Project Primestone (Vineyards Research Park) GPU Test Facility
Colorado Springs, El Paso County, Colorado
Project Primestone (Vineyards Research Park) GPU Test Facility is a proposed data center in Colorado Springs, Colorado (El Paso County), operated by Broadstone Net Lease (developer/owner); operations partner Emergent Data Centers; tenant undisclosed. The public record puts it at 33.8 acres, a reported $303 million investment.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- Broadstone Net Lease (developer/owner); operations partner Emergent Data Centers; tenant undisclosed
- Facility type
- Data center
- Location
- 3819 Janitell Rd, Colorado Springs, El Paso County, CO, 80906
- Coordinates
- 38.7898, -104.7932 (approximate)
- Power capacity
- Not established from a public source
- Land
- 33.8 acres
- Investment
- $303 million
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Closed loop
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- May 2026ProposedCity issued a Rapid Response Certificate (expedited review) in May 2026. Broadstone targets substantial completion and rent commencement in 2027. Source: The Gazette (Colorado Springs)
Opposition and litigation at this site
Nothing on record as of October 19, 2026. No lawsuit, organized opposition, or contested hearing over Project Primestone (Vineyards Research Park) GPU Test Facility in Colorado Springs, El Paso County, Colorado appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Power and water
Project statement describes a closed-loop cooling system. Cooling loops are re-piped between test campaigns.
Notes on the record
Two 110,000 sq ft buildings for GPU burn-in, benchmarking and reliability testing for an unnamed 'Fortune 20' technology tenant. The developer's project statement says it is 'not a data center' because it does not sell compute. It is tracked here as a GPU compute facility. The Pikes Peak Bulletin reports a 100 MW initial building with an option to reach 200 MW, but The Gazette attributes the 100 MW figure to T5's 2013 plans, so no capacity is recorded.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Tax abatements or other public subsidy
- Permanent jobs promised
- How the community has received it
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- T5@Colorado Data Center Campus · Colorado Springs · T5 Data Centersunder 1 mile · Operating
- Raeden Project Taurus · Colorado Springs · Raeden3 mi · Permitted · 50 MW · Contested
- Walmart Colorado Springs Data Center · Colorado Springs · Walmart14 mi · Operating
- Novva Colorado Springs Data Center · Colorado Springs · Novva Data Centers15 mi · Operating · 40 MW
Questions people ask about this site
Is there opposition to the Project Primestone (Vineyards Research Park) GPU Test Facility in Colorado Springs?
Nothing on record as of October 19, 2026. No lawsuit, organized opposition, or contested hearing over Project Primestone (Vineyards Research Park) GPU Test Facility in Colorado Springs, El Paso County, Colorado appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Project Primestone (Vineyards Research Park) GPU Test Facility?
No lawsuit over Project Primestone (Vineyards Research Park) GPU Test Facility appears in the record we track as of October 19, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Project Primestone (Vineyards Research Park) GPU Test Facility use?
No water withdrawal figure for Project Primestone (Vineyards Research Park) GPU Test Facility is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.
Who operates Project Primestone (Vineyards Research Park) GPU Test Facility, and how big is it?
Broadstone Net Lease (developer/owner); operations partner Emergent Data Centers; tenant undisclosed is the operator on record. No capacity figure is on record for this site. The site is recorded at 33.8 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Project Primestone (Vineyards Research Park) GPU Test Facility," updated October 19, 2026, https://suedatacenters.org/data-centers/broadstone-project-primestone-colorado-springs-co.
Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/broadstone-project-primestone-colorado-springs-co, retrieved October 29, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.High-tech graphics card testing facility eyeing former golf course, vineyard for $303M development · The Gazette (Colorado Springs) · retrieved October 19, 2026
- 2.Project Primestone isn't a data center, it will just look and feel like one · Pikes Peak Bulletin · retrieved October 19, 2026
- 3.OSM Nominatim geocode: 3819 Janitell Road · OpenStreetMap · retrieved October 19, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us