Sue Data Centers

The Registry

The projects that did not happen

Every site in the registry recorded as cancelled or withdrawn, largest first, with the last thing the public record says about why. A cancelled project is the outcome every fight on our tracker is about, so this is the page to read before yours.

90
cancelled sites
10.6 GW
planned capacity withdrawn
$59.8 billion
announced investment that did not proceed
61
after documented opposition
34
states

As of September 14, 2026. The fights still going · Download the data.

  1. 2 GW
    June 2, 2026
    Green Data Socorro CampusSocorro, New Mexico · Green Data (Green Data Centers) · Opposed

    New Mexico Tech President Michael Jackson said the university would not proceed and would not renew or extend its agreement with Green Data, citing insufficient contiguous acreage, renewable-integration challenges and community concerns.

    Data centers in New Mexico
  2. 1.4 GW
    May 2026
    A1 Data Center CampusMillville, New Jersey · A1 Data Center

    Millville Board of Commissioners banned new data centers citywide (May 19, 2026), blocking this proposal - the largest data center project ever proposed in New Jersey.

    Data centers in New Jersey
  3. 1.3 GW
    August 6, 2026
    Lovejoy Data Center Campus (Stillwater Development)Lovejoy, Georgia · Stillwater Development · Opposed

    The proposal was formally withdrawn at a Lovejoy city council meeting; the mayor indicated the developers intend to pursue residential development for the site instead.

    Data centers in Georgia
  4. 900 MW
    January 29, 2026
    Hunting Hawk Technology ParkGlen Allen, Virginia · HHHunt · Opposed

    HHHunt withdrew its rezoning application two weeks after the Hanover Planning Commission recommended denial on January 15, 2026, and before a scheduled February 25 Board of Supervisors vote.

    Data centers in Virginia
  5. 900 MW
    May 27, 2026
    Mountain Road Technology ParkVirginia · Tract · Opposed

    Hanover Board of Supervisors denied the rezoning, building-height exception, and substation CUP 4-3

    Data centers in Virginia
  6. 750 MW
    July 27, 2026
    Mudiita Ransom Township Data Center CampusRansom Township, Pennsylvania · Mudiita Land Venture LLC

    Listed incorporator Sinha Shatrughan told WVIA 'Personally, I didn't want to go ahead with any sort of data center there right now'; the Mudiita Infra websites are deactivated.

    Data centers in Pennsylvania
  7. 600 MW
    October 8, 2025
    Project Accelerate, Matthews (East John Street)Matthews, North Carolina · Crosland Southeast · Opposed

    Developers withdrew the rezoning request; the mayor announced the withdrawal after sustained public opposition.

    Data centers in North Carolina
  8. 600 MW
    July 2025
    $6 billion
    Project Lincoln: OC Data CenterLa Grange, Kentucky · Western Hospitality Partners · Opposed

    Original 267-acre application withdrawn amid opposition; Oldham County Fiscal Court passed a 150-day data-center moratorium 4-2 on 2025-07-02 with no exemption carved out for the pending Western Hospitality application. Developer pursued a smaller, relocated ~100 MW proposal at a different site (the Sauerbeck family drive-in theater property) within the county; baxtel.com's tracking record for this original filing lists status as 'Project cancelled before construction.'

    Data centers in Kentucky
  9. 430 MW
    March 2026
    Applied Digital Deuel County AI CampusToronto, South Dakota · Applied Digital Corporation

    Applied Digital told Keloland (statement March 2026) that the project was 'unlikely to go forward,' citing the South Dakota legislature's failure to pass a 50-year sales-tax exemption on IT equipment, and said it would let its land option near Toronto lapse.

    Data centers in South Dakota
  10. 300 MW
    March 5, 2026
    Natelli New Hill Digital CampusNew Hill, North Carolina · Natelli Holdings · Opposed

    Natelli Holdings withdrew its annexation and rezoning applications for the New Hill Digital Campus in early March 2026 amid sustained community opposition (Protect Wake County Coalition); the Apex Town Council moved toward a one-year data-center moratorium. The developer said it may revisit only if Apex later adopts a comprehensive zoning text amendment permitting data centers, no re-filing as of July 2026.

