CyrusOne Data Center Disputes: The Chandler Hum That Wrote the Nation's First Noise Ordinance, and the Illinois Fights Since

CyrusOne is a colocation operator, not a hyperscaler, and it has generated more documented noise conflict than most companies its size. Years of complaints about the hum from its Chandler, Arizona campus produced mitigation in 2018 and then the first data center noise ordinance in the country. In Aurora, Illinois, complaints began the month it opened and the city answered with property line decibel limits. In Sangamon County, a 600 megawatt campus cleared the county board 17 to 10. The record, sourced.

CyrusOne on the tracker

Tracker entries
One: the Sangamon County conditional use approval, filed under no-suit. No damages lawsuit against CyrusOne by neighbors of one of its data centers is documented on our tracker as of September 2026
Chandler, Arizona
Complaints about a constant hum from the roughly one million square foot campus began in 2014, produced mitigation under city pressure in 2018, and led Chandler to adopt the first data center noise ordinance in the nation on December 5, 2022, effective January 5, 2023
Aurora, Illinois
Residents complained about constant noise when the facility began operating in April 2025. Aurora responded with property line limits of 56 decibels by day and 46 decibels from 7 p.m., applied to all ten of its data centers, with mitigation work expected to finish by August 2026
Sangamon County, Illinois
The county board granted a conditional permitted use inside an Agricultural zoning district for a roughly $500 million, 280 acre, 600 megawatt campus near Waverly on April 7, 2026 by a vote of 17 to 10 with one abstention, over objections that cited noise at the Aurora site. County staff analogized the use to a large grain elevator. It was not a rezoning and not a variance
What the company says
CyrusOne states that it strives for a lasting positive impact in every community where it operates and that it collaborates with local, state, and national officials to understand each community's needs

Key Takeaways

  • No damages lawsuit against CyrusOne by neighbors of one of its data centers is documented on our tracker as of September 2026, but the company sits at the center of the two most consequential noise ordinances any American city has written about data centers.
  • Chandler, Arizona is the origin story of data center noise regulation. Neighbors of the CyrusOne campus began complaining about a constant hum in 2014, never sued, won mitigation under city pressure in 2018, and then got something more durable: on December 5, 2022 Chandler unanimously adopted the first data center noise ordinance in the country.
  • Aurora, Illinois repeated the pattern a decade later and much faster. Residents complained as soon as the facility began operating in April 2025, and the city adopted enforceable property line decibel limits, 56 by day and 46 from 7 p.m., rather than litigating.
  • The Aurora record then traveled. When the Sangamon County Board voted 17 to 10 on April 7, 2026 to approve a roughly $500 million, 600 megawatt CyrusOne campus on about 280 acres near Waverly, opponents cited the Aurora noise complaints directly when questioning the company's credibility.
  • Aurora's experience shows why decibel limits at the property line, not octave band tables, are what a community should ask for. The city started with Illinois's nine octave band system and switched to plain decibels because the band approach was too complex to enforce.
  • A Bing query pairing CyrusOne with Mesa, Arizona is a near miss. CyrusOne has pursued a Mesa campus, but the documented Arizona dispute involving the company is in Chandler. Mesa's own 2026 data center controversy, reported in August, involved a different developer.

Has CyrusOne been sued over a data center? Not by neighbors, as far as our tracker documents. What CyrusOne has instead is a rarer distinction: its facilities produced the two clearest examples in the country of communities converting noise complaints into binding law without ever filing a claim. In Chandler, Arizona, residents living near a roughly one million square foot campus began complaining about a constant hum in 2014. The complaints ran for years, produced mitigation under city pressure in 2018, and ended with Chandler unanimously passing the first data center noise ordinance in the United States in December 2022. In Aurora, Illinois, the same thing happened on fast forward: the facility opened in April 2025, residents complained immediately, and the city wrote decibel limits at the property line and applied them to every data center in town. Then, in April 2026, Sangamon County approved a 600 megawatt CyrusOne campus over objections that pointed straight back at Aurora. Here is the record, and what neighbors can take from it.

Every case on the tracker

  • Dispute, no suit filedIllinois
    Sangamon County Approved a 600 Megawatt CyrusOne Campus as a Conditional Use in a Farm Zone, on a Grain Elevator Analogy

    No lawsuit confirmed from court records; zoning granted 17 to 10 with one abstention on April 7, 2026

    On April 7, 2026 the Sangamon County Board granted zoning for a roughly $500 million, 280 acre, 600 megawatt CyrusOne campus near Waverly by a vote of 17 to 10 with one abstention. It was not a rezoning and not a variance. County staff analogized a hyperscale data center to a large grain elevator and routed it as a conditional permitted use inside the Agricultural district. What the county record shows, what it does not, and why the mechanism decides what a challenger would be appealing.

