Data Center Registry
Wallace Jackson Data Center Campus
Griffin, Spalding County, Georgia
Wallace Jackson Data Center Campus is a permitted data center in Griffin, Georgia (Spalding County), operated by Wallace Jackson, LLC (developer; end user undisclosed). The public record puts it at a reported $3.7 billion investment. It is or has been the subject of litigation over its siting, permitting, or operation.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Permitted
- Operator
- Wallace Jackson, LLC (developer; end user undisclosed)
- Facility type
- Data center
- Location
- Jackson Road at Wallace Road, Griffin, Spalding County, GA
- Coordinates
- 33.2468, -84.2641 (approximate)
- Power capacity
- Not established from a public source
- Land
- Not established from a public source
- Investment
- $3.7 billion
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- In litigation
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- January 22, 2026PermittedSpalding County Board of Commissioners approved the campus. Source: Griffin Daily News
Opposition and litigation at this site
Yes. Wallace Jackson Data Center Campus in Griffin, Spalding County, Georgia is or has been the subject of litigation over its siting, permitting, or operation. Two lawsuits were filed in Spalding County Superior Court against the Board of Commissioners' Jan.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: in litigation means the facility is or has been the subject of a lawsuit related to its siting, permitting, or operation.
Two lawsuits were filed in Spalding County Superior Court against the Board of Commissioners' Jan. 22, 2026 approval, alleging the county ignored its own procedural requirements and data center rules and seeking to have the zoning decision vacated.
Notes on the record
Ten two-story buildings ranging from 297,000 to 780,000 sq ft, 4.986 million sq ft total, on roughly 190 acres along the I-75 corridor. The DRI puts value at build-out in 2035 at $3.65B with $51.656M in estimated annual local tax revenue. Acreage omitted as a precise figure, the source says "nearly 190 acres."
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- High Falls Road Data Center Campus (Montana Property Group) · Griffin · Montana Property Group LLC (developer; end user undisclosed)under 1 mile · Permitted
- Spalding Investments Data Center Campus (High Falls Road) · Griffin · Spalding Investments, LLC (developer; end user undisclosed)under 1 mile · Permitted
- Lovejoy Data Center Campus (Stillwater Development) · Lovejoy · Stillwater Development15 mi · Cancelled · 1.3 GW · Opposed
- AWS Butts County Data Center Campus · Jackson · Amazon Web Services18 mi · Proposed
- Microsoft Fairwater Atlanta (Azure AI Superfactory) · Fayetteville · Microsoft18 mi · Operating · 1.5 GW · Contested
- TA Realty East Tanners Church Road Data Center · Ellenwood · TA Realty25 mi · Permitted · 180 MW
- Microsoft Tyrone Campus (Project Rita) · Tyrone · Microsoft25 mi · Permitted · 96 MW · Contested
- CleanSpark College Park Bitcoin Mining Facility · College Park · CleanSpark, Inc.29 mi · Operating · 50 MW
Questions people ask about this site
Is there opposition to the Wallace Jackson Data Center Campus in Griffin?
Yes. Wallace Jackson Data Center Campus in Griffin, Spalding County, Georgia is or has been the subject of litigation over its siting, permitting, or operation. Two lawsuits were filed in Spalding County Superior Court against the Board of Commissioners' Jan.
Has anyone filed a lawsuit over the Wallace Jackson Data Center Campus?
Yes. This site is recorded as being in litigation. The case, the court, and the filings we hold are listed on this page under the timeline and the sources.
How much water does Wallace Jackson Data Center Campus use?
No water withdrawal figure for Wallace Jackson Data Center Campus is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Wallace Jackson Data Center Campus, and how big is it?
Wallace Jackson, LLC (developer; end user undisclosed) is the operator on record. No capacity figure is on record for this site.
How to cite this page
SueDataCenters.org Data Center Registry, "Wallace Jackson Data Center Campus," updated August 28, 2026, https://suedatacenters.org/data-centers/wallace-jackson-data-center-campus-spalding-ga.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/wallace-jackson-data-center-campus-spalding-ga, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.What's $3.7B and larger than 3 malls? Georgia's next potential data center. · The Atlanta Journal-Constitution · retrieved August 28, 2026
- 2.Data centers could bring high tax revenue to Spalding County · Griffin Daily News · retrieved August 28, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us