Granite Renewables Logan County Data Center Campus

Sterling, Logan County, Colorado

ProposedContestedRecord updated August 26, 2026

Granite Renewables Logan County Data Center Campus is a proposed data center in Sterling, Colorado (Logan County), operated by Granite Renewables. The public record puts it at 2 GW planned, 4,000 acres. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
Granite Renewables
Facility type
Data center
Location
Sterling, Logan County, CO
Coordinates
40.6255, -103.2077 (approximate)
Power capacity
2 GW planned
Land
4,000 acres
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Not established from a public source
Power source
Mixed
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Contested
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. December 17, 2025
    Proposed
    Developer began meeting Logan County officials in late summer/early fall 2025; no formal application had been submitted at the time of reporting. Source: Pagosa Daily Post (Big Pivots)

Opposition and litigation at this site

Yes. Granite Renewables Logan County Data Center Campus in Sterling, Logan County, Colorado is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Logan County declared a moratorium on data centers, battery storage, solar and wind development in October 2025 while it wrote regulations; planning-commission recommendations went to the county commissioners on 2026-01-06.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.

Logan County declared a moratorium on data centers, battery storage, solar and wind development in October 2025 while it wrote regulations; planning-commission recommendations went to the county commissioners on 2026-01-06. Existing wind farms add roughly $2.5 million a year to the county tax base.

Source: Pagosa Daily Post (Big Pivots)

Power and water

Developer describes combining solar farms, battery storage and modular gas units with cooperative grid power; the serving cooperative is a member of Tri-State Generation and Transmission. Major natural gas lines run parallel to Interstate 80 within about 30 miles, in nearby Nebraska.

Notes on the record

Proposed hyperscale campus roughly 21 miles northwest of Sterling, 8-10 miles from the Nebraska border, discussed as up to 2 GW on about 4,000 acres. A $15 billion figure was attributed to a speaker describing investment across the corridor between Sterling and the Nebraska border, so it is deliberately NOT recorded as this site's investment. Coordinates are the Sterling town centroid (approximate); the site itself is northwest of town and has no confirmed parcel.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Which utility serves it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Questions people ask about this site

Is there opposition to the Granite Renewables Logan County Data Center Campus in Sterling?

Yes. Granite Renewables Logan County Data Center Campus in Sterling, Logan County, Colorado is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Logan County declared a moratorium on data centers, battery storage, solar and wind development in October 2025 while it wrote regulations; planning-commission recommendations went to the county commissioners on 2026-01-06.

Has anyone filed a lawsuit over the Granite Renewables Logan County Data Center Campus?

No lawsuit over Granite Renewables Logan County Data Center Campus appears in the record we track as of August 26, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Granite Renewables Logan County Data Center Campus use?

No water withdrawal figure for Granite Renewables Logan County Data Center Campus is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Granite Renewables Logan County Data Center Campus, and how big is it?

Granite Renewables is the operator on record. Capacity on record is 2 GW. The site is recorded at 4000 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Granite Renewables Logan County Data Center Campus," updated August 26, 2026, https://suedatacenters.org/data-centers/granite-renewables-logan-county-co.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/granite-renewables-logan-county-co, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.BIG PIVOTS: Massive Data Center Slated for Northeastern Colorado? Part One · Pagosa Daily Post (Big Pivots) · retrieved August 26, 2026
  2. 2.Gearing up for data centers · Big Pivots · retrieved August 26, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us