Data Center Registry
T5 @ Atlanta IV
Palmetto, Fulton County, Georgia · All 8 T5 Data Centers sites · Every T5 Data Centers case on our tracker
T5 @ Atlanta IV is a proposed data center in Palmetto, Georgia (Fulton County), operated by T5 Data Centers. The public record puts it at announced August 28, 2024, 300 MW planned, 91 acres.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- T5 Data Centers
- Facility type
- Data center, AI use likely
- Location
- Palmetto, Fulton County, GA
- Coordinates
- 33.5480, -84.7240
- Power capacity
- 300 MW planned
- Land
- 91 acres
- Investment
- Not established from a public source
- Announced
- August 28, 2024
- Utility
- Not established from a public source
- Power source
- Grid
- Cooling
- Hybrid
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- May 23, 2025ProposedT5 refiled modified plans: 1.32M sq ft, 3 buildings, up to 300 MW; the original June 2024 filing (495K sq ft, 2 buildings) was withdrawn Source: Data Center Dynamics
- August 28, 2024ProposedLand acquisition finalized; 91-acre site already zoned for data-center use; use permit still required Source: PR Newswire
Opposition and litigation at this site
Nothing on record as of September 10, 2026. No lawsuit, organized opposition, or contested hearing over T5 @ Atlanta IV in Palmetto, Fulton County, Georgia appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Power and water
On-site electrical substation providing grid power; substation expected operational 2026.
Air and liquid cooling designed for high-density AI workloads.
Notes on the record
City discrepancy: the ledger cited Fairburn, but T5's own page and PR Newswire list Palmetto, GA; DCD describes it as Fairburn/Fulton County with a 91-acre site in Palmetto - site is on the Fairburn/Palmetto border in South Fulton County (I-85 and Gullatt Rd). Capacity: T5's page lists '200 MW available' (Phase 1) while the Aug 2024 land-acquisition PR cites '300 MW' campus total - 300 MW recorded as planned. No tenant disclosed (T5 is a wholesale/build-to-suit developer targeting hyperscalers; page cites AI/liquid-cooling suitability). Phase 1 construction targeted Q2 2027; on-site substation expected 2026. No investment or jobs figure disclosed. Coordinates approximate (I-85/Gullatt Rd corridor).
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Tax abatements or other public subsidy
- Permanent jobs promised
- How the community has received it
- Which utility serves it
Which document closes each gap
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Project Peach (CyrusOne Palmetto Data Center Campus) · Palmetto · CyrusOne (joint venture with North Coweta Investors)4 mi · Permitted · Opposed
- Project Oak Data Center (Walt Sanders Road) · Newnan · Undisclosed developer8 mi · Cancelled · Opposed
- Microsoft Tyrone Campus (Project Rita) · Tyrone · Microsoft9 mi · Permitted · 96 MW · Contested
- Vantage Data Centers Westlake · South Fulton · Vantage Data Centers11 mi · Proposed
- Project Sail, Prologis Data Center Campus · Newnan · Prologis12 mi · Permitted · 900 MW · In litigation
- Flexential Atlanta - Douglasville 1 · Douglasville · Flexential14 mi · Operating · 22.5 MW
- Google Douglasville Data Center · Douglasville · Google14 mi · Operating
- Vantage Data Centers Douglasville Campus · Douglasville · Vantage Data Centers14 mi · Proposed
Questions people ask about this site
Is there opposition to the T5 @ Atlanta IV data center in Palmetto?
Nothing on record as of September 10, 2026. No lawsuit, organized opposition, or contested hearing over T5 @ Atlanta IV in Palmetto, Fulton County, Georgia appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the T5 @ Atlanta IV data center?
No lawsuit over T5 @ Atlanta IV appears in the record we track as of September 10, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does T5 @ Atlanta IV use?
No water withdrawal figure for T5 @ Atlanta IV is on record here. Cooling is recorded as hybrid, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.
Who operates T5 @ Atlanta IV, and how big is it?
T5 Data Centers is the operator on record. We hold 8 sites for that company across the registry. Capacity on record is 300 MW. The site is recorded at 91 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "T5 @ Atlanta IV," updated September 10, 2026, https://suedatacenters.org/data-centers/t5-atlanta-iv-palmetto-ga.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/t5-atlanta-iv-palmetto-ga, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.T5 files to develop data center campus outside Atlanta, Georgia · Data Center Dynamics · retrieved July 7, 2026
- 2.T5 @ Atlanta IV - Official Operator Location Page · T5 Data Centers · retrieved July 7, 2026 · original offline, archived copy from July 14, 2026
- 3.T5 Finalizes Land Acquisition in Atlanta to Support a 300 MW Data Center Campus · PR Newswire · retrieved July 7, 2026
- 4.T5 Plotting Data Center Campus In Fairburn · Bisnow · retrieved July 7, 2026
- 5.T5 Data Centers pursues 495K square foot campus in Fairburn · Atlanta Journal-Constitution · retrieved July 7, 2026
- 6.T5 @ Atlanta IV, operator location page (archived 2026-07-14) · T5 Data Centers, via Internet Archive Wayback Machine · retrieved September 10, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us