Meyer data center (Yorkville Nexus V LLC), Yorkville

Yorkville, Kendall County, Illinois

CancelledNo reception on recordRecord updated November 5, 2026

Meyer data center (Yorkville Nexus V LLC), Yorkville is a cancelled data center in Yorkville, Illinois (Kendall County), operated by Undisclosed developer (Yorkville Nexus V LLC / Green Door Capital). The public record puts it at 91 acres.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Cancelled

Operator
Undisclosed developer (Yorkville Nexus V LLC / Green Door Capital)
Facility type
Data center
Location
Yorkville, Kendall County, IL
Coordinates
41.6906, -88.4725 (approximate)
Power capacity
Not established from a public source
Land
91 acres
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Not established from a public source
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. April 14, 2026
    Cancelled
    The petitioner formally requested to withdraw the rezoning application; the mayor announced the withdrawal at the April 14 City Council meeting. Source: United City of Yorkville, Illinois
  2. March 24, 2026
    Proposed
    Yorkville City Council tabled the rezoning vote for the Meyer property. Source: Shaw Local

Opposition and litigation at this site

Nothing on record as of November 5, 2026. No lawsuit, organized opposition, or contested hearing over Meyer data center (Yorkville Nexus V LLC), Yorkville in Yorkville, Kendall County, Illinois appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

Notes on the record

Proposed rezoning of two western parcels (PINs 02-18-200-004 and 02-17-100-004, about 91 acres) from R-4 multi-family to M-2 manufacturing for a future data center, south of Corneils Road and east of Beecher Road, west of the Caledonia subdivision; petitioner Matt Gilbert for owner Yorkville Nexus V LLC (Green Door Capital); no end user was named and a PUD was to follow. An earlier version covered about 130 acres. The Plan Commission voted against it on 2026-01-14, the City Council tabled it on 2026-03-24, and the petitioner withdrew it in April 2026 after losing Council support. Distinct from the CyrusOne Yorkville campus. The pin is the Corneils Rd / Beecher Rd intersection from Census TIGER road geometry, not a parcel centroid, and is approximate.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • How the community has received it
  • Which utility serves it
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Tell us about your situation

Living near Meyer data center (Yorkville Nexus V LLC), Yorkville?

Tell us the basics. Where a participating attorney in your state is available, we may share your information with them with your consent. Free, no obligation, and no guarantee anyone will contact you.

Questions people ask about this site

Is there opposition to the Meyer data center (Yorkville Nexus V LLC), Yorkville in Yorkville?

Nothing on record as of November 5, 2026. No lawsuit, organized opposition, or contested hearing over Meyer data center (Yorkville Nexus V LLC), Yorkville in Yorkville, Kendall County, Illinois appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the Meyer data center (Yorkville Nexus V LLC), Yorkville?

No lawsuit over Meyer data center (Yorkville Nexus V LLC), Yorkville appears in the record we track as of November 5, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Meyer data center (Yorkville Nexus V LLC), Yorkville use?

No water withdrawal figure for Meyer data center (Yorkville Nexus V LLC), Yorkville is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Meyer data center (Yorkville Nexus V LLC), Yorkville, and how big is it?

Undisclosed developer (Yorkville Nexus V LLC / Green Door Capital) is the operator on record. No capacity figure is on record for this site. The site is recorded at 91 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Meyer data center (Yorkville Nexus V LLC), Yorkville," updated November 5, 2026, https://suedatacenters.org/data-centers/meyer-yorkville-il.

Facility data from Compute Atlas (E. Kubiak), version 1.35.1 (November 2, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/meyer-yorkville-il, retrieved November 5, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Meyer (Rezone), Current Projects and Public Hearings · United City of Yorkville, Illinois · retrieved November 5, 2026
  2. 2.Yorkville tables vote on 80-acre data center near Caledonia subdivision · Shaw Local · retrieved November 5, 2026
  3. 3.Data center developer drops proposal after losing Yorkville City Council support · Shaw Local · retrieved November 5, 2026

Is a data center disrupting your home?

Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.

  • Tell us about your situation
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us