AWS Butts County Data Center Campus is a proposed data center in Jackson, Georgia (Butts County), operated by Amazon Web Services. The public record puts it at announced January 7, 2025.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- Amazon Web Services
- Facility type
- Data center, AI use likely
- Location
- Jackson, Butts County, GA
- Coordinates
- 33.2946, -83.9663 (approximate)
- Power capacity
- Not established from a public source
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- January 7, 2025
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- January 7, 2025ProposedAWS announced at least $11B of new data center capacity in Georgia, naming Butts and Douglas counties. Source: Amazon
Opposition and litigation at this site
Nothing on record as of August 28, 2026. No lawsuit, organized opposition, or contested hearing over AWS Butts County Data Center Campus in Jackson, Butts County, Georgia appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
Deliberately no site-level investment or job figure: the $11B and the "at least 550 new high-skilled jobs" in Amazon's release are entity-level totals covering BOTH the Butts County and Douglas County projects, and cannot be attributed to either site alone.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- How the community has received it
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- High Falls Road Data Center Campus (Montana Property Group) · Griffin · Montana Property Group LLC (developer; end user undisclosed)18 mi · Permitted
- Spalding Investments Data Center Campus (High Falls Road) · Griffin · Spalding Investments, LLC (developer; end user undisclosed)18 mi · Permitted
- Wallace Jackson Data Center Campus · Griffin · Wallace Jackson, LLC (developer; end user undisclosed)18 mi · Permitted · In litigation
- Serverfarm Covington Data Center (Hazelbrand Road) · Covington · Serverfarm22 mi · Under construction · Contested
- Lovejoy Data Center Campus (Stillwater Development) · Lovejoy · Stillwater Development24 mi · Cancelled · 1.3 GW · Opposed
- DC BLOX Atlanta East Hyperscale Data Center Campus · Conyers · DC BLOX25 mi · Under construction · 216 MW · Mixed reception
- TA Realty East Tanners Church Road Data Center · Ellenwood · TA Realty29 mi · Permitted · 180 MW
- Meta Newton Data Center (Stanton Springs) · Social Circle · Meta Platforms29 mi · Operating · In litigation
Questions people ask about this site
Is there opposition to the AWS Butts County Data Center Campus in Jackson?
Nothing on record as of August 28, 2026. No lawsuit, organized opposition, or contested hearing over AWS Butts County Data Center Campus in Jackson, Butts County, Georgia appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the AWS Butts County Data Center Campus?
No lawsuit over AWS Butts County Data Center Campus appears in the record we track as of August 28, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does AWS Butts County Data Center Campus use?
No water withdrawal figure for AWS Butts County Data Center Campus is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates AWS Butts County Data Center Campus, and how big is it?
Amazon Web Services is the operator on record. We hold 54 sites for that company across the registry. No capacity figure is on record for this site.
How to cite this page
SueDataCenters.org Data Center Registry, "AWS Butts County Data Center Campus," updated August 28, 2026, https://suedatacenters.org/data-centers/aws-butts-county-ga.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/aws-butts-county-ga, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.AWS plans to invest at least $11 billion in Georgia to expand infrastructure to support AI and cloud technologies · Amazon · retrieved August 28, 2026
- 2.Amazon plans $11 billion data center expansion in Georgia · The Atlanta Journal-Constitution · retrieved August 28, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us