Project Peach (CyrusOne Palmetto Data Center Campus)
Palmetto, Coweta County, Georgia · All 24 CyrusOne sites · Every CyrusOne case on our tracker
Project Peach (CyrusOne Palmetto Data Center Campus) is a permitted data center in Palmetto, Georgia (Coweta County), operated by CyrusOne (joint venture with North Coweta Investors). The public record puts it at 320 acres. It faces documented, organized local opposition.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Permitted
- Operator
- CyrusOne (joint venture with North Coweta Investors)
- Facility type
- Data center
- Location
- Palmetto, Coweta County, GA
- Coordinates
- 33.5182, -84.6693 (approximate)
- Power capacity
- Not established from a public source
- Land
- 320 acres
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- air
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- Opposed
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- April 15, 2025PermittedCoweta County Board of Commissioners approved the rezoning of ~320 acres from rural conservation to industrial by a 3-2 vote. Source: DeSmog
Opposition and litigation at this site
Yes. Organized local opposition to Project Peach (CyrusOne Palmetto Data Center Campus) in Palmetto, Coweta County, Georgia is documented in the public record, without a lawsuit on file in the sources we track. Residents packed the rezoning hearing in opposition; Palmetto's mayor asked commissioners to weigh the long-term cost to quality of life, environment and residents.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: opposed means documented, organized local opposition is the dominant signal on record.
Residents packed the rezoning hearing in opposition; Palmetto's mayor asked commissioners to weigh the long-term cost to quality of life, environment and residents. Coweta County later imposed a six-month moratorium on new data center proposals.
Power and water
Reported as air-cooled rather than water-cooled.
Notes on the record
Eight buildings planned, completion projected 2036. Distinct from the tracked T5 @ Atlanta IV, which is also at Palmetto but a different operator, site and jurisdiction (Fulton County).
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Tax abatements or other public subsidy
- Permanent jobs promised
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- T5 @ Atlanta IV · Palmetto · T5 Data Centers4 mi · Proposed · 300 MW
- Microsoft Tyrone Campus (Project Rita) · Tyrone · Microsoft5 mi · Permitted · 96 MW · Contested
- Project Oak Data Center (Walt Sanders Road) · Newnan · Undisclosed developer7 mi · Cancelled · Opposed
- Vantage Data Centers Westlake · South Fulton · Vantage Data Centers10 mi · Proposed
- Project Sail, Prologis Data Center Campus · Newnan · Prologis12 mi · Permitted · 900 MW · In litigation
- Microsoft Fairwater Atlanta (Azure AI Superfactory) · Fayetteville · Microsoft13 mi · Operating · 1.5 GW · Contested
- Flexential Atlanta - Douglasville 1 · Douglasville · Flexential15 mi · Operating · 22.5 MW
- Flexential Atlanta - Douglasville 2 · Douglasville · Flexential15 mi · Operating
Questions people ask about this site
Is there opposition to the Project Peach (CyrusOne Palmetto Data Center Campus) in Palmetto?
Yes. Organized local opposition to Project Peach (CyrusOne Palmetto Data Center Campus) in Palmetto, Coweta County, Georgia is documented in the public record, without a lawsuit on file in the sources we track. Residents packed the rezoning hearing in opposition; Palmetto's mayor asked commissioners to weigh the long-term cost to quality of life, environment and residents.
Has anyone filed a lawsuit over the Project Peach (CyrusOne Palmetto Data Center Campus)?
No lawsuit over Project Peach (CyrusOne Palmetto Data Center Campus) appears in the record we track as of August 28, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Project Peach (CyrusOne Palmetto Data Center Campus) use?
No water withdrawal figure for Project Peach (CyrusOne Palmetto Data Center Campus) is on record here. Cooling is recorded as air, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.
Who operates Project Peach (CyrusOne Palmetto Data Center Campus), and how big is it?
CyrusOne (joint venture with North Coweta Investors) is the operator on record. We hold 24 sites for that company across the registry. No capacity figure is on record for this site. The site is recorded at 320 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Project Peach (CyrusOne Palmetto Data Center Campus)," updated August 28, 2026, https://suedatacenters.org/data-centers/cyrusone-project-peach-palmetto-ga.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/cyrusone-project-peach-palmetto-ga, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Coweta County residents concerned over proposed 320-acre data center · FOX 5 Atlanta · retrieved August 28, 2026
- 2.How Data Center Developers Staked Their Claim in Rural Georgia · DeSmog · retrieved August 28, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us