    Data centers in North Carolina
  11. 300 MW
    January 2024
    NE Edge Millstone Nuclear Data CenterWaterford, Connecticut · NE Edge · Opposed

    CT Siting Council denies Dominion's petition for exemption from state review. Host fee agreement terminated by default.

    Data centers in Connecticut
  12. 200 MW
    August 25, 2026
    Aligned Data Centers, PataskalaPataskala, Ohio · Aligned Data Centers · Contested

    Pataskala City Council voted 7-0 on Aug. 25, 2026 to reject the site plan, accepting the Planning and Zoning Commission's recommendation to deny it. Aligned has not withdrawn, its general counsel said only that the company would “reflect and regroup.” A separate citizen charter amendment banning data centers over 25 MW goes to Pataskala and Granville voters on Nov. 3, 2026.

    Data centers in Ohio
  13. 180 MW
    June 30, 2026
    CoreWeave Digital CrossroadsHammond, Indiana · CoreWeave

    City of Hammond announced the development agreement expired June 30, 2026 - required milestones and obligations were not completed by the deadline, and no further extensions were offered; no groundbreaking occurred.

    Data centers in Indiana
  14. 150 MW
    May 14, 2026
    $1.6 billion
    East 55th Street Data Center (Slavic Village)Cleveland, Ohio · Lakeland Equity Group · Opposed

    City of Cleveland rejected the permit application.

    Data centers in Ohio
  15. 150 MW
    September 12, 2026
    Steward Drive Data Center (Rochelle)Rochelle, Illinois · Midwest Power Investors LLC (LFF Industrial) · Opposed

    Rochelle City Council rejected the development agreement 0-7 on 27 April 2026 after tabling it in March.

    Data centers in Illinois
  16. 100 MW
    $264 million
    Greenidge Spartanburg (South Carolina)Spartanburg, South Carolina · Greenidge Generation

    The record marks the project cancelled without a stated reason. The profile lists the sources and the document that would establish one.

    Data centers in South Carolina
  17. 82 MW
    June 2026
    $550 million
    Sentinel Data Centers Androscoggin Mill Campus, JayJay, Maine · Sentinel Data Centers · Supported

    Sentinel Data Centers withdrew from the Androscoggin Mill project and halted work in June 2026 (after Gov. Mills vetoed a statewide 20MW+ data-center moratorium that had been intended to protect it). Per the JGT2 mill-redevelopment team, the site itself is 'not dead', the 82MW (expandable) power infrastructure and rail access remain, and JGT2 is seeking a new data-center operator or industrial tenant.

    Data centers in Maine
  18. 60 MW
    April 2025
    $300 million

    Reported dead by One Katahdin's mill-site redevelopment director; Nautilus could not secure the AI customer it wanted because the site could not deliver enough power.

    Data centers in Maine
  19. 50 MW
    November 2024

    DC Blox withdrew rezoning application after sustained community opposition; 195,000 sq ft, 50 MW capacity

    Data centers in Virginia
  20. 50 MW
    February 2026
    Sabey Data Centers Butte Campus (Montana Connections)Butte, Montana · Sabey Data Centers

    Land purchase/sale agreement for a 606.5-acre parcel in the Montana Connections Industrial Park was still contingent on closing, with the deadline extended to Feb 11, 2026.

    Data centers in Montana
  21. 33 MW
    Elk River Data Center (Elk River Capital / Swervo Development)Elk River, Minnesota · Elk River Capital LLC (Swervo Development Corp affiliate)

    The record marks the project cancelled without a stated reason. The profile lists the sources and the document that would establish one.

    Data centers in Minnesota
  22. 30 MW
    July 2023
    $100 million
    Roundhouse Cascade Locks Data CenterCascade Locks, Oregon · Roundhouse Digital Infrastructure · Opposed

    The Port of Cascade Locks and Roundhouse jointly announced the project would be discontinued before construction.

    Data centers in Oregon
  23. 26 MW
    June 2026
    Allen Park Data CenterAllen Park, Michigan · Solstice Data · Opposed

    Site plan denied 7-2 by the Allen Park Planning Commission on 2026-06-04.

