CyrusOne DFW3-DFW5 (Allen)

Allen, Collin County, Texas · All 35 CyrusOne sites · Every CyrusOne case on our tracker

OperatingNo reception on recordAI likelyRecord updated September 21, 2026

CyrusOne DFW3-DFW5 (Allen) is an operating data center in Allen, Texas (Collin County), operated by CyrusOne. The public record puts it at 50 MW planned, 90 acres.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Operating

Operator
CyrusOne
Facility type
Data center, AI use likely
Location
Allen, Collin County, TX
Coordinates
33.1385, -96.6600
Power capacity
77 MW operating; 50 MW planned
Land
90 acres
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Oncor
Power source
Mixed
Cooling
Closed loop
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Reported by at least one credible outlet or filing

Opposition and litigation at this site

Nothing on record as of September 21, 2026. No lawsuit, organized opposition, or contested hearing over CyrusOne DFW3-DFW5 (Allen) in Allen, Collin County, Texas appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

Power and water

CyrusOne signed a 40MW wind+solar PPA with Gexa Energy (announced April 2022) explicitly covering its North Texas data centers, naming Allen, Carrollton, and Lewisville as the sites the purchase powers.

Notes on the record

Confirmed 90-acre, 3-building, 50MW campus at Allen, TX (largest DC development in the state per operator page). AI/HPC (likely): Allen campus marketed for AI training, HPC, multi-cloud.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • How the community has received it
Which document closes each gap
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Our reporting on this site

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Tell us about your situation

Living near CyrusOne DFW3-DFW5 (Allen)?

Tell us the basics. Where a participating attorney in your state is available, we may share your information with them with your consent. Free, no obligation, and no guarantee anyone will contact you.

Questions people ask about this site

Is there opposition to the CyrusOne DFW3-DFW5 (Allen) data center in Allen?

Nothing on record as of September 21, 2026. No lawsuit, organized opposition, or contested hearing over CyrusOne DFW3-DFW5 (Allen) in Allen, Collin County, Texas appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the CyrusOne DFW3-DFW5 (Allen) data center?

No lawsuit over CyrusOne DFW3-DFW5 (Allen) appears in the record we track as of September 21, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does CyrusOne DFW3-DFW5 (Allen) use?

No water withdrawal figure for CyrusOne DFW3-DFW5 (Allen) is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates CyrusOne DFW3-DFW5 (Allen), and how big is it?

CyrusOne is the operator on record. We hold 35 sites for that company across the registry. Capacity on record is 50 MW. The site is recorded at 90 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "CyrusOne DFW3-DFW5 (Allen)," updated September 21, 2026, https://suedatacenters.org/data-centers/cyrusone-dfw3-dfw5-allen-tx.

Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/cyrusone-dfw3-dfw5-allen-tx, retrieved October 29, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.CyrusOne facility directory · CyrusOne · retrieved September 21, 2026
  2. 2.OpenStreetMap way/590213771 · OpenStreetMap · retrieved July 22, 2026
  3. 3.CyrusOne AI/HPC, Allen campus marketed for AI training, HPC, multi-cloud · datacenterknowledge.com · retrieved July 23, 2026
  4. 4.Business Wire: CyrusOne Purchases Solar and Wind Energy in North Texas from Gexa Energy (Apr 2022), names Allen, Carrollton, Lewisville · retrieved July 24, 2026
  5. 5.DataCenterDynamics: CyrusOne signs 40MW wind and solar PPA with Gexa Energy in Texas · retrieved July 24, 2026

Is a data center disrupting your home?

Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.

  • Tell us about your situation
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us