Hub (OASIS)ContestedWise Innovation Hub Venture LLC · Proposed · 600 MW

    Appalachian Voices reports Wise County residents learned of the project in late 2025 through a LinkedIn post rather than official county channels and raised transparency concerns; as of early March 2026 no additional public information was available.

  • Gainesville Crossing Digital Campus (GCDC)ContestedGainesville · Corscale Data Centers (Patrinely / USAA Real Estate) · Under construction · 300 MW

    The Prince William County BOS approved the Gainesville Crossing rezoning (REZ2018-00008) 7-1 on Dec 10 2019 over opposition from the Coalition to Protect Prince William County (Elena Schlossberg: 'Citizens are carrying the burden of the massive infrastructure bills for these energy hogs').

  • 58 East Data Campus (Route 58 East Data Center Campus)ContestedRinggold · Anchorstone Advisors LLC · Permitted

    Pittsylvania BOS approved the rezoning unanimously (July 2024), but residents living near the Ringgold parcel spoke against the project at both the Board and Planning Commission meetings, citing noise and light pollution.

  • Amazon Devlin Technology ParkContestedBristow · Amazon Web Services · Permitted

    Bristow residents organized and challenged rezoning in court unsuccessfully.

  • Convergent Technology ParkContestedRemington · Convergent VA LLC · Proposed

    The Piedmont Environmental Council (PEC), a regional land-use advocacy group, has formally opposed this project since its original 2019 iteration and reiterated concerns in Oct 2024 about the site's proximity to the Town of Remington and flood-risk impact.

  • Cross Mill CenterContestedLeesburg · JK Land Holdings · Permitted

    Four supervisors, Michael Turner, Juli E.

  • Crossroads Technology CampusContestedRCK Digital Crossroads LLC · Proposed

    Actively contested, packed Board of Supervisors / Planning Commission meetings (July 2026).

  • CyrusOne Vint Hill CampusContestedVint Hill · CyrusOne · Proposed

    At a March 2024 Vint Hill Conservancy community meeting devoted largely to the CyrusOne campus, critics said the plans showed 45-foot buildings on elevated ground that would be obtrusive to residents roughly a third of a mile away, while conservancy president Chris Zumot publicly backed the project, telling the Fauquier Times the group "feels for CyrusOne" over county restrictions affecting it.

  • Gigaland Data CentersContestedRemington · Gigaland LLC · Proposed

    Planning Commission reportedly recommended denial (mid-2025); application on hold pending additional information.

  • Potomac Church Technology CenterContestedFredericksburg · Amazon Data Services · Under construction

    Stafford Board of Supervisors deferred (did not approve) the Amazon Potomac Church proffer amendment on June 18, 2026, citing road damage, generator emissions, and water-sharing concerns.

  • Project PeanutContestedChester · Google · Under construction

    Residents packed a June 24, 2026 Chesterfield Board of Supervisors meeting demanding transparency on the three Google projects (Peanut, Skye, Loch; $9B combined); zero speakers voiced support and no developers attended.

  • Project SkyeContestedMidlothian · Google · Permitted

    Same June 24, 2026 packed Chesterfield Board of Supervisors meeting covering all three Google projects (Peanut, Skye, Loch; $9B combined); zero speakers voiced support, residents demanded transparency and are organizing for continued engagement as further proposals advance.

  • Solis Arx Progress Park Data Center CampusContestedMax Meadows · Solis Arx · Proposed

    Residents voiced concerns at county informational sessions over the proposed AI campus.

  • Vint Hill CornersContestedVint Hill · Vint Hill Corners LLC · Proposed

    In May 2024, Fauquier County supervisors voted 4-1 to grandfather the Vint Hill Corners project out of stricter new Vint Hill data-center zoning rules; Supervisor Ike Broaddus, who represents the district, said he remained personally opposed to the project as sited because it would be too close to residences, while Supervisor Regan Washer cast the lone dissenting vote on the exemption agreement.

Washington

3 contested · 0 in court · 2.0 GW planned

  • STACK Infrastructure Goldendale Data CenterOpposedGoldendale · STACK Infrastructure · Proposed · 958 MW

    Yakama Nation members and environmental groups protest the adjacent Goldendale pumped-storage project on the sacred site of Pushpum, which would supply up to 80% of its output to this data center.

  • Rock Point Data Center ProjectContestedWest Plains · Apricus Energy Partners · Proposed · 1 GW

    Developer has little operating history and a prior unrealized project in Livermore, CA; undisclosed discussions between the developer and Spokane County commissioners drew public criticism; a companion Avista MOU (counterparty undisclosed, believed to be this project) was paused June 12, 2026.

  • Blue Fern Cle Elum Data CenterContestedCle Elum · Blue Fern Development · Proposed · 20 MW

    Cle Elum's city council voted unanimously to introduce a six-month data-center moratorium and scheduled a Sept.

West Virginia

3 contested · 0 in court · 2.6 GW planned

  • Ridgeline Data CenterOpposedFundamental Data LLC · Proposed

    Air quality permit for the co-located power plant has been formally appealed by Tucker United, the West Virginia Highlands Conservancy, and the Sierra Club; litigation over jurisdiction was ongoing as of an August 31, 2026 report (advocacy groups seeking WV Supreme Court review).

  • Monarch Compute CampusContestedPoint Pleasant · Nscale · Under construction · 2 GW

    60+ Mason County residents attended March 17, 2026 meeting to organize opposition; concerns over noise, light, water, and CO2 pollution.

  • Bedington CampusContestedPenzance Management · Proposed · 600 MW

    300+ residents packed a Spring Mills High School town hall (March 2026) over water, flooding, eminent-domain, and loss-of-local-zoning-control (HB 2014) concerns, backed by an organized 'No Data Centers in the Eastern Panhandle' Facebook group; no vote has been held yet.

Wisconsin

11 contested · 2 in court · 2.7 GW planned

Wyoming

1 contested · 0 in court · 1.5 GW planned

  • Prometheus Hyperscale Falls Ranch Data Center CampusContestedGlenrock · Prometheus Hyperscale · Proposed · 1.5 GW

    Neighboring landowners mounted "fierce pushback" over noise, heat, fumes, and traffic concerns, prompting developers to weigh relocating to an alternate parcel as of July 2026 (no denial or lawsuit yet).

Questions

How many data centers in the US are facing opposition?

355 sites in the registry carry a documented reception of contested, opposed or in litigation as of September 14, 2026: 62 are or have been the subject of a lawsuit, 111 face organized local opposition without a suit on record, and 182 are under active public debate with hearings or petitions. Sites with no reception on record are not counted, so the true number is higher.

Which state has the most contested data centers?

Ohio, with 25 sites, followed by Virginia (25) and Georgia (20).

What counts as contested?

Reception is a sourced signal from the record, not our judgment. In litigation means a lawsuit related to the site is or has been filed. Opposed means organized opposition is the dominant signal. Contested means hearings, petitions or organized opposition are on record and no suit has been filed. Where our own case files establish a lawsuit, the site is marked in litigation.

How much capacity is contested?

128.8 GW of planned capacity sits at sites with documented opposition or litigation. Capacity is only counted where a megawatt figure is in the record, so this is a floor.

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us