Project Bus (Atlas Development Temple Data Center Campus)

Temple, Carroll County, Georgia · All 4 Atlas Development sites

ProposedOpposedRecord updated September 10, 2026

Project Bus (Atlas Development Temple Data Center Campus) is a proposed data center in Temple, Georgia (Carroll County), operated by Atlas Development LLC. The public record puts it at announced January 26, 2026, 350 acres, a reported $11 billion investment. It faces documented, organized local opposition.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
Atlas Development LLC
Facility type
Data center
Location
Vaughn Road / Center Point Road / Terrell Road / Mandeville Road, Temple, Carroll County, GA
Coordinates
33.7376, -85.0327 (approximate)
Power capacity
Not established from a public source
Land
350 acres
Investment
$11 billion
Announced
January 26, 2026
Utility
Not established from a public source
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
275 permanent
Public subsidy
Not established from a public source
Community reception
Opposed
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. January 26, 2026
    Proposed
    Development of Regional Impact form filed with the Georgia Department of Community Affairs for a 350-acre data center in Temple; rezoning, annexation and sewer extension still required. Source: Times-Georgian

Opposition and litigation at this site

Yes. Organized local opposition to Project Bus (Atlas Development Temple Data Center Campus) in Temple, Carroll County, Georgia is documented in the public record, without a lawsuit on file in the sources we track. Sustained resident opposition organised as the Carroll County Anti-Data Center Coalition over roughly two weeks; the Carroll County Board of Commissioners issued a statement opposing annexation of the county property into Temple, and the developer withdrew the proposal on 2026-08-04.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: opposed means documented, organized local opposition is the dominant signal on record.

Sustained resident opposition organised as the Carroll County Anti-Data Center Coalition over roughly two weeks; the Carroll County Board of Commissioners issued a statement opposing annexation of the county property into Temple, and the developer withdrew the proposal on 2026-08-04. The DRI filing also recorded current water supply capacity for the site as 'not sufficient'.

Source: Gradick Communications

Notes on the record

12 buildings and 2 substations on properties with Temple addresses north and south of I-20; estimated completion 2036 and over $42M/year in combined ad valorem tax to Carroll County. Public-reception check (2026-09-10): Checked the original Times-Georgian article (2026-09-10); it covers the Development of Regional Impact filing (350 acres, ~$11B estimated value) and general academic research on data centers' impact, but documents no public hearing, resident reaction, or official statement of support/opposition specific to this project.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Which utility serves it
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Project Bus (Atlas Development Temple Data Center Campus) in Temple?

Yes. Organized local opposition to Project Bus (Atlas Development Temple Data Center Campus) in Temple, Carroll County, Georgia is documented in the public record, without a lawsuit on file in the sources we track. Sustained resident opposition organised as the Carroll County Anti-Data Center Coalition over roughly two weeks; the Carroll County Board of Commissioners issued a statement opposing annexation of the county property into Temple, and the developer withdrew the proposal on 2026-08-04.

Has anyone filed a lawsuit over the Project Bus (Atlas Development Temple Data Center Campus)?

No lawsuit over Project Bus (Atlas Development Temple Data Center Campus) appears in the record we track as of September 10, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Project Bus (Atlas Development Temple Data Center Campus) use?

No water withdrawal figure for Project Bus (Atlas Development Temple Data Center Campus) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Project Bus (Atlas Development Temple Data Center Campus), and how big is it?

Atlas Development LLC is the operator on record. We hold 4 sites for that company across the registry. No capacity figure is on record for this site. The site is recorded at 350 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Project Bus (Atlas Development Temple Data Center Campus)," updated September 10, 2026, https://suedatacenters.org/data-centers/atlas-project-bus-temple-ga.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/atlas-project-bus-temple-ga, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Data center proposed for Temple · Times-Georgian · retrieved August 28, 2026
  2. 2.Data Center Planned For Development In Carroll County · Gradick Communications · retrieved August 28, 2026
  3. 3.Developer Pulls Data Center Proposal… at least, for now · Gradick Communications · retrieved September 10, 2026
  4. 4.Data center proposed for Temple · Times-Georgian · retrieved September 10, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us