Steward Drive Data Center (Rochelle) is a cancelled data center in Rochelle, Illinois (Ogle County), operated by Midwest Power Investors LLC (LFF Industrial). The public record puts it at 150 MW planned. It faces documented, organized local opposition.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Cancelled

Operator
Midwest Power Investors LLC (LFF Industrial)
Facility type
Data center
Location
Steward Drive, Rochelle, Ogle County, IL
Coordinates
41.8979, -89.0482 (approximate)
Power capacity
150 MW planned
Land
Not established from a public source
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Not established from a public source
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Opposed
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. September 12, 2026
    Cancelled
    Rochelle City Council rejected the development agreement 0-7 on 27 April 2026 after tabling it in March. Source: Rockford News First

Opposition and litigation at this site

Yes. Organized local opposition to Steward Drive Data Center (Rochelle) in Rochelle, Ogle County, Illinois is documented in the public record, without a lawsuit on file in the sources we track. Residents raised concerns about environmental impact and utility bills during a roughly two-year review; the mayor asked the council to vote the development agreement down.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: opposed means documented, organized local opposition is the dominant signal on record.

Residents raised concerns about environmental impact and utility bills during a roughly two-year review; the mayor asked the council to vote the development agreement down.

Source: Rockford News First

Notes on the record

Proposed along Steward Drive in Rochelle, which operates its own municipal electric utility. The initial phase would have required at least 48 MW, with later phases expanding to about 150 MW; the recorded planned capacity is the full-build figure. The mayor cited projected Illinois capacity shortfalls from 2029.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Land area
  • Which utility serves it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Land area
The rezoning application, the plat, or the deed recorded with the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Steward Drive Data Center (Rochelle) in Rochelle?

Yes. Organized local opposition to Steward Drive Data Center (Rochelle) in Rochelle, Ogle County, Illinois is documented in the public record, without a lawsuit on file in the sources we track. Residents raised concerns about environmental impact and utility bills during a roughly two-year review; the mayor asked the council to vote the development agreement down.

Has anyone filed a lawsuit over the Steward Drive Data Center (Rochelle)?

No lawsuit over Steward Drive Data Center (Rochelle) appears in the record we track as of September 12, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Steward Drive Data Center (Rochelle) use?

No water withdrawal figure for Steward Drive Data Center (Rochelle) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Steward Drive Data Center (Rochelle), and how big is it?

Midwest Power Investors LLC (LFF Industrial) is the operator on record. Capacity on record is 150 MW.

How to cite this page

SueDataCenters.org Data Center Registry, "Steward Drive Data Center (Rochelle)," updated September 12, 2026, https://suedatacenters.org/data-centers/midwest-power-investors-rochelle-il.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/midwest-power-investors-rochelle-il, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Rochelle City Council unanimously rejects data center proposal · Rockford News First · retrieved September 12, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us