Allen Park Data Center
Allen Park, Wayne County, Michigan
Allen Park Data Center is a cancelled data center in Allen Park, Michigan (Wayne County), operated by Solstice Data. The public record puts it at 26 MW planned. It faces documented, organized local opposition.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Cancelled
- Operator
- Solstice Data
- Facility type
- Data center
- Location
- Enterprise Drive, south of I-94, Allen Park, Wayne County, MI
- Coordinates
- 42.2830, -83.1947 (approximate)
- Power capacity
- 26 MW planned
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- Opposed
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- June 2026CancelledSite plan denied 7-2 by the Allen Park Planning Commission on 2026-06-04. Source: Planet Detroit
- January 2026ProposedPlanning commission delayed a decision for additional analysis; the vote was postponed three times in total. Source: Planet Detroit
Opposition and litigation at this site
Yes. Organized local opposition to Allen Park Data Center in Allen Park, Wayne County, Michigan is documented in the public record, without a lawsuit on file in the sources we track. The planning commission voted 7-2 on 2026-06-04 to deny the site plan after postponing the decision three times, citing needed zoning-ordinance revisions, missing information and inadequate engineering studies, and a sound study that failed to demonstrate noise mitigation.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: opposed means documented, organized local opposition is the dominant signal on record.
The planning commission voted 7-2 on 2026-06-04 to deny the site plan after postponing the decision three times, citing needed zoning-ordinance revisions, missing information and inadequate engineering studies, and a sound study that failed to demonstrate noise mitigation. Residents cheered the rejection; a nurse practitioner raised pollution concerns in an area with high asthma rates near Melvindale High School. The commission also recommended a six-month moratorium on data-center development.
Power and water
The source states the cooling system would NOT be connected to municipal water and that the facility's draw would rank below the city's 20th-largest water customer. That rules out a municipally-supplied evaporative load but does not describe the heat-rejection circuit, so coolingType is left 'unknown' rather than inferred as air or closed_loop.
Notes on the record
26 MW proposal on Enterprise Drive south of I-94, near homes and Melvindale High School. Status 'cancelled' records the DENIED site plan; the source does not report an appeal or resubmission. CONFIRMED ABSENCES: no acreage, investment figure, or job count is stated in either source. Coordinates are Nominatim's street-level match for Enterprise Drive, the only location the source gives (no house number); the parcel is not confirmed.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- Which utility serves it
Which document closes each gap
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Our reporting on this site
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- EdgeConneX DET01 · Detroit (Oakland County) · EdgeConneX12 mi · Operating
- Gibraltar Data Center (former McLouth Steel site) · Gibraltar · Raeden (with Cal Realty / Ferragon Corp.)12 mi · Proposed · 100 MW · In litigation
- 123NET Southfield DC3 (Southfield Data Center W) · Southfield · 123NET13 mi · Operating
- 123NET Southfield DC2 (Southfield Data Center NW) · Southfield · 123NET13 mi · Operating
- Project Cannoli · Van Buren Township · Google13 mi · Proposed · 1 GW · Contested
- 123NET Southfield DC1 · Southfield · 123NET13 mi · Operating · 4 MW
- 365 Data Centers Detroit (DT1) · Southfield · 365 Data Centers13 mi · Operating
- Metrobloks Southfield Data Center · Southfield · Metrobloks14 mi · Permitted · 100 MW · Contested
Questions people ask about this site
Is there opposition to the Allen Park Data Center in Allen Park?
Yes. Organized local opposition to Allen Park Data Center in Allen Park, Wayne County, Michigan is documented in the public record, without a lawsuit on file in the sources we track. The planning commission voted 7-2 on 2026-06-04 to deny the site plan after postponing the decision three times, citing needed zoning-ordinance revisions, missing information and inadequate engineering studies, and a sound study that failed to demonstrate noise mitigation.
Has anyone filed a lawsuit over the Allen Park Data Center?
No lawsuit over Allen Park Data Center appears in the record we track as of September 9, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Allen Park Data Center use?
No water withdrawal figure for Allen Park Data Center is on record here. Cooling is recorded as unknown, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.
Who operates Allen Park Data Center, and how big is it?
Solstice Data is the operator on record. Capacity on record is 26 MW.
How to cite this page
SueDataCenters.org Data Center Registry, "Allen Park Data Center," updated September 9, 2026, https://suedatacenters.org/data-centers/solstice-data-allen-park-mi.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/solstice-data-allen-park-mi, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Allen Park planners reject proposed data center: 'We're gonna celebrate with one eye open' · Planet Detroit · retrieved September 9, 2026
- 2.How many AI data centers are planned in Michigan? We counted. · Gander Newsroom · retrieved September 9, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us