CloudHQ Mount Prospect (ORD) Campus

Mount Prospect, Cook County, Illinois · All 4 CloudHQ sites

Under constructionNo reception on recordRecord updated September 10, 2026

CloudHQ Mount Prospect (ORD) Campus is a data center under construction in Mount Prospect, Illinois (Cook County), operated by CloudHQ. The public record puts it at announced 2022, 49.7 acres, a reported $2.5 billion investment.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Under construction

Operator
CloudHQ
Facility type
Data center
Location
Mount Prospect, Cook County, IL
Coordinates
42.0550, -87.9350 (approximate)
Power capacity
Not established from a public source
Land
49.7 acres
Investment
$2.5 billion
Announced
2022
Utility
ComEd
Power source
Grid
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. July 2026
    Under construction
    Mid-permitting the revised design (~3,700 drawing sheets, 1,500+ pages of structural calcs); village hired outside firm HR Green to review it. Cranes active on the fenced 50-acre site as of January 2026. Source: Daily Herald
  2. October 2025
    Under construction
    Village board approved a revised plan consolidating the original three two-story buildings into two three-story buildings plus a second electrical substation. First building targeted for 2027, second for end of 2030. Source: Daily Herald
  3. August 2022
    Under construction
    Groundbreaking with ComEd on hyperscale campus Source: DatacenterDynamics

Opposition and litigation at this site

Nothing on record as of September 10, 2026. No lawsuit, organized opposition, or contested hearing over CloudHQ Mount Prospect (ORD) Campus in Mount Prospect, Cook County, Illinois appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

Notes on the record

$2.5B, ~1.5 million sq ft across three two-story hyperscale buildings (each >80 MW) on a 49.7-acre site; ComEd grid partnership. Update: the village board approved a revised plan (~Oct 2025) consolidating the original three two-story buildings into two three-story buildings plus a second electrical substation, superseding the building-count description above; confirmed delivery targets are the first building in 2027 and the second by end of 2030. As of July 2026, CloudHQ was mid-permitting the revised design (~3,700 drawing sheets, 1,500+ pages of structural calcs); the village hired outside firm HR Green to review it. Construction is active, with cranes on the fenced 50-acre site as of January 2026. Public-reception check (2026-09-10): Could not get past a paywall/block for the Daily Herald's Mount Prospect coverage or the original CloudHQ groundbreaking press release (both 403'd). Notable circumstantial signal: the Village of Mount Prospect maintains its own dedicated 'Community Information and Fact Check Portal' page specifically for this project (URL found via search, itself 403'd on fetch), which typically indicates the village has been fielding enough resident questions/concerns to warrant an official FAQ/rebuttal page -- but I could not retrieve its actual content, so I am not asserting a status from an inference I couldn't verify. Also found (via search, not independently fetched) reporting that Illinois data-center opposition broadly 'escalates' statewide and that the village sought outside help on Biometric Information Privacy Act (BIPA)-related permitting questions, neither of which I could confirm as specific to community opposition at this site. Reporting 'unknown' rather than guessing.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • How the community has received it
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the CloudHQ Mount Prospect (ORD) Campus in Mount Prospect?

Nothing on record as of September 10, 2026. No lawsuit, organized opposition, or contested hearing over CloudHQ Mount Prospect (ORD) Campus in Mount Prospect, Cook County, Illinois appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the CloudHQ Mount Prospect (ORD) Campus?

No lawsuit over CloudHQ Mount Prospect (ORD) Campus appears in the record we track as of September 10, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does CloudHQ Mount Prospect (ORD) Campus use?

No water withdrawal figure for CloudHQ Mount Prospect (ORD) Campus is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates CloudHQ Mount Prospect (ORD) Campus, and how big is it?

CloudHQ is the operator on record. We hold 4 sites for that company across the registry. No capacity figure is on record for this site. The site is recorded at 49.7 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "CloudHQ Mount Prospect (ORD) Campus," updated September 10, 2026, https://suedatacenters.org/data-centers/cloudhq-mount-prospect-ord-il.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/cloudhq-mount-prospect-ord-il, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.CloudHQ breaks ground on 1.5 million sq ft campus in Mount Prospect, Illinois · DatacenterDynamics · retrieved August 3, 2026
  2. 2.CloudHQ Breaks Ground on $2.5 Billion Chicago Data Center Campus · Data Center Frontier · retrieved August 3, 2026
  3. 3.ComEd joins with CloudHQ to build $2.5B data center in northern Illinois · Daily Energy Insider · retrieved August 3, 2026
  4. 4.Mount Prospect data center developer prepared to donate $3 million for recreation, street upgrades · Daily Herald · retrieved August 8, 2026
  5. 5.Mount Prospect hires outside firm to handle data center permitting · Daily Herald · retrieved July 16, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us