Digital Realty Fort Gillem Data Center Campus
Forest Park, Clayton County, Georgia · All 70 Digital Realty sites
Digital Realty Fort Gillem Data Center Campus is a proposed data center in Forest Park, Georgia (Clayton County), operated by Digital Realty. The public record puts it at 212 MW planned, 97 acres, a reported $3 billion investment.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- Digital Realty
- Facility type
- Data center
- Location
- Forest Park, Clayton County, GA
- Coordinates
- 33.6220, -84.3691 (approximate)
- Power capacity
- 212 MW planned
- Land
- 97 acres
- Investment
- $3 billion
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- June 2025ProposedDigital Realty project page describes a two-facility campus at former Fort Gillem; first phase expected early 2028 Source: Digital Realty
Opposition and litigation at this site
Nothing on record as of October 14, 2026. No lawsuit, organized opposition, or contested hearing over Digital Realty Fort Gillem Data Center Campus in Forest Park, Clayton County, Georgia appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
Two mission-critical facilities on ~97 acres at the former Fort Gillem Army base in Forest Park: ~1.9M sq ft and ~212 MW initial IT load. About $3B total proposed, including >$100M for remediation. First phase expected early 2028. Digital Realty projects 60 to 75 permanent jobs after phase 1. All figures are subject to change, per Digital Realty. Coordinates are the Forest Park city centroid.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- How the community has received it
- Which utility serves it
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- CleanSpark College Park Bitcoin Mining Facility · College Park · CleanSpark, Inc.4 mi · Operating
- TA Realty East Tanners Church Road Data Center · Ellenwood · TA Realty5 mi · Permitted · 180 MW
- Project Preserve (Ellenwood Data Center) · Ellenwood · PCC-DeKalb LLC5 mi · Cancelled
- Microsoft East Point Data Center (Ben Hill Road) · East Point · Microsoft9 mi · Operating
- Digital Realty Atlanta ATL13 · Atlanta · Digital Realty9 mi · Operating
- CoreSite AT1 - Atlanta, GA · Atlanta · CoreSite9 mi · Operating
- Union City Data Center Campus (EdgeConneX / TA Realty) · Union City · EdgeConneX (campus investment and operations with TA Realty; land owned by Microsoft, site development by Burr Computer Environments)10 mi · Under construction · 324 MW
- QTS Atlanta 1 (Atlanta-Metro DC1) · Atlanta · QTS Data Centers11 mi · Operating · 278 MW
Questions people ask about this site
Is there opposition to the Digital Realty Fort Gillem Data Center Campus in Forest Park?
Nothing on record as of October 14, 2026. No lawsuit, organized opposition, or contested hearing over Digital Realty Fort Gillem Data Center Campus in Forest Park, Clayton County, Georgia appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Digital Realty Fort Gillem Data Center Campus?
No lawsuit over Digital Realty Fort Gillem Data Center Campus appears in the record we track as of October 14, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Digital Realty Fort Gillem Data Center Campus use?
No water withdrawal figure for Digital Realty Fort Gillem Data Center Campus is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Digital Realty Fort Gillem Data Center Campus, and how big is it?
Digital Realty is the operator on record. We hold 70 sites for that company across the registry. Capacity on record is 212 MW. The site is recorded at 97 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Digital Realty Fort Gillem Data Center Campus," updated October 14, 2026, https://suedatacenters.org/data-centers/digital-realty-fort-gillem-forest-park-ga.
Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/digital-realty-fort-gillem-forest-park-ga, retrieved October 29, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Fort Gillem data center project · Digital Realty · retrieved October 14, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us