Data Center Registry
High Falls Road Data Center Campus (Montana Property Group)
Griffin, Spalding County, Georgia
High Falls Road Data Center Campus (Montana Property Group) is a permitted data center in Griffin, Georgia (Spalding County), operated by Montana Property Group LLC (developer; end user undisclosed). The public record puts it at 132.9 acres.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Permitted
- Operator
- Montana Property Group LLC (developer; end user undisclosed)
- Facility type
- Data center
- Location
- High Falls Road at Alicia Drive (north side), Griffin, Spalding County, GA
- Coordinates
- 33.2468, -84.2641 (approximate)
- Power capacity
- Not established from a public source
- Land
- 132.9 acres
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- July 2025PermittedSpalding County Board of Commissioners approved rezonings and special exceptions with conditions on two adjoining parcels totalling 132.9 acres. Source: Griffin Daily News
Opposition and litigation at this site
Nothing on record as of August 28, 2026. No lawsuit, organized opposition, or contested hearing over High Falls Road Data Center Campus (Montana Property Group) in Griffin, Spalding County, Georgia appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Power and water
Approved site plan includes a power substation and a proposed on-site solar farm.
Notes on the record
Spalding County's first approved data center campus: three two-story buildings (two at 936,460 sq ft, one at 686,737 sq ft) totalling 2,559,500 sq ft, plus two detached administrative buildings. Property owner listed as Alan R. Mobley. Build-out scheduled for 2030; estimated local tax revenue at build-out $26.859M. As of April 2026 none of Spalding's approved campuses had requested a land disturbance permit.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- How the community has received it
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Spalding Investments Data Center Campus (High Falls Road) · Griffin · Spalding Investments, LLC (developer; end user undisclosed)under 1 mile · Permitted
- Wallace Jackson Data Center Campus · Griffin · Wallace Jackson, LLC (developer; end user undisclosed)under 1 mile · Permitted · In litigation
- Lovejoy Data Center Campus (Stillwater Development) · Lovejoy · Stillwater Development15 mi · Cancelled · 1.3 GW · Opposed
- AWS Butts County Data Center Campus · Jackson · Amazon Web Services18 mi · Proposed
- Microsoft Fairwater Atlanta (Azure AI Superfactory) · Fayetteville · Microsoft18 mi · Operating · 1.5 GW · Contested
- TA Realty East Tanners Church Road Data Center · Ellenwood · TA Realty25 mi · Permitted · 180 MW
- Microsoft Tyrone Campus (Project Rita) · Tyrone · Microsoft25 mi · Permitted · 96 MW · Contested
- CleanSpark College Park Bitcoin Mining Facility · College Park · CleanSpark, Inc.29 mi · Operating · 50 MW
Questions people ask about this site
Is there opposition to the High Falls Road Data Center Campus (Montana Property Group) in Griffin?
Nothing on record as of August 28, 2026. No lawsuit, organized opposition, or contested hearing over High Falls Road Data Center Campus (Montana Property Group) in Griffin, Spalding County, Georgia appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the High Falls Road Data Center Campus (Montana Property Group)?
No lawsuit over High Falls Road Data Center Campus (Montana Property Group) appears in the record we track as of August 28, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does High Falls Road Data Center Campus (Montana Property Group) use?
No water withdrawal figure for High Falls Road Data Center Campus (Montana Property Group) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates High Falls Road Data Center Campus (Montana Property Group), and how big is it?
Montana Property Group LLC (developer; end user undisclosed) is the operator on record. No capacity figure is on record for this site. The site is recorded at 132.9 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "High Falls Road Data Center Campus (Montana Property Group)," updated August 28, 2026, https://suedatacenters.org/data-centers/montana-property-group-high-falls-road-spalding-ga.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/montana-property-group-high-falls-road-spalding-ga, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Data centers could bring high tax revenue to Spalding County · Griffin Daily News · retrieved August 28, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us