    Data centers in Michigan
  24. 24 MW
    April 2026
    $120 million
    Deep Green Lansing Data CenterLansing, Michigan · Deep Green · Mixed reception

    Gander Newsroom's running Michigan data-center tracker records the application as withdrawn in April 2026, after the March planning-commission recommendation.

    Data centers in Michigan
  25. 24 MW
    August 2026
    Harrington Data Center Proposal (Maguire Hayden)Harrington, Delaware · Maguire Hayden · Opposed

    Harrington City Council voted unanimously to reject the zoning change needed for the project; per Spotlight Delaware the vote 'prompted cheers and a standing ovation' from residents opposed to the project.

    Data centers in Delaware
  26. 20 MW
    May 27, 2026
    Boxminer La Pine Bitcoin Mining FacilityLa Pine, Oregon · Boxminer (Hidden Pines LLC) · Opposed

    La Pine City Council voted unanimously to reject the proposed 20 MW facility in the La Pine Industrial Park.

    Data centers in Oregon
  27. 15 MW
    WestBlock Capital Bitcoin Mine (Shiprock)Shiprock, New Mexico · WestBlock Capital · Contested

    The record marks the project cancelled without a stated reason. The profile lists the sources and the document that would establish one.

    Data centers in New Mexico
  28. 5 MW
    September 3, 2026
    Green Data Spaceport America Data CenterNew Mexico · Green Data / Aetherion Inc. · Opposed

    The NM State Land Office rejected the Aetherion/Green Data sublease proposal at Spaceport America on 2026-09-03, and Land Commissioner Stephanie Garcia Richard ruled Sierra County's 2026-07-21 data-center moratorium applies to Spaceport activity despite it sitting on state trust land. Spaceport's executive director Scott McLaughlin said the facility will honor the decision. The developer (Jason Bak) did not respond to comment and left the door open to a future proposal once moratoria expire, but this specific sublease proposal is dead as of this report.

    Data centers in New Mexico
  29. Size not on record
    August 26, 2026
    1500 Gateway Data Center (denied)Fredericksburg, Virginia · 1500 Gateway LLC (Penzance) · Opposed

    Fredericksburg City Council voted 7 to 0 early on August 26, 2026 to deny the rezoning and 7 to 0 to deny the special use permit. The land stays Planned Development-Medical Center.

    Data centers in Virginia
  30. Size not on record
    2025
    $1 billion
    Amazon Becker Data Center (Suspended)Becker, Minnesota · Amazon Web Services · Mixed reception

    Amazon suspended plans citing 'uncertain' permit and utility agreement timelines; Minnesota lawmakers simultaneously reduced sales tax exemptions on electricity for large data center facilities

    Data centers in Minnesota
  31. Size not on record
    Apple Valley Technology Park (Oppidan/Rockport)Apple Valley, Minnesota · Oppidan Investment Company · Opposed

    The record marks the project cancelled without a stated reason. The profile lists the sources and the document that would establish one.

    Data centers in Minnesota
  32. Size not on record
    August 26, 2026
    AWS Calvert County Data Center CampusLusby, Maryland · Amazon Web Services · Mixed reception

    Amazon Data Services Inc. formally withdrew its Calvert Technology Center Conceptual Site Development Plan application and decided not to pursue the proposed data center project in Calvert County. Calvert County Government announced the withdrawal in an Aug. 4, 2026 press release; the county's data center page now records the application as withdrawn and states no site plan applications for data center development are pending. The withdrawal followed voter backlash in the county's June 23, 2026 primary, and the county subsequently passed a six-month moratorium on data center site plan approvals effective Aug. 28, 2026.

    Data centers in Maryland
  33. Size not on record
    Big Horn Data Hub (Hardin Generating Station)Hardin, Montana · Beowulf Electricity & Data

    The record marks the project cancelled without a stated reason. The profile lists the sources and the document that would establish one.

    Data centers in Montana
  34. Size not on record
    Bonner Mill Bitcoin Mine (Project Spokane / HyperBlock)Bonner, Montana · HyperBlock Inc. · Opposed

    The record marks the project cancelled without a stated reason. The profile lists the sources and the document that would establish one.