Every CyrusOne site in the registry

24 sites on the public record in 11 states: 14 operating, 5 under construction, 2 permitted, 3 proposed. 4 carry documented opposition or litigation. 2.0 GW planned. Most contested first.

9 more in the full registry, or download the data and filter by company.

Free case review

Living near a CyrusOne data center? See if you have a case.

Chandler: the complaints that became the country's first data center noise ordinance

The Chandler story is the reason this site keeps telling people to document before they sue. Neighbors of the CyrusOne campus in Chandler, Arizona started complaining about a constant hum from cooling equipment in 2014. Nobody filed a lawsuit. The complaints accumulated, the city applied pressure, and mitigation followed in 2018.

Then Chandler did the thing that actually changed the industry. On December 5, 2022, the city unanimously passed the first data center noise ordinance in the nation, effective January 5, 2023. It requires pre construction community meetings, a paid noise liaison officer, a baseline acoustic study before operations begin, a standard that operations must not raise neighborhood sound above that baseline, five years of annual noise studies, and generator testing protocols. Chandler went on to reject a subsequent data center proposal in 2025. Our Arizona page covers the full sequence, and our noise limits guide reproduces what the ordinance actually requires.

Note what the Chandler ordinance does not do. It sets no fixed decibel number. It measures the facility against the neighborhood as it sounded before the facility existed, which is a harder standard for an operator to satisfy and a much easier one for a resident to prove. That design choice came out of a decade of complaints from people who could hear the difference and could not point to a number that captured it.

Aurora: complaints in month one, decibel limits by 2026

CyrusOne's Aurora, Illinois facility began operating in April 2025 and, per NPR Illinois reporting, residents complained about constant noise immediately. Aurora's mayor described the city's answer in procedural terms: the approach, both legally and legislatively, was to adopt noise limits at the property line.

The limits Aurora adopted are 56 decibels during the day and 46 decibels in the evening starting at 7 p.m., measured at property lines, and they apply to all ten of the city's data centers rather than to one company. Aurora initially tried to enforce sound using Illinois's nine octave band system and switched to straight decibel measurement after concluding the band approach was too complex to administer. The city's chief development services officer described the problem plainly: each of the nine bands carries its own permitted level, which produces variable decibel levels across all of them. Sound mitigation work at the site was expected to be complete by August 2026, with open questions about rooftop versus ground level chillers and about wind carrying sound to neighborhoods farther away.

Aurora's sequence is worth studying by anyone facing a facility already under construction. The city did not sue and did not need a class. It wrote a number, attached it to the property line, and applied it to every operator equally, which is both harder to challenge and easier to enforce than a facility specific condition. Our noise lawsuit guide covers what happens when a city will not do that and a private nuisance claim becomes the only route.

Free case review

Living near a CyrusOne data center?

Sangamon County: the Aurora record used as evidence 200 miles away

On April 7, 2026, the Sangamon County Board granted zoning for a CyrusOne campus in Talkington Township near Waverly, on roughly 280 acres of farmland in the 13000 block of Thayer Road. The vote was 17 to 10 with one abstention, and the county's adopted minutes record that "the resolution was adopted and the zoning was granted." The mechanism matters: this was a conditional permitted use inside the existing Agricultural district, not a rezoning and not a variance. The county's own staff report says the professional staff's opinion was that the proposed use "can be analogized to the operation of a large grain elevator and granting a conditional permitted use within the Agricultural zoning classification best protects the surrounding area which is agricultural." Our full report on the approval walks through the record. Per NPR Illinois, the project is reported at roughly $500 million, would draw about 600 megawatts at full operation, and would create roughly 500 construction jobs over several years and about 100 permanent positions. Capitol News Illinois separately reported the Sangamon County facility among Illinois data centers on track for state tax credits, and noted that CyrusOne's Aurora data center received state backing in 2024.

CyrusOne committed to funding electrical infrastructure upgrades and to using a closed loop cooling system to reduce water consumption, and said it planned to dredge Waverly Lake to extend its viability as a water source. County estimates put annual property tax revenue at roughly $6.5 million once operational, against $20,000 to $50,000 a year from the land as farmland today, with the county, the North Mac School District, and other local bodies sharing it.

The objections were the ones this site sees everywhere: diesel generator noise and emissions, strain on the electrical grid, and the risk of higher utility costs. One speaker asked the board to listen to the community and take more time for research. And opponents questioned the company's credibility by citing the noise complaints at its Aurora facility, which is the practical reason a company's record in one town is not a local matter. It becomes an exhibit in the next town's hearing.

CyrusOne, for its part, states publicly that it strives for a lasting positive impact in every community where it operates, that its presence brings direct investment, job creation, and infrastructure development, and that it collaborates with local, state, and national government officials to understand each community's unique needs. Nothing on this page is a finding that the company violated any law or ordinance.

