Union City Data Center Campus (EdgeConneX / TA Realty) is a data center under construction in Union City, Georgia (Fulton County), operated by EdgeConneX (campus investment and operations with TA Realty; land owned by Microsoft, site development by Burr Computer Environments). The public record puts it at 324 MW planned, 136 acres, a reported $1.8 billion investment.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Under construction
- Operator
- EdgeConneX (campus investment and operations with TA Realty; land owned by Microsoft, site development by Burr Computer Environments)
- Facility type
- Data center
- Location
- Union City, Fulton County, GA
- Coordinates
- 33.5871, -84.5424 (approximate)
- Power capacity
- 324 MW planned
- Land
- 136 acres
- Investment
- $1.8 billion
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- 50 permanent
- Public subsidy
- Development Authority of Fulton County tax abatement (10 years), $75 million, Fulton County, Georgia
- Community reception
- No reception on record
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- 2024Under constructionPhase 1 construction began late 2024; all three phases required to be complete no later than 2032 under the development authority's motion. Source: Baxtel
Opposition and litigation at this site
Nothing on record as of September 23, 2026. No lawsuit, organized opposition, or contested hearing over Union City Data Center Campus (EdgeConneX / TA Realty) in Union City, Fulton County, Georgia appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Public money on the record
| Program | Amount | Granted by | Year |
|---|---|---|---|
| Development Authority of Fulton County tax abatement (10 years) | $75 million | Fulton County, Georgia |
Notes on the record
Three buildings of roughly 612,000 sq ft each (campus over 2 million sq ft) on 136 acres Microsoft bought in April 2024 for $53.5m. Operator is recorded as EdgeConneX rather than Microsoft because the fetched sources describe Microsoft as the landowner while EdgeConneX and TA Realty lead investment and operations, ownership and operation diverge here. Construction employment is reported as a 400 to 600 range, so only the permanent figure is recorded. Building 1 is designated AT11 by EdgeConneX; this is NOT Digital Realty's separately tracked ATL11. Coordinates are the Union City centroid (OSM Nominatim); one source lists the mailing address as College Park 30349.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- How the community has received it
- Which utility serves it
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Vantage Data Centers Westlake · South Fulton · Vantage Data Centers3 mi · Proposed
- Microsoft East Point Data Center (Ben Hill Road) · East Point · Microsoft4 mi · Operating
- Microsoft Tyrone Campus (Project Rita) · Tyrone · Microsoft7 mi · Permitted · 96 MW · Contested
- CleanSpark College Park Bitcoin Mining Facility · College Park · CleanSpark, Inc.8 mi · Operating · 50 MW
- Project Peach (CyrusOne Palmetto Data Center Campus) · Palmetto · CyrusOne (joint venture with North Coweta Investors)9 mi · Permitted · Opposed
- Microsoft Palmetto Data Center · Palmetto · Microsoft9 mi · Under construction
- Flexential Atlanta - Douglasville 2 · Douglasville · Flexential11 mi · Operating
- T5 @ Atlanta IV · Palmetto · T5 Data Centers11 mi · Proposed · 300 MW
Questions people ask about this site
Is there opposition to the Union City Data Center Campus (EdgeConneX / TA Realty) in Union City?
Nothing on record as of September 23, 2026. No lawsuit, organized opposition, or contested hearing over Union City Data Center Campus (EdgeConneX / TA Realty) in Union City, Fulton County, Georgia appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Union City Data Center Campus (EdgeConneX / TA Realty)?
No lawsuit over Union City Data Center Campus (EdgeConneX / TA Realty) appears in the record we track as of September 23, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Union City Data Center Campus (EdgeConneX / TA Realty) use?
No water withdrawal figure for Union City Data Center Campus (EdgeConneX / TA Realty) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Union City Data Center Campus (EdgeConneX / TA Realty), and how big is it?
EdgeConneX (campus investment and operations with TA Realty; land owned by Microsoft, site development by Burr Computer Environments) is the operator on record. We hold 21 sites for that company across the registry. Capacity on record is 324 MW. The site is recorded at 136 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Union City Data Center Campus (EdgeConneX / TA Realty)," updated September 23, 2026, https://suedatacenters.org/data-centers/edgeconnex-union-city-campus-fulton-ga.
Facility data from Compute Atlas (E. Kubiak), version 1.34.0 (September 21, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/edgeconnex-union-city-campus-fulton-ga, retrieved October 1, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Microsoft: Union City Campus Data Center · Baxtel · retrieved September 23, 2026
- 2.Details Emerge On Microsoft's $1.8 Billion Investment In Atlanta Data Centers Amid Tax, Development Wrangles · Data Center Frontier · retrieved September 23, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us