T5 Data Centers Lawsuits: The Grayslake Case Seeking to Void a 472 Acre, 1.55 Gigawatt Campus

T5 Data Centers, the data center developer and builder behind T5@Chicago IV, is a defendant in a July 2026 Lake County suit asking a judge to void the Village of Grayslake's approvals for a 472 acre, roughly 1.55 gigawatt campus. The complaint alleges a 61 second hearing and code-name-only notices. T5 says it followed the letter and intent of every law. The record, sourced.

Overhead view of a dense curving subdivision around lakes on the west side of a straight north-south road, with open farm fields stretching east of the road.

fields rezoned for a data center campus in Grayslake, Illinois, photographed 2019-08-09. Saddlebrook Farms on the west side of Alleghany Road, and the open fields across from it where 472 acres lost their residential zoning in about a minute. The imagery predates the vote.

USDA Farm Service Agency / USGS National Map, National Agriculture Imagery Program. Cropped from NAIP 0.6 m aerial imagery, scene m_4208848_ne_16_060_20190809. (original)

T5 Data Centers on the tracker

Tracker entries
One: Preservation of Community Well-being Collective LLC and nine Lake County residents v. Village of Grayslake, T5 Data Centers LLC, and Alter Asset Management Company, filed July 31, 2026 in Lake County Circuit Court
What kind of operator
Developer, general contractor, and operations provider rather than a hyperscaler. Its own site describes divisions for data center development and ownership, construction services, and facilities operations
Footprint
Founded in 2008. Its own site claims 22 data centers developed, about 4 million square feet, general contractor licensure in 48 states, and more than 3 gigawatts of capacity managed
Project at issue
T5@Chicago IV at the Cornerstone development in Grayslake, Illinois: 472 acres, more than 10 million square feet, roughly 1.55 gigawatts from ComEd with diesel backup
Company response
Chief executive Pete Marin said T5 has followed the letter and intent of every law and regulation every step of the way, that it will respond to legal claims in court, and that it volunteered to suspend its wetland permit application indefinitely

Key Takeaways

  • T5 Data Centers appears in one tracker entry, the July 31, 2026 Lake County, Illinois suit seeking to void the Village of Grayslake's approvals for T5@Chicago IV. The claims are unproven and the case is pending, with a status hearing set for October 30, 2026.
  • The case is not about noise, water, or emissions. It is a procedural challenge to how the approvals happened: allegedly defective public notices that named only a project code, a September 2024 hearing that removed the site's remaining residential uses in 61 seconds, an Open Meetings Act claim, and approval of a use the village zoning code does not list.
  • T5 rejects that account. Chief executive Pete Marin has said the company followed the letter and intent of every law and regulation at every step, will answer the claims in court, and volunteered to suspend its federal wetland permit application indefinitely.
  • T5 is a developer and builder rather than a hyperscaler, which is why the village and the master developer are co-defendants. In this kind of case the operator is named because it holds the approvals, not because a court has found it did anything wrong.
  • The remedy sought is the one that has produced the biggest resident wins nationally: void the approvals rather than regulate the building. It is the same shape of relief that undid the Prince William Digital Gateway rezoning in Virginia.

Has T5 Data Centers been sued? Yes, once on our tracker, and the case aims at paperwork rather than pollution. On July 31, 2026, the Preservation of Community Well-being Collective and nine Lake County residents sued the Village of Grayslake, T5 Data Centers LLC, and master developer Alter Asset Management in Lake County Circuit Court, asking a judge to declare the village's 2024 and 2025 approvals for T5@Chicago IV invalid, void the development agreement, and enjoin further permits. The project is enormous: 472 acres at the Cornerstone development, more than 10 million square feet, and roughly 1.55 gigawatts of power from ComEd with diesel backup. The complaint's theory is that the public never knew what was being approved, pointing to notices that identified the project only by its code name and to a September 9, 2024 hearing that eliminated the site's remaining residential uses in 61 seconds with no public comment. T5 disputes it. Chief executive Pete Marin says the company has followed the letter and intent of every law and regulation every step of the way, that it will respond to the claims in court, and that it volunteered to suspend its wetland permit application indefinitely. A status hearing is set for October 30, 2026.