If you live near a CyrusOne facility

Two American cities have now regulated data center sound because of complaints about CyrusOne campuses, and neither needed a lawsuit to do it. That is the fastest available path and it is worth trying first. Log the sound with dates, times, weather, and how it affects sleep. Take readings at your own property line. Find out whether your city or county has a numeric limit, an octave band table, or nothing at all, and file every complaint in writing so the record exists. Our guide to documenting data center harm is the checklist, and noise limits by jurisdiction shows what other places require, including Chandler's baseline standard.

If a CyrusOne project is proposed rather than built, the Sangamon County hearing is the model for what works: show up, put the company's record in other towns into the record in yours, and ask for conditions in writing before the vote rather than mitigation promises after it. Our guide to fighting a proposed data center covers the approval sequence, and zoning appeal deadlines by state covers the clocks that start the moment a decision is made. Illinois's data center litigation is on the tracker in Grayslake and Joliet.

If a facility is already operating and the noise has not stopped, a claim may exist. Our free case review connects you with an independent attorney in our network who handles data center cases in your state, at no cost and with no obligation.

Frequently asked questions

Has CyrusOne been sued over a data center?

No damages lawsuit by neighbors against CyrusOne over one of its data centers is documented on our tracker as of September 2026. The company's documented disputes are regulatory and land use fights: years of noise complaints in Chandler, Arizona that produced the nation's first data center noise ordinance, noise complaints in Aurora, Illinois that produced citywide property line decibel limits, and a contested county board approval in Sangamon County, Illinois.

What is the CyrusOne noise ordinance in Chandler, Arizona?

Chandler unanimously adopted the first data center noise ordinance in the nation on December 5, 2022, effective January 5, 2023, after years of resident complaints about a constant hum from the CyrusOne campus that began in 2014. It requires pre construction community meetings, a paid noise liaison officer, a baseline acoustic study, a rule that operations must not raise neighborhood sound above that baseline, five years of annual noise studies, and generator testing protocols.

How loud can the CyrusOne data center in Aurora, Illinois be?

Aurora adopted property line limits of 56 decibels during the day and 46 decibels in the evening beginning at 7 p.m., and applied them to all ten data centers in the city. The city switched from Illinois's nine octave band system to plain decibel measurement because the band approach proved too complex to enforce. Sound mitigation work at the CyrusOne site was expected to be finished by August 2026.

Did Sangamon County approve the CyrusOne data center?

Yes. On April 7, 2026 the Sangamon County Board granted zoning by a vote of 17 to 10 with one abstention for a roughly $500 million CyrusOne campus on about 280 acres near Waverly, projected to draw about 600 megawatts at full operation. The approval was a conditional permitted use inside the existing Agricultural district, not a rezoning and not a variance, on county staff's analogy to a large grain elevator. Opponents raised diesel generator noise and emissions, grid strain, and utility costs, and cited noise complaints at the company's Aurora facility.

Is there a CyrusOne data center dispute in Mesa, Arizona?

Not one that our research documents. We found no lawsuit, moratorium, referendum, or regulatory action involving CyrusOne in Mesa as of September 2026. The documented Arizona dispute involving the company is in neighboring Chandler, where a decade of noise complaints produced the nation's first data center noise ordinance, unanimously adopted December 5, 2022 and effective January 5, 2023.

Article sources

Our editorial standards require primary sources: government publications, regulator data, company filings, and established industry research.

  1. 1.NPR Illinois: How Aurora and DeKalb residents are dealing with data centers (August 3, 2026)
  2. 2.NPR Illinois: Sangamon County Board approves a controversial data center project (April 7, 2026)
  3. 3.Sangamon County Board minutes, April 7, 2026, recording the 17 to 10 vote with one abstention and that the zoning was granted
  4. 4.Sangamon County: Proposed CyrusOne Data Center, Merged Staff Report, on the conditional permitted use and the grain elevator analogy
  5. 5.Sangamon County: Proposed CyrusOne Data Center informational page and county question and answer record
  6. 6.Illinois Times: The first data center in Sangamon County, describing the approval as a conditional permitted use rather than a rezoning or variance
  7. 7.NPR Illinois: Plans for Sangamon County data center raise hopes, concerns (November 4, 2025)
  8. 8.Capitol News Illinois: Here are the Illinois data centers on track for more than $650M in tax credits (July 1, 2026)
  9. 9.Capitol News Illinois: Pritzker touts Illinois' economic development at data center groundbreaking, Aurora (October 2, 2024)
  10. 10.City of Chandler: Chandler's data center ordinance now in effect, unanimously approved December 5, 2022 and effective January 5, 2023
  11. 11.Chandler City Code Sec. 35-2214, data center regulations
  12. 12.CyrusOne: Communities, the company's statement on local impact and engagement
  13. 13.CyrusOne: Sustainability commitments, including water conservation

Is a CyrusOne data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.