Data Center Registry
Sentinel East Whiteland Data Center
East Whiteland Township, Chester County, Pennsylvania · All 3 Sentinel Data Centers sites
Sentinel East Whiteland Data Center is a data center under construction in East Whiteland Township, Pennsylvania (Chester County), operated by Sentinel Data Centers. The public record puts it at 300 MW planned, 100 acres. It is or has been the subject of litigation over its siting, permitting, or operation.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Under construction
- Operator
- Sentinel Data Centers
- Facility type
- Data center, AI use likely
- Location
- East Whiteland Township, Chester County, PA
- Coordinates
- 40.0410, -75.5450
- Power capacity
- 300 MW planned
- Land
- 100 acres
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- PECO
- Power source
- Grid
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- In litigation
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- August 17, 2026Under constructionConstruction has begun. Earth-moving work (dirt movement and digging under an erosion and sedimentation control permit) started at the East Whiteland site, was halted by a township stop-work order earlier in July 2026 while officials reviewed soil and health safety plans for the former Cyprus Foote Mineral Superfund site, and resumed on Wednesday, July 30, 2026 under a permit carrying conditions on soil monitoring, dust control and protection of the Superfund remedy. Stormwater management work is also under way in adjacent West Whiteland. Further permits are still needed for concrete and foundations, and the developers' request to shrink the building program from 1.5 million to 536,000 sq ft was tabled to an August 19, 2026 meeting. Source: The Philadelphia Inquirer
Opposition and litigation at this site
Yes. Sentinel East Whiteland Data Center in East Whiteland Township, Chester County, Pennsylvania is or has been the subject of litigation over its siting, permitting, or operation. Original 2018/2024 zoning and final-plan approvals are being challenged; a court called one challenge 'frivolous' (June 2026).
How the community has taken it
Reception is a sourced signal, not an editorial judgment: in litigation means the facility is or has been the subject of a lawsuit related to its siting, permitting, or operation.
Original 2018/2024 zoning and final-plan approvals are being challenged; a court called one challenge 'frivolous' (June 2026). An amended expansion plan seeks up to 1.6M sq ft / 100-600MW (a range, not a confirmed single figure).
Notes on the record
Site: 13 S. Bacton Hill Rd, former Foote Mineral Superfund site. Coordinates are approximate for the township.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Flexential Philadelphia - Collegeville (PHL01) · Collegeville · Flexential8 mi · Operating
- TierPoint Valley Forge · Norristown · TierPoint9 mi · Operating
- Lumen Norristown · Norristown · Lumen Technologies9 mi · Operating
- Pennhurst Data Center Campus · Spring City · Penn Hurst Holdings11 mi · Proposed · In litigation
- Renaissance Park and Innovation Data Center Campus · King of Prussia · MLP Ventures11 mi · Proposed · Opposed
- MLP Ventures Plymouth Township Data Center (former Cleveland-Cliffs Conshohocken plant) · Conshohocken · MLP Ventures13 mi · Proposed · Opposed
- Limerick Township Data Center Campus (MCD 7) · Limerick Township · MCD 7 LLC14 mi · Proposed · 750 MW · Opposed
- White Clay Corporate Center Data Center Redevelopment · Newark · Shelbourne27 mi · Proposed · Contested
Questions people ask about this site
Is there opposition to the Sentinel East Whiteland Data Center in East Whiteland Township?
Yes. Sentinel East Whiteland Data Center in East Whiteland Township, Chester County, Pennsylvania is or has been the subject of litigation over its siting, permitting, or operation. Original 2018/2024 zoning and final-plan approvals are being challenged; a court called one challenge 'frivolous' (June 2026).
Has anyone filed a lawsuit over the Sentinel East Whiteland Data Center?
Yes. This site is recorded as being in litigation. The case, the court, and the filings we hold are listed on this page under the timeline and the sources.
How much water does Sentinel East Whiteland Data Center use?
No water withdrawal figure for Sentinel East Whiteland Data Center is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Sentinel East Whiteland Data Center, and how big is it?
Sentinel Data Centers is the operator on record. We hold 3 sites for that company across the registry. Capacity on record is 300 MW. The site is recorded at 100 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Sentinel East Whiteland Data Center," updated August 17, 2026, https://suedatacenters.org/data-centers/sentinel-east-whiteland-chester-county-pa.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/sentinel-east-whiteland-chester-county-pa, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Sentinel Data Centers announces 300 MW Sentinel East Whiteland Data Center in PA · CleanView · retrieved July 9, 2026
- 2.Judge denies challenges to East Whiteland data center expansion · Philadelphia Inquirer · retrieved July 9, 2026
- 3.HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · Oak Ridge National Laboratory (ORNL) / HIFLD · retrieved July 23, 2026
- 4.East Whiteland officials allow work to resume on data center planned for Superfund site · The Philadelphia Inquirer · retrieved August 17, 2026
- 5.Data center construction starts - then stops - at Superfund site in East Whiteland · Suburban Realtors Alliance · retrieved August 17, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us