Sue Data Centers

Data Center Registry

Dobson Farms East

Florence, Pinal County County, Arizona · All 6 EdgeCore Digital Infrastructure sites

PermittedNo reception on recordRecord updated September 23, 2026

Dobson Farms East is a permitted data center in Florence, Arizona (Pinal County County), operated by EdgeCore Digital Infrastructure. The public record puts it at 720 MW planned, 239 acres.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Permitted

Operator
EdgeCore Digital Infrastructure
Facility type
Data center
Location
Florence, Pinal County County, AZ
Coordinates
33.1183, -111.4733 (approximate)
Power capacity
720 MW planned
Land
239 acres
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Not established from a public source
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. September 23, 2026
    Permitted
    Included in the Florence Town Council's unanimous October 7, 2025 rezoning of 1,619 Dobson Farms acres from residential to industrial. Source: Pinal Post

Opposition and litigation at this site

Nothing on record as of September 23, 2026. No lawsuit, organized opposition, or contested hearing over Dobson Farms East in Florence, Pinal County County, Arizona appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

Notes on the record

239 acres at the northeast corner of Arizona Farms Road and Attaway Road; conceptual plan shows ten two-story data center buildings of roughly 332,100 sq ft each at about 72 MW apiece, which the source states as 720 MW total. EdgeCore appears as the party behind the concept plans, not yet as a confirmed owner of record. Coordinate derived from the OSM geometries of Arizona Farms Road and Attaway Road.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • How the community has received it
  • Which utility serves it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Free case review

Living near Dobson Farms East?

Tell us the basics and an independent attorney handling data center cases in your state will follow up. Free, and you are never obligated to hire anyone.

Questions people ask about this site

Is there opposition to the Dobson Farms East data center in Florence?

Nothing on record as of September 23, 2026. No lawsuit, organized opposition, or contested hearing over Dobson Farms East in Florence, Pinal County County, Arizona appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the Dobson Farms East data center?

No lawsuit over Dobson Farms East appears in the record we track as of September 23, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Dobson Farms East use?

No water withdrawal figure for Dobson Farms East is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Dobson Farms East, and how big is it?

EdgeCore Digital Infrastructure is the operator on record. We hold 6 sites for that company across the registry. Capacity on record is 720 MW. The site is recorded at 239 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Dobson Farms East," updated September 23, 2026, https://suedatacenters.org/data-centers/edgecore-dobson-farms-east-florence-az.

Facility data from Compute Atlas (E. Kubiak), version 1.34.0 (September 21, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/edgecore-dobson-farms-east-florence-az, retrieved October 1, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Florence Approves Data Centers on 1,619 Acres as Dobson Farms Becomes Major Tech Park · Pinal Post · retrieved September 23, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us