    Data centers in Montana
  35. Size not on record
    December 2025
    Boomtown Lawton Data Center, cancelledLawton, Oklahoma · Boomtown

    Project listed as canceled in December 2025 after the developer walked away from a long-term lease on state school-trust land east of Lawton.

    Data centers in Oklahoma
  36. Size not on record
    September 12, 2026
    $2 billion
    Brennan Barrington Hills Data CenterBarrington Hills, Illinois · Brennan Investment Group · Opposed

    Brennan Investment Group withdrew the proposal on 28 January 2026, cancelling a 2 February plan commission presentation 'based on initial feedback'.

    Data centers in Illinois
  37. Size not on record
    April 2026
    $1 billion
    Cassville Data Center Campus (Undisclosed Developer)Cassville, Wisconsin · Undisclosed (major tech company, NDA not signed) · Opposed

    Town of Cassville voters approved 44-0 an ordinance banning data centers in the township on April 16, 2026; developer went silent after the vote and was reported considering sites in Indiana and North Dakota

    Data centers in Wisconsin
  38. Size not on record
    August 17, 2026
    Cetronia Road Data Center (former Air Products site)Trexlertown, Pennsylvania · Air Products · Contested

    Project ended. The Upper Macungie Township Zoning Hearing Board rejected Air Products' request to establish a data center on the 194-acre former headquarters property in a decision issued July 2026 (after a May 27, 2026 hearing). Air Products let the August 5, 2026 appeal deadline pass without appealing; spokesman Art George confirmed 'Air Products has decided not to pursue an appeal of the Upper Macungie Township Zoning Board decision.' No decision has been made on future ownership or use of the property.

    Data centers in Pennsylvania
  39. Size not on record
    CleanSpark Limestone Bitcoin Mining Facility (closed 2026)Limestone, Tennessee · CleanSpark, Inc. · In litigation

    The record marks the project cancelled without a stated reason. The profile lists the sources and the document that would establish one.

    Data centers in Tennessee
  40. Size not on record
    December 2025
    Cloverleaf Carlton Data Center Site (Kewaunee County)Carlton, Wisconsin · Cloverleaf Infrastructure · Opposed

    Cloverleaf stopped pursuing farmland in the town of Carlton in late 2025 after town leadership and residents opposed it.

    Data centers in Wisconsin
  41. Size not on record
    June 4, 2026
    Coachella Valley Technology CampusCoachella, California · Stronghold Power Systems · Opposed

    City Council unanimously terminated the Stronghold utility agreement and approved a 45-day data-center moratorium after sustained community opposition. The moratorium was extended roughly 10.5 months on 2026-07-08, and the Planning Commission recommended a permanent citywide data-center ban (two conditions attached) on 2026-07-15, with Council adoption votes scheduled for 2026-08-12 and 2026-08-26.

    Data centers in California
  42. Size not on record
    Crypto Colo Center McLouth Data Center (proposed), cancelledMcLouth, Kansas · Crypto Colo Center Corp · Opposed

    The record marks the project cancelled without a stated reason. The profile lists the sources and the document that would establish one.

    Data centers in Kansas
  43. Size not on record
    June 12, 2024
    Culpeper Acquisitions Brandy Station Campus (denied)Brandy Station, Virginia · Culpeper Acquisitions LLC

    Unanimously denied by Culpeper County Planning Commission; concerns over rural preservation and proximity to Culpeper Battlefields State Park

    Data centers in Virginia
  44. Size not on record
    March 31, 2026
    DigiCo LAX1 (1977 Saturn Street)Monterey Park, California · DigiCo Infrastructure REIT · Opposed

    HMC StratCap 1977 Saturn, LLC (a DigiCo Infrastructure REIT subsidiary) formally withdrew Development Agreement No. 24.02 / Site Development Plan No. 24-040 in a signed letter to the Monterey Park City Council (signed by Interim CEO Chris Maher) - filed before, not after, the city's Measure NDC ballot vote.

    Data centers in California
  45. Size not on record
    Dulles Cloud South (Dulles South Innovation Center)Gainesville, Virginia · Undisclosed

    The record marks the project cancelled without a stated reason. The profile lists the sources and the document that would establish one.

