Data Center Registry
Midtown Center Computing Facility (Former Walmart, 5825 W. Hope Ave.)
Milwaukee, Milwaukee County, Wisconsin
Midtown Center Computing Facility (Former Walmart, 5825 W. Hope Ave.) is a cancelled data center in Milwaukee, Wisconsin (Milwaukee County), operated by AFS Milwaukee LLC. The public record puts it at 10 MW planned.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Cancelled
- Operator
- AFS Milwaukee LLC
- Facility type
- Data center
- Location
- 5825 W. Hope Ave., Milwaukee, Milwaukee County, WI, 53216
- Coordinates
- 43.0929, -87.9851 (approximate)
- Power capacity
- 10 MW planned
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- July 6, 2026CancelledAld. Mark Chambers announced the computing research facility was removed from the redevelopment proposal after resident opposition. Source: BizTimes Milwaukee
- June 29, 2026ProposedThe Milwaukee City Plan Commission heard the redevelopment proposal, including a 19,000 sq ft computing facility, and held it without a decision. Source: BizTimes Milwaukee
Opposition and litigation at this site
Nothing on record as of October 16, 2026. No lawsuit, organized opposition, or contested hearing over Midtown Center Computing Facility (Former Walmart, 5825 W. Hope Ave.) in Milwaukee, Milwaukee County, Wisconsin appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
A small high-performance computing facility proposed for 19,000 sq ft of the 108,000 sq ft former Walmart at Midtown Center, with a stated maximum utility capacity of 10 MW. It was dropped in July 2026. The site redevelopment continues as self-storage, affordable housing and a library branch.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- How the community has received it
- Which utility serves it
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Data Holdings Milwaukee Data Center · Milwaukee · Data Holdings LLC4 mi · Operating · 10 MW
- Aventus Lakes Data Center · Milwaukee · Aventus Data Centers4 mi · Operating
- Wells Interconnection Data Center (Wells Building) · Milwaukee · Wells Interconnection5 mi · Operating
- TierPoint Milwaukee · Milwaukee · TierPoint6 mi · Operating
- ISCorp Mequon Data Center (MQS5) · Mequon · ISCorp8 mi · Operating
- N15W24250 Riverwood Drive Data Centre (Pewaukee) · Pewaukee · Mapletree Redwood Data Centre Trust13 mi · Operating
- Expedient MKE1 (Milwaukee/Franklin) · Franklin · Expedient16 mi · Operating · 1.6 MW
- CyberLynk Franklin Data Center (MKE1) · Franklin · CyberLynk Network, Inc.16 mi · Operating
Questions people ask about this site
Is there opposition to the Midtown Center Computing Facility (Former Walmart, 5825 W. Hope Ave.) in Milwaukee?
Nothing on record as of October 16, 2026. No lawsuit, organized opposition, or contested hearing over Midtown Center Computing Facility (Former Walmart, 5825 W. Hope Ave.) in Milwaukee, Milwaukee County, Wisconsin appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Midtown Center Computing Facility (Former Walmart, 5825 W. Hope Ave.)?
No lawsuit over Midtown Center Computing Facility (Former Walmart, 5825 W. Hope Ave.) appears in the record we track as of October 16, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Midtown Center Computing Facility (Former Walmart, 5825 W. Hope Ave.) use?
No water withdrawal figure for Midtown Center Computing Facility (Former Walmart, 5825 W. Hope Ave.) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Midtown Center Computing Facility (Former Walmart, 5825 W. Hope Ave.), and how big is it?
AFS Milwaukee LLC is the operator on record. Capacity on record is 10 MW.
How to cite this page
SueDataCenters.org Data Center Registry, "Midtown Center Computing Facility (Former Walmart, 5825 W. Hope Ave.)," updated October 16, 2026, https://suedatacenters.org/data-centers/afs-milwaukee-midtown-center-computing-facility-wi.
Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/afs-milwaukee-midtown-center-computing-facility-wi, retrieved October 29, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Plan Commission holds redevelopment proposal for former Midtown Center Walmart store following tense public hearing · BizTimes Milwaukee · retrieved October 16, 2026
- 2.Data computing facility removed from Midtown Center redevelopment proposal · BizTimes Milwaukee · retrieved October 16, 2026
- 3.OpenStreetMap/Nominatim geocode of 5825 West Hope Avenue, Midtown Center, Milwaukee 53216 · OpenStreetMap contributors · retrieved October 16, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us