Holder Industrial Park Data Center Expansion (withdrawn)

Lecanto, Citrus County, Florida

CancelledOpposedRecord updated September 10, 2026

Holder Industrial Park Data Center Expansion (withdrawn) is a cancelled data center in Lecanto, Florida (Citrus County), operated by Deltona Corporation. It faces documented, organized local opposition.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Cancelled

Operator
Deltona Corporation
Facility type
Data center
Location
Lecanto, Citrus County, FL
Coordinates
28.8672, -82.4944 (approximate)
Power capacity
Not established from a public source
Land
Not established from a public source
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Not established from a public source
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Opposed
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. June 23, 2026
    Cancelled
    Deltona withdrew both applications rather than face a July 14, 2026 commission vote, after the Planning and Development Commission unanimously recommended denial following an 8-hour public hearing. Source: 352Today
  2. January 2026
    Proposed
    Deltona Corporation filed applications to expand the existing 557-acre Holder Industrial Park and add data-center uses ('information processing', 'data center utilities', 'data storage') as permitted uses. Source: FloridaDataCenters.org

Opposition and litigation at this site

Yes. Organized local opposition to Holder Industrial Park Data Center Expansion (withdrawn) in Lecanto, Citrus County, Florida is documented in the public record, without a lawsuit on file in the sources we track. More than 200 residents attended the Planning and Development Commission's public hearing, the vast majority speaking in opposition, citing water and electricity use, artificial light in a rural area, and a continuous low-frequency hum.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: opposed means documented, organized local opposition is the dominant signal on record.

More than 200 residents attended the Planning and Development Commission's public hearing, the vast majority speaking in opposition, citing water and electricity use, artificial light in a rural area, and a continuous low-frequency hum.

Source: 352Today

Notes on the record

Site described as near County Road 491 & Tram Road, Lecanto, within/adjoining the existing 557-acre Holder Industrial Park. Sources disagree on the exact expansion acreage (352Today describes a 675-777 acre 'Data Center Use Area' within a >1,300-acre rezoning request; FloridaDataCenters.org describes expansion to ~813 acres) so landAcres is omitted rather than picking one. No specific data-center operator/tenant beyond landowner-developer Deltona Corporation (attorney of record: Sid Ansbacher) was named in any source found this run. The withdrawal came after a county-wide data-center moratorium took effect May 26, 2026, any future Deltona filing on this site is now a new filing subject to that 12-month moratorium, per FloridaDataCenters.org. Coordinates are an approximate geocode of Lecanto, the nearest named place in sourcing, not the parcel itself.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Land area
  • Which utility serves it
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Land area
The rezoning application, the plat, or the deed recorded with the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Questions people ask about this site

Is there opposition to the Holder Industrial Park Data Center Expansion (withdrawn) in Lecanto?

Yes. Organized local opposition to Holder Industrial Park Data Center Expansion (withdrawn) in Lecanto, Citrus County, Florida is documented in the public record, without a lawsuit on file in the sources we track. More than 200 residents attended the Planning and Development Commission's public hearing, the vast majority speaking in opposition, citing water and electricity use, artificial light in a rural area, and a continuous low-frequency hum.

Has anyone filed a lawsuit over the Holder Industrial Park Data Center Expansion (withdrawn)?

No lawsuit over Holder Industrial Park Data Center Expansion (withdrawn) appears in the record we track as of September 10, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Holder Industrial Park Data Center Expansion (withdrawn) use?

No water withdrawal figure for Holder Industrial Park Data Center Expansion (withdrawn) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Holder Industrial Park Data Center Expansion (withdrawn), and how big is it?

Deltona Corporation is the operator on record. No capacity figure is on record for this site.

How to cite this page

SueDataCenters.org Data Center Registry, "Holder Industrial Park Data Center Expansion (withdrawn)," updated September 10, 2026, https://suedatacenters.org/data-centers/deltona-holder-industrial-park-citrus-county-fl.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/deltona-holder-industrial-park-citrus-county-fl, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Citrus County panel rejects Holder Industrial Park data center rezoning · Bay News 9 · retrieved September 10, 2026
  2. 2.Company Withdraws Controversial Industrial Park Data Center Proposal in Citrus County · 352Today · retrieved September 10, 2026
  3. 3.Citrus County Data Centers, Deltona Corp Filing · FloridaDataCenters.org · retrieved September 10, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us