    Data centers in Virginia
  46. Size not on record
    June 17, 2025
    Etheridge Lakes Data Center (Great Bridge)Chesapeake, Virginia · Emerald Lakes Estates (Doug Fuller) · Opposed

    cancelled per City of Chesapeake Department of Planning, Rezoning Case PLN-REZ-2025-002 (Etheridge Lakes Data Center)

    Data centers in Virginia
  47. Size not on record
    Giga Watt Mining Facility (former)East Wenatchee, Washington · Giga Watt Inc.

    The record marks the project cancelled without a stated reason. The profile lists the sources and the document that would establish one.

    Data centers in Washington
  48. Size not on record
    Green Digital Harrison Mine (proposed, withdrawn)Harrison, Arkansas · Green Digital LLC · Opposed

    The record marks the project cancelled without a stated reason. The profile lists the sources and the document that would establish one.

    Data centers in Arkansas
  49. Size not on record
    May 2025
    Hancock County MegaSiteIndiana · Surge Development LLC · Opposed

    Surge Development LLC withdrew its PUD rezoning petition, announced via a county government news release the evening of 2025-05-13, after weeks of public backlash. Baxtel's tracking record for the site lists status as 'Project cancelled before construction.'

    Data centers in Indiana
  50. Size not on record
    Highwire Energy Partners Bitcoin Mining Facility (Evansville)Evansville, Wyoming · Highwire Energy Partners · Supported

    The record marks the project cancelled without a stated reason. The profile lists the sources and the document that would establish one.

    Data centers in Wyoming
  51. Size not on record
    June 23, 2026
    Holder Industrial Park Data Center Expansion (withdrawn)Lecanto, Florida · Deltona Corporation · Opposed

    Deltona withdrew both applications rather than face a July 14, 2026 commission vote, after the Planning and Development Commission unanimously recommended denial following an 8-hour public hearing.

    Data centers in Florida
  52. Size not on record
    December 2025
    $1 billion
    Howell Township Hyperscale Data CenterHowell, Michigan · Stantec Consulting Michigan / Randee LLC · Opposed

    Applicants withdrew the conditional rezoning request on 2025-12-08, saying they would honour the township's moratorium. Township officials indicated the developers may resubmit once the moratorium ends.

    Data centers in Michigan
  53. Size not on record
    Interstate Holdings Blockchain Vilonia Mine (proposed, denied)Vilonia, Arkansas · Interstate Holdings Blockchain · Opposed

    The record marks the project cancelled without a stated reason. The profile lists the sources and the document that would establish one.

    Data centers in Arkansas
  54. Size not on record
    November 20, 2025
    Kalkaska GoMichigan · Rocklocker LLC · Opposed

    Rocklocker withdrew the proposal after public opposition and the DNR's rejection of the state-land purchase request.

    Data centers in Michigan
  55. Size not on record
    August 28, 2026
    La Osa Data Center ParkEloy, Arizona · Vermaland LLC · Opposed

    The Pinal County Board of Supervisors voted 4-1 on August 26, 2026 to reject the La Osa Energy Center rezoning request and development plans, after the developer had already scaled the proposal back roughly 80% (from 59 data center buildings and 3 GW of demand to 11 buildings, a 500 MW gas plant, battery storage and a 1 GW cap) in response to opposition over aquifer drawdown and incomplete energy sourcing plans. Supervisor Stephen Miller cast the lone dissent. Recorded as cancelled because the entitlement the project required was denied; Vermaland has not publicly announced a withdrawal or a refiling, so this reflects the county's denial rather than a developer decision.

    Data centers in Arizona
  56. Size not on record
    July 2026
    $2.3 billion
    Lex Developments AI Data Center (former Hoku polysilicon site)Pocatello, Idaho · Lex Developments · Contested

    Pocatello City Council voted 4-1 to uphold the Hearing Examiner's denial of the conditional use permit, ending the local approval path as of retrieval.

    Data centers in Idaho
  57. Size not on record
    July 8, 2026
    Liberty Road Data Center Campus (EdgeConneX)Villa Rica, Georgia · EdgeConneX (applicant East Village Dothan LLC) · Opposed

    The Douglas County Commission voted 4-1 to deny the rezoning for a six-building, 4.4 million sq ft campus on roughly 700 acres near Liberty Road and I-20, the second denial for the property in seven months.

