Data Center Registry
T5 Chicago IV (CHI IV)
Grayslake, Lake County, Illinois · All 11 T5 Data Centers sites · Every T5 Data Centers case on our tracker
T5 Chicago IV (CHI IV) is a data center under construction in Grayslake, Illinois (Lake County), operated by T5 Data Centers. The public record puts it at announced 2026, 1.6 GW planned, 472 acres, a reported $250 million investment. It is or has been the subject of litigation over its siting, permitting, or operation.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
What our reporting adds
Our case file adds the July 31, 2026 lawsuit, the 61 second hearing allegation and the status hearing date, and sets the reception to in litigation. Our case file documents this site. Pending, Lake County Circuit Court (filed July 31, 2026); status hearing October 30, 2026. The base record lists the reception as contested; the case record sets it to litigation.
Facility record
Under construction
- Operator
- T5 Data Centers
- Facility type
- Data center, AI use confirmed
- Location
- Grayslake, Lake County, IL
- Coordinates
- 42.3442, -88.0417 (approximate)
- Power capacity
- 1.6 GW planned
- Land
- 472 acres
- Investment
- $250 million
- Announced
- 2026
- Utility
- ComEd
- Power source
- Grid
- Cooling
- Closed loop
- Water use
- Not established from a public source
- Jobs
- 20 permanent
- Public subsidy
- Illinois Data Center Investment Program, $16 million, Illinois, 2025
- Community reception
- In litigation
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- May 7, 2026Under constructionVillage officials maintained that approvals for the T5 Chicago IV campus were in order, and earthmoving had started on the first piece of the site (Hoodline, May 7, 2026); residents said they plan to pursue appeals. Source: Hoodline
- 2026ProposedT5 announced its CHI IV campus in Grayslake (Lake County): up to 1.2 GW IT / 1.6 GW secured utility power; Phase 1 (3 × 60 MW) targeted Q4 2027 Source: Data Center Dynamics
Opposition and litigation at this site
Yes. T5 Chicago IV (CHI IV) in Grayslake, Lake County, Illinois is or has been the subject of litigation over its siting, permitting, or operation. A residents' collective and nine Lake County homeowners sued Grayslake, T5 Data Centers and Alter Asset Management on July 31, 2026 in Lake County Circuit Court to void the approvals.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: in litigation means the facility is or has been the subject of a lawsuit related to its siting, permitting, or operation.
A residents' collective and nine Lake County homeowners sued Grayslake, T5 Data Centers and Alter Asset Management on July 31, 2026 in Lake County Circuit Court to void the approvals. The complaint alleges that a September 9, 2024 hearing that eliminated the site's remaining residential uses lasted 61 seconds with no public comment, and that public notices identified the project only by its code name. Status hearing October 30, 2026.
Power and water
1.6 GW of secured ComEd utility power via an on-site substation.
Village FAQ: closed-loop water cooling, with projected campus-wide average daily use of about 50,000 gallons for ordinary domestic purposes (roughly 2,500-3,500 gallons per building per day). Supply is Lake Michigan water via the Central Lake County Joint Action Water Agency, so no private wells are affected, and there is no groundwater discharge. As the campus is under construction, no water-use figure is recorded.
Public money on the record
| Program | Amount | Granted by | Year |
|---|---|---|---|
| Illinois Data Center Investment Program | $16 million | Illinois | 2025 |
Notes on the record
CHI IV in Grayslake, Lake County (~40 mi north of Chicago): up to 1.2 GW IT capacity with 1.6 GW secured ComEd power; envisions 20 × 60 MW buildings, Phase 1 (3 × 60 MW) targeted Q4 2027. Earthmoving had started on the first piece of the site by May 2026 (Hoodline), and the record is listed as under construction. The Village of Grayslake's FAQ, updated August 18, 2026, says the approved campus is located on 473 acres in the Peterson Road corridor; T5's May 2024 announcement described a 160-acre site supporting up to 480 MW of critical IT capacity, which is a planned figure, not capacity in operation. Distinct from T5's Palmetto, GA campus. Coordinates are the Grayslake area centroid.
