Data Center Registry
CyrusOne CHI1-CHI3 (Aurora)
Aurora, Kane County, Illinois · All 24 CyrusOne sites · Every CyrusOne case on our tracker
CyrusOne CHI1-CHI3 (Aurora) is an operating data center in Aurora, Illinois (Kane County), operated by CyrusOne. The public record puts it at 109 MW operating.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Operating
- Operator
- CyrusOne
- Facility type
- Data center, AI use likely
- Location
- Aurora, Kane County, IL
- Coordinates
- 41.7966, -88.2438
- Power capacity
- 109 MW operating
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- ComEd
- Power source
- Grid
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Opposition and litigation at this site
Nothing on record as of August 16, 2026. No lawsuit, organized opposition, or contested hearing over CyrusOne CHI1-CHI3 (Aurora) in Aurora, Kane County, Illinois appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Power and water
CHI1-CHI3 in Aurora, IL run on the standard ComEd grid. CyrusOne's own back-up generation schedule page describes working with ComEd to reduce diesel generator run time (standard backup/demand-response practice, not a defining clean-energy procurement). No site-specific solar/wind/nuclear PPA found for this campus.
Notes on the record
Confirmed at 2905 Diehl Road, Aurora, IL via aggregator cross-reference; operator directory page also lists Aurora IL: CHI1-CHI3. AI/HPC (likely): Aurora campus AI-optimized via CyrusOne Intelliscale high-density design.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- How the community has received it
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Edged Chicago Campus, Aurora (ORD01) · Aurora · Edged US2 mi · Under construction · 72 MW · Mixed reception
- Hut 8 Batavia Data Center · Batavia · Batavia DC Corp (Hut 8 Corp subsidiary)5 mi · Under construction · 50 MW · Mixed reception
- Centersquare ORD4 (Lisle) · Lisle · Centersquare (Csquare)8 mi · Operating
- Project Cardinal Data Center Campus · Yorkville · Pioneer Development LLC13 mi · Permitted · 1.8 GW · In litigation
- Equinix CH7 · Westmont · Equinix14 mi · Operating
- Project Steel Data Center Campus · Yorkville · Prologis14 mi · Permitted
- Project Kilo Data Center (South Elgin) · South Elgin · White Rose Partners14 mi · Proposed · Opposed
- CyrusOne Yorkville Technology Campus (CHI-11) · Yorkville · CyrusOne15 mi · Under construction
Questions people ask about this site
Is there opposition to the CyrusOne CHI1-CHI3 (Aurora) data center in Aurora?
Nothing on record as of August 16, 2026. No lawsuit, organized opposition, or contested hearing over CyrusOne CHI1-CHI3 (Aurora) in Aurora, Kane County, Illinois appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the CyrusOne CHI1-CHI3 (Aurora) data center?
No lawsuit over CyrusOne CHI1-CHI3 (Aurora) appears in the record we track as of August 16, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does CyrusOne CHI1-CHI3 (Aurora) use?
No water withdrawal figure for CyrusOne CHI1-CHI3 (Aurora) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates CyrusOne CHI1-CHI3 (Aurora), and how big is it?
CyrusOne is the operator on record. We hold 24 sites for that company across the registry. Capacity on record is 109 MW.
How to cite this page
SueDataCenters.org Data Center Registry, "CyrusOne CHI1-CHI3 (Aurora)," updated August 16, 2026, https://suedatacenters.org/data-centers/cyrusone-chi1-chi3-aurora-il.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/cyrusone-chi1-chi3-aurora-il, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.CyrusOne facility directory · CyrusOne · retrieved July 22, 2026
- 2.OpenStreetMap way/199252950 · OpenStreetMap · retrieved July 22, 2026
- 3.CyrusOne AI/HPC, Aurora campus AI-optimized via CyrusOne Intelliscale high-density desi · cyrusone.com · retrieved July 23, 2026
- 4.HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · Oak Ridge National Laboratory (ORNL) / HIFLD · retrieved July 23, 2026
- 5.CyrusOne Aurora IL back-up generator schedule (ComEd coordination) · retrieved July 24, 2026
- 6.CyrusOne facility directory · CyrusOne · retrieved August 16, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us