    Data centers in Georgia
  58. Size not on record
    February 2025
    LN Energy Blackshear Bitcoin MineBlackshear, Georgia · LN Energy · Opposed

    Pierce County Commission unanimously denied the conditional-use permit.

    Data centers in Georgia
  59. Size not on record
    January 20, 2026
    Logix Reality Frankfort Data CenterFrankfort, Indiana · Logix Reality LLC · Opposed

    Clinton County Commissioners unanimously denied the rezoning, citing impact on adjacent property owners and the developer's failure to negotiate the 14 proposed commitments. The denial bars the petitioner from returning for 12 months.

    Data centers in Indiana
  60. Size not on record
    September 12, 2026
    Lutticken Farm Data Center (Pekin)Pekin, Illinois · Western Hospitality Partners · Opposed

    Mayor Mary Burress announced on 9 March 2026 that the city would not move forward; the developer formally terminated the purchase agreement in a 5 May 2026 letter.

    Data centers in Illinois
  61. Size not on record
    MiningStore Grundy Center FacilityGrundy Center, Iowa · MiningStore

    The record marks the project cancelled without a stated reason. The profile lists the sources and the document that would establish one.

    Data centers in Iowa
  62. Size not on record
    August 13, 2025
    Mooresville CampusMooresville, North Carolina · Tract

    Tract withdrew its rezoning application for the Mooresville Technology Park (Iredell County) in August 2025 after community opposition. The Mooresville mayor said there is 'no longer an active request' to build the data center and that it was removed from all future town meeting agendas. (This project was already withdrawn ~11 months before Compute Atlas added it as 'proposed'.)

    Data centers in North Carolina
  63. Size not on record
    January 28, 2026
    MS Solar Grid Data (New Orleans East)New Orleans, Louisiana · MS Solar Grid Data · Opposed

    Developer pulled the zoning permit the same day the City Council passed a one-year data center moratorium.

    Data centers in Louisiana
  64. Size not on record
    December 10, 2025
    New Carlisle Chicago Trail Data Center (rezoning denied)New Carlisle, Indiana · Undisclosed · Opposed

    St. Joseph County Council voted 7-2 to deny the rezoning after a hearing that ran until roughly 4 a.m.

    Data centers in Indiana
  65. Size not on record

    The record marks the project cancelled without a stated reason. The profile lists the sources and the document that would establish one.

    Data centers in Oklahoma
  66. Size not on record
    Okee-One Data Center CampusOkeechobee, Florida · Indian River State College

    The record marks the project cancelled without a stated reason. The profile lists the sources and the document that would establish one.

    Data centers in Florida
  67. Size not on record
    May 2026
    Old Ridge Road Data Center CampusDoswell, Virginia · LS Power

    New York-based LS Power withdrew its zoning request for the Old Ridge Road site in a letter from the developer's attorney to Hanover County; no replacement zoning application had been filed as of late June 2026.

    Data centers in Virginia
  68. Size not on record
    May 2026
    Outrigger Industrial Washington Data CenterWashington, Indiana · Outrigger Industrial · Opposed

    Washington City Council voted unanimously to cease all business with the developer and explore a moratorium, ending the proposal.

    Data centers in Indiana
  69. Size not on record
    July 2026
    Prince William Digital GatewayGainesville, Virginia · QTS / Compass Datacenters · Opposed

    QTS withdrew Virginia Supreme Court appeal July 2, 2026 after Court of Appeals unanimously halted project March 2026. Circuit court had voided rezoning August 2024 citing inadequate public notice under Va. Code § 15.2-2204. Project officially terminated.

    Data centers in Virginia
  70. Size not on record
    June 3, 2026
    Project Altair (Mid-Carolina Commerce Park II)Prosperity, South Carolina · Undisclosed developer (Project Altair) · Opposed

    Newberry County Council voted unanimously to deny the land-sale ordinance at third reading, reversing the first two readings, and then moved to a 12-month moratorium on accepting new data center permits.

