OperatingNo reception on recordRecord updated September 30, 2026

T5@Colorado Data Center Campus is an operating data center in Colorado Springs, Colorado (El Paso County), operated by T5 Data Centers. The public record puts it at 64 acres.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Operating

Operator
T5 Data Centers
Facility type
Data center
Location
3323 Janitell Road, Colorado Springs, El Paso County, CO, 80906
Coordinates
38.7960, -104.7945 (approximate)
Power capacity
Not established from a public source
Land
64 acres
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Colorado Springs Utilities
Power source
Grid
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Reported by at least one credible outlet or filing

Opposition and litigation at this site

Nothing on record as of September 30, 2026. No lawsuit, organized opposition, or contested hearing over T5@Colorado Data Center Campus in Colorado Springs, El Paso County, Colorado appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

Notes on the record

T5 announced this 64-acre campus in 2013: 100 MW of expandable power and an $800M plan. That is a campus-wide plan, not built investment, so investmentUsd is left unset. In June 2016 an unnamed top-10 technology company bought 8.5 acres and broke ground on the first data center. Baxtel lists the campus at 3323 Janitell Rd as operational since 2017, with up to 82 MW of on-site expansion and Colorado Springs Utilities service. The campus is separate from Novva (650 Sybilla Ln) and QTS (311 S. Rockrimmon Blvd). T5's current ownership was not independently verified, and the end tenant is undisclosed.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • How the community has received it
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Free case review

Living near T5@Colorado Data Center Campus?

Tell us the basics and an independent attorney handling data center cases in your state will follow up. Free, and you are never obligated to hire anyone.

Questions people ask about this site

Is there opposition to the T5@Colorado Data Center Campus in Colorado Springs?

Nothing on record as of September 30, 2026. No lawsuit, organized opposition, or contested hearing over T5@Colorado Data Center Campus in Colorado Springs, El Paso County, Colorado appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the T5@Colorado Data Center Campus?

No lawsuit over T5@Colorado Data Center Campus appears in the record we track as of September 30, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does T5@Colorado Data Center Campus use?

No water withdrawal figure for T5@Colorado Data Center Campus is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates T5@Colorado Data Center Campus, and how big is it?

T5 Data Centers is the operator on record. We hold 11 sites for that company across the registry. No capacity figure is on record for this site. The site is recorded at 64 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "T5@Colorado Data Center Campus," updated September 30, 2026, https://suedatacenters.org/data-centers/t5-colorado-springs-co.

Facility data from Compute Atlas (E. Kubiak), version 1.34.0 (September 21, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/t5-colorado-springs-co, retrieved October 1, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.T5 Colorado Data Center · Baxtel · retrieved September 30, 2026
  2. 2.Global Software Company First Tenant to Break Ground at T5 Data Centers' T5@Colorado Campus · T5 Data Centers · retrieved September 30, 2026
  3. 3.T5 Plans $800 Million Campus in Colorado Springs · Data Center Knowledge · retrieved September 30, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us