Sue Data Centers

Data Center Registry

La Osa Data Center Park

Eloy, Pinal County, Arizona

CancelledOpposedAI likelyRecord updated August 28, 2026

La Osa Data Center Park is a cancelled data center in Eloy, Arizona (Pinal County), operated by Vermaland LLC. The public record puts it at announced 2025, 3,300 acres. It faces documented, organized local opposition.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Cancelled

Operator
Vermaland LLC
Facility type
Data center, AI use likely
Location
Eloy, Pinal County, AZ
Coordinates
32.7500, -111.5500
Power capacity
Not established from a public source
Land
3,300 acres
Investment
Not established from a public source
Announced
2025
Utility
Western Area Power Administration (WAPA), proposed grid transmission line upgrades for interconnect. APS and SRP not confirmed as utility providers.
Power source
Mixed
Cooling
Closed loop
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Opposed
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. August 28, 2026
    Cancelled
    The Pinal County Board of Supervisors voted 4-1 on August 26, 2026 to reject the La Osa Energy Center rezoning request and development plans, after the developer had already scaled the proposal back roughly 80% (from 59 data center buildings and 3 GW of demand to 11 buildings, a 500 MW gas plant, battery storage and a 1 GW cap) in response to opposition over aquifer drawdown and incomplete energy sourcing plans. Supervisor Stephen Miller cast the lone dissent. Recorded as cancelled because the entitlement the project required was denied; Vermaland has not publicly announced a withdrawal or a refiling, so this reflects the county's denial rather than a developer decision. Source: KJZZ
  2. 2026
    Proposed
    April 17, 2026: Pinal County land-use committee recommends advancing to full rezoning and site-plan review. No construction authorization granted; comprehensive plan amendment, drainage, flood mitigation, and road improvements still required. Source: Hoodline
  3. 2026
    Proposed
    May 2026: Operator announces 80% scale-back after all ~60 public comments opposed the project, revised plan reduces to 11 data centers and a 1 GW energy demand ceiling (down from 59 DCs / 3 GW). Board of Supervisors hearing rescheduled to August 26, 2026. Source: KJZZ (Arizona Public Radio)
  4. 2025
    Proposed
    Vermaland publicly announces La Osa Project (DCD: Aug 4, 2025; AZ Big Media: Sep 15, 2025); rezoning application filed with Pinal County ~April 2025. $33B/3 GW ceiling figures publicized. Pinal County Planning & Zoning Commission holds non-voting informational session July 17, 2025. Source: Data Center Dynamics

Opposition and litigation at this site

Yes. Organized local opposition to La Osa Data Center Park in Eloy, Pinal County, Arizona is documented in the public record, without a lawsuit on file in the sources we track. All approximately 60 public comments and 50 emails received by the Pinal County Board opposed the project.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: opposed means documented, organized local opposition is the dominant signal on record.

All approximately 60 public comments and 50 emails received by the Pinal County Board opposed the project. Concerns raised: location in a high-risk flood zone, wildlife and environmental impacts, water use risk, power bill impacts for local residents, construction timeline (gas plant likely last, 5-7 year timeline). Scale-back from 3 GW to 1 GW was a direct response to this opposition. Pinal County Supervisor Rich Vitiello expressed concern about constituent energy cost impacts.

Source: KJZZ (Arizona Public Radio)

Power and water

Phase 1 would rely on on-site natural gas turbines as primary power source, transitioning to solar as adjacent solar projects come online. Utility-scale battery storage included in original 3 GW plan. Hybrid model: gas + solar + battery + WAPA grid. On-site generation MW not specified in any source.

Developer's attorney stated commitment to air-cooled or closed-loop cooling to minimize water demand. Site borders the Greene Canal, raising concerns about water access and consumption in an arid region. No MGD figures have been published. Critics cited Pima County's 'Project Blue' hyperscale data center as a cautionary precedent for water misuse in Arizona desert developments.

Notes on the record

Vermaland LLC is a Phoenix-area land developer and land-banking company (CEO Kuldip 'Ken' Verma, founded 2006, controls ~25,000 acres of metro Phoenix land). DCD explicitly noted 'it is unclear whether Vermaland would operate its own data center facilities', Vermaland plans to sell or rent parcels/buildings to tenants. No end tenants or hyperscaler operators have been named as of July 2026. Original plan: 59 data centers, up to 3 GW capacity ceiling, up to $33B investment ceiling, 3,300-acre site south of Eloy along the Greene Canal. A separate adjacent 1,700-acre parcel already holds Industrial-2 zoning for data centers, gas plants, battery storage, and solar. After strong public opposition (all ~60 public comments opposed), operator announced May 2026 scale-back to 11 data centers and 1 GW ceiling. Board of Supervisors hearing scheduled August 26, 2026; no permits issued as of record date. Site lies adjacent to a Qualified Opportunity Zone (investor tax benefit; not a direct subsidy to Vermaland, no subsidy award confirmed, omitted). Coordinates are approximate (parcel south of Eloy city center along Greene Canal; no precise APN published). $33B investment and all GW figures are announced ceilings, not firm commitments.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Tax abatements or other public subsidy
  • Permanent jobs promised
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the La Osa Data Center Park in Eloy?

Yes. Organized local opposition to La Osa Data Center Park in Eloy, Pinal County, Arizona is documented in the public record, without a lawsuit on file in the sources we track. All approximately 60 public comments and 50 emails received by the Pinal County Board opposed the project.

Has anyone filed a lawsuit over the La Osa Data Center Park?

No lawsuit over La Osa Data Center Park appears in the record we track as of August 28, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does La Osa Data Center Park use?

No water withdrawal figure for La Osa Data Center Park is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates La Osa Data Center Park, and how big is it?

Vermaland LLC is the operator on record. No capacity figure is on record for this site. The site is recorded at 3300 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "La Osa Data Center Park," updated August 28, 2026, https://suedatacenters.org/data-centers/vermaland-la-osa-eloy-az.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/vermaland-la-osa-eloy-az, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Land developer Vermaland pitches $33bn data center in Arizona · Data Center Dynamics · retrieved July 7, 2026
  2. 2.$33 billion data center industrial park coming to Pinal County · AZ Big Media · retrieved July 7, 2026
  3. 3.Largest proposed data center in Arizona to be scaled back 80% after opposition · KJZZ (Arizona Public Radio) · retrieved July 7, 2026
  4. 4.Pinal County Advances Vermaland's La Osa Data Center Plan · Hoodline · retrieved July 7, 2026
  5. 5.$33B Data Center Park Eyed in Arizona · Commercial Property Executive · retrieved July 7, 2026
  6. 6.Pinal County rejects massive La Osa data center. Residents want more rules for future projects · KJZZ · retrieved August 28, 2026
  7. 7.Data centers in the Sonoran Desert, update (La Osa rezoning denied August 26, 2026) · Coalition for Sonoran Desert Protection · retrieved August 28, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us