Every case on the tracker

  • Active litigationIllinois
    The Grayslake Lawsuit: Nine Neighbors Sue to Void a 472 Acre, 1.55 Gigawatt Data Center Campus

    Pending, Lake County Circuit Court (filed July 31, 2026); status hearing October 30, 2026

    On July 31, 2026, a residents' collective and nine Lake County homeowners sued the Village of Grayslake, T5 Data Centers, and Alter Asset Management to void approvals for T5@Chicago IV, a 472 acre, 10 million square foot campus drawing about 1.55 gigawatts. The suit alleges a 61 second hearing, code-name-only public notices, an Open Meetings Act violation, and approvals for a use the zoning code does not contain. What the case says and what it means for anyone facing a fast-tracked approval.

Every T5 Data Centers site in the registry

9 sites on the public record in 6 states: 5 operating, 2 under construction, 1 permitted, 1 proposed. 1 carry documented opposition or litigation. 1.9 GW planned. Most contested first.

Free case review

Living near a T5 Data Centers data center? See if you have a case.

What T5 is, and why that shapes the case

T5 is not a hyperscaler and does not own the workloads that would run at Grayslake. On its own account it is a developer, a data center general contractor, and an operations provider, founded in 2008, with divisions covering development and ownership, construction, and facilities management. Its own site claims 22 data centers developed, roughly 4 million square feet, general contractor licensure in 48 states, and more than 3 gigawatts of capacity managed. That profile explains the shape of the litigation: a developer's exposure is concentrated at the approval stage, before a building exists to make noise or draw water, which is precisely where this case sits.

It also explains the co-defendants. The suit names the Village of Grayslake, which granted the approvals, and Alter Asset Management, which assembled the 641 acre Cornerstone development, alongside T5. When residents want approvals voided, they have to sue the body that issued them and the parties who hold them. Being named in a case like this is not an allegation of harm to any neighbor's health or property; it is a consequence of holding the entitlement under challenge. Our full report on the Grayslake case covers the complaint and the response.

The procedural playbook, and what T5 says about it

The plaintiffs plead four things: that the approvals departed from the village's comprehensive planning framework so sharply as to violate substantive due process; that public participation was inadequate because notices identified the project only as T5@Chicago IV and the hearing that removed the remaining residential uses lasted 61 seconds; that officials violated the Illinois Open Meetings Act by doing public business on personal email and devices; and that the village approved a data center under a zoning code containing no data center category. None of it has been adjudicated.

T5's answer is that the process was clean. Marin has said publicly that the company followed the letter and intent of every law and regulation every step of the way, that it will respond to legal claims in that forum, and that the project would generate well over $1.5 billion in new taxes and fees for Grayslake and Lake County, including more than half a billion dollars for local schools, plus more than 1,600 jobs. He also said the company volunteered to suspend its wetland remediation permit application indefinitely, which pauses a federal approval while the state case runs.

The case matters beyond Illinois because the remedy is the strong one. Voiding approvals is what killed the Prince William Digital Gateway in Virginia over a public notice defect, and the same counsel filed the Joliet Technology Center case two months earlier, making Grayslake the second front in a coordinated Illinois challenge to fast-tracked approvals. If a large project near you is moving, our guide to fighting a proposed data center and our zoning appeal deadlines guide are the place to start, and our free case review connects you with an independent attorney in our network who handles data center cases in your state, at no cost and with no obligation.

Free case review

Living near a T5 Data Centers data center?

Frequently asked questions

Has T5 Data Centers been sued?

Yes. On July 31, 2026, the Preservation of Community Well-being Collective and nine Lake County residents sued the Village of Grayslake, T5 Data Centers LLC, and Alter Asset Management in Lake County Circuit Court, seeking to void the approvals for the T5@Chicago IV campus. The suit alleges defective public notice, a 61 second hearing, an Open Meetings Act violation, and approval of a use the zoning code does not contain. It is pending, with a status hearing set for October 30, 2026, and none of the allegations has been proven.

What has T5 Data Centers said about the Grayslake lawsuit?

Chief executive Pete Marin said the company has followed the letter and intent of every law and regulation every step of the way and that it will respond to any legal claims in court. He also said T5 volunteered to suspend its wetland remediation permit application indefinitely, and he described the project as generating well over $1.5 billion in new taxes and fees for the village and county.

What kind of company is T5 Data Centers?

T5 is a data center developer, general contractor, and operations provider founded in 2008, rather than a hyperscaler or a cloud company. Its own site describes divisions for development and ownership, construction services, and facilities operations, and claims 22 data centers developed, about 4 million square feet, general contractor licensure in 48 states, and more than 3 gigawatts of capacity managed.

Is a T5 Data Centers data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us