    Data centers in South Carolina
  71. Size not on record
    March 30, 2026
    Project Atlas (Coweta), withdrawnCoweta, Oklahoma · Beale Infrastructure

    Beale Infrastructure withdrew the 270-acre rezoning application after resident opposition and NDA-disclosure concerns; the Coweta planning commission had voted 4-1 to deny.

    Data centers in Oklahoma
  72. Size not on record
    August 16, 2026
    Project Flash (Summit View Business Park)Rocky Mount, Virginia · Crusoe · Opposed

    Boone District Supervisor Mike Meredith announced the county had received verification that the project would not move forward. No agreements were ever reached and no votes were taken on data center development in Franklin County.

    Data centers in Virginia
  73. Size not on record
    June 2026
    $2.4 billion
    Project Liberty (Stream Data Centers, Marion County Industrial Park)Marion, South Carolina · Stream Data Centers (site entity: Eagle Myra, LLC) · Opposed

    Stream Data Centers withdrew, stating utility power could not be sourced to the site within the required timeframe.

    Data centers in South Carolina
  74. Size not on record
    September 2026
    Project Oak Data Center (Walt Sanders Road)Newnan, Georgia · Undisclosed developer · Opposed

    The Coweta County Board of Commissioners unanimously denied the rezoning application to allow data center use on the Walt Sanders Road industrial property. County procedure requires a six-month wait before reapplying.

    Data centers in Georgia
  75. Size not on record
    February 28, 2026

    TigerDC formally withdrew Project Spero from consideration in Spartanburg County after the council declined to offer tax incentives, stating that 'alignment has not been achieved' and that it would pursue alternative sites.

    Data centers in South Carolina
  76. Size not on record
    June 2026
    Project SwanLakeland, Florida · Ryan Companies (end operator TBD) · Opposed

    CONFLICTING REPORTING - flag for maintainer judgment before applying. A 2026-06-03 city clarification (WUSF/LkldNow 'Still Active') said the applicant only withdrew from a June 3 Development Review Team meeting, not the application itself, after it was mistakenly marked withdrawn in the city's iMS system. But this 2026-09-01 piece states flatly the application 'had already been withdrawn in June' and that no data-center applications were pending when Lakeland passed its 1-year, 50MW-threshold moratorium on 2026-08-03. Reporting as cancelled on the more recent, more specific source, but the earlier contradiction should be checked.

    Data centers in Florida
  77. Size not on record
    July 16, 2026
    Project Tango AI Data Center CampusLoxahatchee, Florida · PBA Holdings (end tenant undisclosed) · Contested

    Palm Beach County Board of County Commissioners denied the Project Tango hyperscale-data-center development-order amendment on a 5-1 vote on 2026-07-16, after a 12-hour hearing with overflow crowds. A smaller data-center use (~206,000 sq ft, alongside ~1.8M sq ft of warehouse) remains approved under the 2016 Central Park Commerce Center zoning at the 202-acre site (20125 Southern Blvd), where construction continues under that prior approval.

    Data centers in Florida
  78. Size not on record
    February 2026
    Proposed St. Albans, VT Data Center (Unbuilt)St. Albans, Vermont · Unnamed developer

    "It was going to cost just too much money to build a substation that would have allowed the project to move forward" -- Sean Adkins, then St. Albans town manager, on why the developer withdrew: connecting to the grid would have required a new substation costing roughly $30 million.

    Data centers in Vermont
  79. Size not on record
    September 29, 2025
    PRSM Preble County Data Center CampusMonroe Township, Ohio · PRSM Group · Opposed

    Property owners withdrew the rezoning application before the Board of Commissioners vote; the developer has signalled a possible future re-application.

    Data centers in Ohio
  80. Size not on record
    January 28, 2026
    $12 billion
    QTS Dane County Hyperscale Campus (DeForest)DeForest, Wisconsin · QTS Data Centers · Opposed

    Village of DeForest declared the proposal not feasible; QTS withdrew all applications after the Village Board signaled a 7-0 rejection of annexation. WI DOA separately found the annexation not in the public interest.

