KARIS DeKalb Campus (Peace and Gurler Roads) is a permitted data center in DeKalb, Illinois (DeKalb County), operated by Karis Acquisitions.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Permitted

Operator
Karis Acquisitions
Facility type
Data center
Location
DeKalb, DeKalb County, IL
Coordinates
41.8930, -88.7242 (approximate)
Power capacity
Not established from a public source
Land
Not established from a public source
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Not established from a public source
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. July 22, 2024
    Permitted
    DeKalb City Council approved an amendment to Ordinance 2023-038 to accommodate a 1,750,000 sq ft data center in seven buildings at the NE corner of Peace and Gurler Roads; still carried on the city's project list as of 7/15/2026. Source: City of DeKalb

Opposition and litigation at this site

Nothing on record as of November 4, 2026. No lawsuit, organized opposition, or contested hearing over KARIS DeKalb Campus (Peace and Gurler Roads) in DeKalb, DeKalb County, Illinois appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

People and entities in the record

  • Andre Powell · public_official via DeKalb City Council

    Member of the DeKalb City Council; voted for Ordinance 2024-035 amending the agreement for the Goldin Property at Gurler and Peace Roads to accommodate a data center (Karis Acquisitions LLC). Outcome: approved 8-0 by roll call (2024-07-22).

    Source
  • Barb Larson · public_official via DeKalb City Council

    Member of the DeKalb City Council; voted for Ordinance 2024-035 amending the agreement for the Goldin Property at Gurler and Peace Roads to accommodate a data center (Karis Acquisitions LLC). Outcome: approved 8-0 by roll call (2024-07-22).

    Source
  • Carolyn Zasada · public_official via DeKalb City Council

    Member of the DeKalb City Council; voted for Ordinance 2024-035 amending the agreement for the Goldin Property at Gurler and Peace Roads to accommodate a data center (Karis Acquisitions LLC). Outcome: approved 8-0 by roll call (2024-07-22).

    Source
  • Cohen Barnes · public_official via DeKalb City Council

    Mayor of DeKalb; voted for Ordinance 2024-035 amending the agreement for the Goldin Property at Gurler and Peace Roads to accommodate a data center (Karis Acquisitions LLC). Outcome: approved 8-0 by roll call (2024-07-22).

    Source
  • Greg Perkins · public_official via DeKalb City Council

    Member of the DeKalb City Council; voted for Ordinance 2024-035 amending the agreement for the Goldin Property at Gurler and Peace Roads to accommodate a data center (Karis Acquisitions LLC). Outcome: approved 8-0 by roll call (2024-07-22).

    Source
  • John Walker · public_official via DeKalb City Council

    Member of the DeKalb City Council; voted for Ordinance 2024-035 amending the agreement for the Goldin Property at Gurler and Peace Roads to accommodate a data center (Karis Acquisitions LLC). Outcome: approved 8-0 by roll call (2024-07-22).

    Source
  • Mike Verbic · public_official via DeKalb City Council

    Member of the DeKalb City Council; voted for Ordinance 2024-035 amending the agreement for the Goldin Property at Gurler and Peace Roads to accommodate a data center (Karis Acquisitions LLC). Outcome: approved 8-0 by roll call (2024-07-22).

    Source
  • Tracy Smith · public_official via DeKalb City Council

    Member of the DeKalb City Council; voted for Ordinance 2024-035 amending the agreement for the Goldin Property at Gurler and Peace Roads to accommodate a data center (Karis Acquisitions LLC). Outcome: approved 8-0 by roll call (2024-07-22).

    Source

Notes on the record

Seven-building, 1,750,000 sq ft campus. Coordinates are the Peace Road / Gurler Road intersection (OSM); the approval describes the NE corner, so the true footprint lies north-east of this point. No megawatt figure appears in the city record.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Land area
  • How the community has received it
  • Which utility serves it
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Land area
The rezoning application, the plat, or the deed recorded with the county.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Tell us about your situation

Living near KARIS DeKalb Campus (Peace and Gurler Roads)?

Tell us the basics. Where a participating attorney in your state is available, we may share your information with them with your consent. Free, no obligation, and no guarantee anyone will contact you.

Questions people ask about this site

Is there opposition to the KARIS DeKalb Campus (Peace and Gurler Roads) in DeKalb?

Nothing on record as of November 4, 2026. No lawsuit, organized opposition, or contested hearing over KARIS DeKalb Campus (Peace and Gurler Roads) in DeKalb, DeKalb County, Illinois appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the KARIS DeKalb Campus (Peace and Gurler Roads)?

No lawsuit over KARIS DeKalb Campus (Peace and Gurler Roads) appears in the record we track as of November 4, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does KARIS DeKalb Campus (Peace and Gurler Roads) use?

No water withdrawal figure for KARIS DeKalb Campus (Peace and Gurler Roads) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates KARIS DeKalb Campus (Peace and Gurler Roads), and how big is it?

Karis Acquisitions is the operator on record. No capacity figure is on record for this site.

How to cite this page

SueDataCenters.org Data Center Registry, "KARIS DeKalb Campus (Peace and Gurler Roads)," updated November 4, 2026, https://suedatacenters.org/data-centers/karis-dekalb-campus-il.

Facility data from Compute Atlas (E. Kubiak), version 1.35.1 (November 2, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/karis-dekalb-campus-il, retrieved November 5, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.City of DeKalb Zoning & Development Projects list as of 7/15/2026, Steven Goldin and Karis Acquisitions, NE Corner of Peace and Gurler Roads, 1,750,000 sq ft data center in seven buildings, approved 7/22/24 · City of DeKalb · retrieved September 25, 2026 · original offline, archived copy from November 10, 2026
  2. 2.City of DeKalb Zoning & Development Projects list as of 3/18/2026 (same entry) · City of DeKalb · retrieved September 25, 2026 · original offline, archived copy from November 3, 2026
  3. 3.DeKalb City Council regular meeting minutes, July 22, 2024 · City of DeKalb · retrieved November 4, 2026

Is a data center disrupting your home?

Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.

  • Tell us about your situation
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us