Our reporting on this site
- The Grayslake Lawsuit · Active litigation
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Volo Data Center · Volo · Chirisa Technology Parks5 mi · Operating
- Microsoft Kenosha Data Center Campus · Kenosha · Microsoft15 mi · Proposed · Contested
- Microsoft Hoffman Estates Data Center · Hoffman Estates · Microsoft19 mi · Operating
- Brennan Barrington Hills Data Center · Barrington Hills · Brennan Investment Group19 mi · Cancelled · Opposed
- Compass Datacenters Hoffman Estates Campus · Hoffman Estates · Compass Datacenters21 mi · Under construction
- CloudHQ Mount Prospect (ORD) Campus · Mount Prospect · CloudHQ21 mi · Under construction
- T5 Chicago II · Elk Grove Village · T5 Data Centers22 mi · Operating
- Prime ORD Chicago Campus · Elk Grove Village · Prime Data Centers23 mi · Under construction · 175 MW · Supported
Questions people ask about this site
Is there opposition to the T5 Chicago IV (CHI IV) data center in Grayslake?
Yes. T5 Chicago IV (CHI IV) in Grayslake, Lake County, Illinois is or has been the subject of litigation over its siting, permitting, or operation. A residents' collective and nine Lake County homeowners sued Grayslake, T5 Data Centers and Alter Asset Management on July 31, 2026 in Lake County Circuit Court to void the approvals.
Has anyone filed a lawsuit over the T5 Chicago IV (CHI IV) data center?
Yes. This site is recorded as being in litigation. The case, the court, and the filings we hold are listed on this page under the timeline and the sources.
How much water does T5 Chicago IV (CHI IV) use?
No water withdrawal figure for T5 Chicago IV (CHI IV) is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.
Who operates T5 Chicago IV (CHI IV), and how big is it?
T5 Data Centers is the operator on record. We hold 11 sites for that company across the registry. Capacity on record is 1.6 GW. The site is recorded at 472 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "T5 Chicago IV (CHI IV)," updated October 28, 2026, https://suedatacenters.org/data-centers/t5-chicago-iv-grayslake-il.
Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/t5-chicago-iv-grayslake-il, retrieved October 29, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.T5 plans five gigawatt-scale data center campuses, announces Chicago campus · Data Center Dynamics · retrieved July 7, 2026
- 2.Despite village approvals, legal action expected against Grayslake data center · Daily Herald · retrieved August 3, 2026
- 3.Grayslake T5 Data Center Moves Ahead Amid Local Protests · Hoodline · retrieved July 18, 2026
- 4.Data Center Could Be Largest Lake County, Ill., Development · Government Technology · retrieved September 12, 2026
- 5.Approved T5 Data Center Campus FAQ (updated June 5, 2026) · Village of Grayslake · retrieved August 3, 2026 · original offline, no archived copy found
- 6.Data Center Investment Program 2025 Annual Report, T5@Chicago IV, LP, Grayslake (2025 MOU) · Illinois Department of Commerce and Economic Opportunity · retrieved September 25, 2026
- 7.Approved Village of Grayslake Data Center Campus FAQs (updated 18 August 2026) · Village of Grayslake, Illinois · retrieved September 12, 2026 · original offline, archived copy from April 20, 2026
- 8.Illinois Data Centers, T5 Chicago IV, Grayslake, 1.2 GW IT (Phase 1: 480 MW) · Coalition for Responsible Data Centers · retrieved September 25, 2026
- 9.Correction source · retrieved October 15, 2026
- 10.The Grayslake Lawsuit: Nine Neighbors Sue to Void a 472 Acre, 1.55 Gigawatt Data Center Campus · SueDataCenters.org · retrieved September 2, 2026
- 11.Lake and McHenry County Scanner: Lake County residents file lawsuit to block 472 acre data center campus in Grayslake (August 8, 2026) · lakemchenryscanner.com · retrieved September 2, 2026
- 12.Shaw Local: Lawsuit against Joliet data center heading to court hearing (August 18, 2026) · shawlocal.com · retrieved September 2, 2026
- 13.Programs.com: Data center moratoriums by state, tracker and statistics (as of August 26, 2026) · programs.com · retrieved September 2, 2026
- 14.The Grayslake lawsuit: the 61 second hearing · SueDataCenters.org · retrieved September 5, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us