    Data centers in Wisconsin
  81. Size not on record
    March 11, 2026
    Revolve Labs Moose Lake (withdrawn)Moose Lake, Minnesota · Revolve Labs · Opposed

    Revolve Labs withdrew its application; the city administrator informed the City Council. The company said “the current timeline for power availability at the site does not align with several near-term initiatives we are advancing elsewhere.”

    Data centers in Minnesota
  82. Size not on record
    September 2024
    Revolve Labs Windom (withdrawn)Windom, Minnesota · Revolve Labs · Opposed

    Revolve Labs withdrew its conditional-use application for the site, citing feedback received from the community.

    Data centers in Minnesota
  83. Size not on record
    July 30, 2026
    $3 billion
    Rural Hall Data Center (The Drox Group)Rural Hall, North Carolina · The Drox Group · Contested

    Forsyth County Board of Commissioners denied rezoning case F-1669 (Project Iron Spur) 5-2 on July 30, 2026, ending the Drox Group's proposed Rural Hall hyperscale data center. The existing record's statusHistory had this vote as 'expected around July 30, 2026', it has now happened and gone against the project.

    Data centers in North Carolina
  84. Size not on record
    $13.5 billion
    Sentinel Grove Technology Park (Project Jarvis)Fort Pierce, Florida · Undisclosed developer (marketed as 'Sentinel Grove Technology Park', county code-named 'Project Jarvis')

    The record marks the project cancelled without a stated reason. The profile lists the sources and the document that would establish one.

    Data centers in Florida
  85. Size not on record
    Simple Mining Cedar Falls (rezoning defeated)Cedar Falls, Iowa · Simple Mining · Opposed

    The record marks the project cancelled without a stated reason. The profile lists the sources and the document that would establish one.

    Data centers in Iowa
  86. Size not on record
    May 13, 2026
    $1.7 billion
    South Annville Township Data Center Campus (withdrawn)South Annville Township, Pennsylvania · Inch & Co. / Eastern Land & Resources Co. (1235 Martina Drive Owner) · Opposed

    Counsel for the petitioner wrote to the Board of Supervisors that it had 'decided to no longer pursue the development of a data center in South Annville Township.'

    Data centers in Pennsylvania
  87. Size not on record
    July 2014
    STAR Campus Data Center & Cogeneration Plant (The Data Centers, LLC)Newark, Delaware · The Data Centers, LLC · Opposed

    University of Delaware terminated its lease agreement with The Data Centers, LLC (TDC) on 2014-07-10.

    Data centers in Delaware
  88. Size not on record
    August 2026
    $10 billion

    Maryland-based developer Stonebridge stopped exploring the Town of Pacific site after the town chair required that any proposal be aired in a public meeting; no follow-up occurred.

    Data centers in Wisconsin
  89. Size not on record
    August 4, 2026
    $1 billion
    Thor Equities Augusta Township Data Center (Form8tion)Augusta Township, Michigan · Thor Equities · Opposed

    Augusta Township voters overturned the rezoning at the August primary, about 90% voted to overturn, returning the seven parcels to agricultural residential and removing the zoning the project depended on. Results were still unofficial as of 2026-08-05.

    Data centers in Michigan
  90. Size not on record
    May 2026
    Washington Township Technical CampusWashington, Michigan · Prologis · Opposed

    Prologis withdrew the rezoning application on 2026-05-19, stating it would wait until the township adopts a data-center ordinance before proceeding.

    Data centers in Michigan

Questions

How many data center projects have been cancelled?

90 sites in the registry carry a status of cancelled as of September 14, 2026, representing 10.6 GW of planned capacity where a figure was on record and $59.8 billion of announced investment. The count covers projects the public record shows as cancelled, withdrawn or rejected; projects that quietly stalled are not counted.

How many were cancelled after local opposition?

61 of the 90 carry a documented reception of contested, opposed or in litigation. Reception is a sourced signal from the record, and a cancelled project with no reception on record is not counted here, so the share is a floor.

Which state has the most cancelled projects?

VA, with 10 cancelled sites on record.

Where does the reason for cancellation come from?

From the last dated note in the site's status history, which the survey or our case files took from a named report, a council record or a company statement. Where no note exists the entry says so rather than guessing.

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us