PAX, Pennsylvania Digital I

Carlisle, Cumberland County, Pennsylvania · All 12 PowerHouse Data Centers sites · Every PowerHouse and Hillwood case on our tracker

Under constructionContestedAI confirmedRecord updated August 2, 2026

PAX, Pennsylvania Digital I is a data center under construction in Carlisle, Pennsylvania (Cumberland County), operated by PowerHouse Data Centers. The public record puts it at announced July 2025, 1.4 GW planned, 700 acres. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Under construction

Operator
PowerHouse Data Centers
Facility type
Data center, AI use confirmed
Location
Carlisle, Cumberland County, PA
Coordinates
40.2015, -77.1889
Power capacity
1.4 GW planned
Land
700 acres
Investment
Not established from a public source
Announced
July 2025
Utility
PPL Electric Utilities
Power source
Grid
Cooling
Evaporative
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Contested
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. July 2025
    Under construction
    PA Data Center Partners and PowerHouse launched a $15B JV for a 1.35 GW hyperscale campus (Pennsylvania Digital I / PAX) in Carlisle; near-term 300 MW by Q2 2027 Source: GlobeNewswire

Opposition and litigation at this site

Yes. PAX, Pennsylvania Digital I in Carlisle, Cumberland County, Pennsylvania is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Middlesex Township supervisors voted 3-0 (Ordinance 3-2025, May 30 2025) to create a 694-acre Data Center Overlay District making data centers a by-right use; Protect Cumberland County PA documents organized opposition over water, pollution, utility rates, and private-well impacts (Rep.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.

Middlesex Township supervisors voted 3-0 (Ordinance 3-2025, May 30 2025) to create a 694-acre Data Center Overlay District making data centers a by-right use; Protect Cumberland County PA documents organized opposition over water, pollution, utility rates, and private-well impacts (Rep. Barb Gleim questioned utility-bill effects). No litigation as of 2026-07-08.

Source: Protect Cumberland County PA

Power and water

PPL Electric Utilities will connect the campuses via a new 500 kV-138 kV switching station; 1.35 GW delivered via the PJM grid. No on-site generation confirmed.

Evaporative cooling for peak thermal conditions. A $14.1M agreement with the Middlesex Township Municipal Authority grants access to up to 400,000 gal/day (0.4 MGD) - a contracted ceiling (~2,367 dwelling units), not measured operational use; regulated by PA DEP and the Susquehanna River Basin Commission.

Notes on the record

'Pennsylvania Digital I' (PAX) in Carlisle, Cumberland County: a ~700-acre, three-campus development delivering 1.35 GW (expandable to 1.8 GW, in notes), each campus with six buildings and a 450 MW substation. The $15B is the project value across all three campuses (in notes). Near-term 300 MW by Q2 2027. Coordinates are the Carlisle area centroid. The $15B figure is the three-campus JV total, not broken out per campus -> investmentUsd omitted. Pennsylvania's data-center sales-tax exemption eligibility is likely but no confirmed award or LERTA designation was found. Partner: Pennsylvania Data Center Partners.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Tax abatements or other public subsidy
  • Permanent jobs promised
Which document closes each gap
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the PAX, Pennsylvania Digital I data center in Carlisle?

Yes. PAX, Pennsylvania Digital I in Carlisle, Cumberland County, Pennsylvania is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Middlesex Township supervisors voted 3-0 (Ordinance 3-2025, May 30 2025) to create a 694-acre Data Center Overlay District making data centers a by-right use; Protect Cumberland County PA documents organized opposition over water, pollution, utility rates, and private-well impacts (Rep.

Has anyone filed a lawsuit over the PAX, Pennsylvania Digital I data center?

No lawsuit over PAX, Pennsylvania Digital I appears in the record we track as of August 2, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does PAX, Pennsylvania Digital I use?

No water withdrawal figure for PAX, Pennsylvania Digital I is on record here. Cooling is recorded as evaporative, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates PAX, Pennsylvania Digital I, and how big is it?

PowerHouse Data Centers is the operator on record. We hold 12 sites for that company across the registry. Capacity on record is 1.4 GW. The site is recorded at 700 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "PAX, Pennsylvania Digital I," updated August 2, 2026, https://suedatacenters.org/data-centers/powerhouse-pax-carlisle-pa.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/powerhouse-pax-carlisle-pa, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Pennsylvania Data Center Partners and PowerHouse Data Centers launch JV to build 1.35 GW hyperscale campus in Carlisle · GlobeNewswire · retrieved July 7, 2026
  2. 2.PA Data Center Partners and PowerHouse launch 1.35 GW Carlisle JV · PowerHouse Data Centers · retrieved July 8, 2026
  3. 3.Data center's $14.1M deal to consume 40% of a PA town's excess water · Common Dreams · retrieved July 8, 2026
  4. 4.Cumberland County, PA data centers take new step forward · Government Technology · retrieved July 8, 2026
  5. 5.Middlesex Township data center overlay · Protect Cumberland County PA · retrieved July 8, 2026
  6. 6.PA Data Center Partners and PowerHouse launch JV for 1.35 GW hyperscale campus in Carlisle · GlobeNewswire · retrieved August 2, 2026
  7. 7.450 MW substation approved for $15B Pennsylvania Digital I (PAX) AI data center in Carlisle · Construction Review Online · retrieved August 2, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us