CyrusOne AI Data Center at NAS Lemoore is a proposed data center in California (Kings County), operated by CyrusOne. The public record puts it at announced September 2025, 100 MW planned. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- CyrusOne
- Facility type
- Data center, AI use confirmed
- Location
- Kings County, CA
- Coordinates
- 36.3030, -119.9530
- Power capacity
- 100 MW planned
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- September 2025
- Utility
- Pacific Gas & Electric (PG&E)
- Power source
- On site gas
- Cooling
- Not established
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- Contested
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- September 2025ProposedAmeresco, U.S. Navy, and CyrusOne announced public-private partnership to build 100MW AI-optimized data center at NAS Lemoore; first phase expected online 2027; land leased from DOD Source: Ameresco, Inc.
Opposition and litigation at this site
Yes. CyrusOne AI Data Center at NAS Lemoore in Kings County, California is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Kings County Supervisor Garrett Gilcrease (also Farm Bureau president) opposed the project on water grounds during his 2024 campaign; the project advanced with little public input; no formal legal challenge as of mid-2026.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.
Kings County Supervisor Garrett Gilcrease (also Farm Bureau president) opposed the project on water grounds during his 2024 campaign; the project advanced with little public input; no formal legal challenge as of mid-2026. A 2023 EIR projects ~400 construction workers and ~20 permanent employees for the proposed facility (projections, not confirmed headcount). The ~$1B figure reported by the Hanford Sentinel covers the integrated project (data center + ~425 MW solar + battery storage), not the data center alone, so no data-center-only investmentUsd.
Power and water
Fully off-grid microgrid system including engine generators and control systems built by Ameresco. Aligned with Trump Administration AI Action Plan. Separate discussions ongoing for 425MW solar farm on 920 acres of surrounding DOD land.
Developer has not disclosed cooling method or water source (arid Central Valley; NAS Lemoore draws from the Kings River). Kings County Supervisor Gilcrease flagged water as a key opposition concern.
Notes on the record
Located at Naval Air Station Lemoore on the Kings/Fresno county border. Ameresco leads energy infrastructure via its Intelliscale platform; CyrusOne operates the data center for federal and defense AI workloads (FedRAMP, FISMA High, DoD IL5/IL6). Land leased from DOD. Announced September 9, 2025; first phase expected online 2027.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
Which document closes each gap
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Questions people ask about this site
Is there opposition to the CyrusOne AI Data Center at NAS Lemoore in Kings County, California?
Yes. CyrusOne AI Data Center at NAS Lemoore in Kings County, California is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Kings County Supervisor Garrett Gilcrease (also Farm Bureau president) opposed the project on water grounds during his 2024 campaign; the project advanced with little public input; no formal legal challenge as of mid-2026.
Has anyone filed a lawsuit over the CyrusOne AI Data Center at NAS Lemoore?
No lawsuit over CyrusOne AI Data Center at NAS Lemoore appears in the record we track as of July 23, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does CyrusOne AI Data Center at NAS Lemoore use?
No water withdrawal figure for CyrusOne AI Data Center at NAS Lemoore is on record here. Cooling is recorded as unknown, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.
Who operates CyrusOne AI Data Center at NAS Lemoore, and how big is it?
CyrusOne is the operator on record. We hold 24 sites for that company across the registry. Capacity on record is 100 MW.
How to cite this page
SueDataCenters.org Data Center Registry, "CyrusOne AI Data Center at NAS Lemoore," updated July 23, 2026, https://suedatacenters.org/data-centers/cyrusone-nas-lemoore-ca.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/cyrusone-nas-lemoore-ca, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Ameresco and U.S. Navy Partner to Build AI-Optimized Data Center and Energy Infrastructure at NAS Lemoore · Ameresco, Inc. · retrieved July 6, 2026
- 2.Ameresco Partners with CyrusOne to Develop Offgrid AI Data Center at Naval Air Station Lemoore in California · Data Center Dynamics · retrieved July 6, 2026
- 3.Groundbreaking for NAS Lemoore data center & energy project · Hanford Sentinel · retrieved July 6, 2026
- 4.Gilcrease calls for dialogue over data center · Hanford Sentinel · retrieved July 6, 2026
- 5.HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · Oak Ridge National Laboratory (ORNL) / HIFLD · retrieved July 23, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us