Data Center Registry
Project Sail, Prologis Data Center Campus
Newnan, Coweta County, Georgia · All 9 Prologis sites
Project Sail, Prologis Data Center Campus is a permitted data center in Newnan, Georgia (Coweta County), operated by Prologis. The public record puts it at announced April 2026, 900 MW planned, 800 acres, a reported $17 billion investment. It is or has been the subject of litigation over its siting, permitting, or operation.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
What our reporting adds
Our case file documents this site. Pending, Coweta County Superior Court.
Facility record
Permitted
- Operator
- Prologis
- Facility type
- Data center, AI use likely
- Location
- Newnan, Coweta County, GA
- Coordinates
- 33.3807, -84.7974
- Power capacity
- 900 MW planned
- Land
- 800 acres
- Investment
- $17 billion
- Announced
- April 2026
- Utility
- Georgia Power
- Power source
- Grid
- Cooling
- Evaporative
- Water use
- 6 million gallons a day, reported
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- In litigation
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- May 5, 2026PermittedCoweta County residents filed appeal in Superior Court seeking to reverse rezoning decision Source: The Citizen
- April 8, 2026PermittedCoweta County Board of Commissioners approved rezoning 3-2 for 800+ acres along US-27 near Newnan Source: Atlanta Journal-Constitution
- May 2025ProposedPrologis acquired site from original developer Atlas Development LLC; DRI review completed February 2024 for 200-acre precursor Pegasus proposal
Opposition and litigation at this site
Yes. Project Sail, Prologis Data Center Campus in Newnan, Coweta County, Georgia is or has been the subject of litigation over its siting, permitting, or operation. Pending, Coweta County Superior Court.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: in litigation means the facility is or has been the subject of a lawsuit related to its siting, permitting, or operation.
Pending, Coweta County Superior Court. Project Sail, a $17 billion hyperscale data center campus near Sargent Road. Coweta County residents filed appeal in Coweta County Superior Court May 5, 2026 to reverse 3-2 rezoning vote. Separate eminent domain controversy: Georgia Power acquired easements on 330+ private properties for high-voltage transmission lines needed to serve new data centers.
Power and water
Georgia Power is the service-territory utility for Coweta County; the site is adjacent to Georgia Power's Plant Yates, and the developer states the load was included in Georgia Power's 2025 Integrated Resource Plan. Reporting indicates Georgia Power was not yet under contract to serve the campus as of mid-2026. No on-site generation reported.
Expected to use 6 million gallons of water per day drawn from the Chattahoochee River
Notes on the record
Nine buildings, 4.3 million sq ft. End tenant not publicly identified; project marketed to hyperscalers. Rezoning includes decommissioning and site restoration plan requirement if dormant over one year. Coordinates are Newnan city centroid; actual site is along US-27 southwest of Newnan. A developer-commissioned fiscal study modeled roughly $488M in county and school property-tax abatements over 18 years, but the Coweta County Development Authority reported no incentive negotiations had occurred as of January 2025; no confirmed incentive agreement or job count has been published.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Tax abatements or other public subsidy
- Permanent jobs promised
Which document closes each gap
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Our reporting on this site
- Coweta County's Project Sail Lawsuit · Active litigation
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Project Oak Data Center (Walt Sanders Road) · Newnan · Undisclosed developer5 mi · Cancelled · Opposed
- Bridgeport Data Center Campus · Moreland · Undisclosed developer (Bridgeport Industrial Park)7 mi · Proposed
- Project Peach (CyrusOne Palmetto Data Center Campus) · Palmetto · CyrusOne (joint venture with North Coweta Investors)12 mi · Permitted · Opposed
- T5 @ Atlanta IV · Palmetto · T5 Data Centers12 mi · Proposed · 300 MW
- Microsoft Tyrone Campus (Project Rita) · Tyrone · Microsoft14 mi · Permitted · 96 MW · Contested
- Microsoft Fairwater Atlanta (Azure AI Superfactory) · Fayetteville · Microsoft20 mi · Operating · 1.5 GW · Contested
- Vantage Data Centers Westlake · South Fulton · Vantage Data Centers22 mi · Proposed
- Liberty Road Data Center Campus (EdgeConneX) · Villa Rica · EdgeConneX (applicant East Village Dothan LLC)25 mi · Cancelled · Opposed
Questions people ask about this site
Is there opposition to the Project Sail, Prologis Data Center Campus in Newnan?
Yes. Project Sail, Prologis Data Center Campus in Newnan, Coweta County, Georgia is or has been the subject of litigation over its siting, permitting, or operation. Pending, Coweta County Superior Court.
Has anyone filed a lawsuit over the Project Sail, Prologis Data Center Campus?
Yes. This site is recorded as being in litigation. The case, the court, and the filings we hold are listed on this page under the timeline and the sources.
How much water does Project Sail, Prologis Data Center Campus use?
6 million gallons a day is the reported figure on record. Cooling is recorded as evaporative. Expected to use 6 million gallons of water per day drawn from the Chattahoochee River
Who operates Project Sail, Prologis Data Center Campus, and how big is it?
Prologis is the operator on record. We hold 9 sites for that company across the registry. Capacity on record is 900 MW. The site is recorded at 800 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Project Sail, Prologis Data Center Campus," updated July 6, 2026, https://suedatacenters.org/data-centers/prologis-project-sail-coweta-ga.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/prologis-project-sail-coweta-ga, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.$17B Project Sail data center project approved south of Atlanta · Atlanta Journal-Constitution · retrieved July 6, 2026
- 2.Coweta Residents Sue to Block Project Sail Data Center · The Citizen · retrieved July 6, 2026
- 3.Project Sail, developer project overview · Prologis / Atlas Development · retrieved July 6, 2026
- 4.Coweta County's Project Sail Lawsuit: Residents Sue to Void a $17 Billion Data Center Rezoning · SueDataCenters.org · retrieved September 2, 2026
- 5.CBS News Atlanta: Coweta County residents file appeal to stop massive data center on protected rural land · cbsnews.com · retrieved September 2, 2026
- 6.11Alive: Coweta County data center project lawsuit · 11alive.com · retrieved September 2, 2026
- 7.Fortune: Data center water wars in Georgia and Arizona (May 13, 2026) · fortune.com · retrieved September 2, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation