Data Center Registry
Merit Partners Legacy Business Park (Mesa)
Mesa, Maricopa County, Arizona
Merit Partners Legacy Business Park (Mesa) is a permitted data center in Mesa, Arizona (Maricopa County), operated by Undisclosed (landowner: Pacific Proving, LLC). The public record puts it at 43 acres.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Permitted
- Operator
- Undisclosed (landowner: Pacific Proving, LLC)
- Facility type
- Data center
- Location
- Mesa, Maricopa County, AZ
- Coordinates
- 33.2942, -111.6199 (approximate)
- Power capacity
- Not established from a public source
- Land
- 43 acres
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- August 26, 2024PermittedMesa City Council adopted annexation (Ord. 5870), rezoning to LI-PAD with a Council Use Permit to allow a data center (Ord. 5871), a minor General Plan amendment (Res. 12256) and a pre-annexation development agreement (Res. 12257), unanimously. Source: City of Mesa, Office of the City Clerk
Opposition and litigation at this site
Nothing on record as of November 5, 2026. No lawsuit, organized opposition, or contested hearing over Merit Partners Legacy Business Park (Mesa) in Mesa, Maricopa County, Arizona appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
Roughly 43 acres on the north side of East Pecos Road (9700-10000 blocks) and the west side of the future South Crismon alignment, Mesa District 6; owner Pacific Proving, LLC; applicant Gammage & Burnham, PLC. Rezoned from Agricultural to Light Industrial with a Planned Area Development overlay and Council Use Permit; the Council vote was 7-0 (Giles, Heredia, Duff, Freeman, Goforth, Somers, Spilsbury) with a 5-0 Planning and Zoning Board recommendation. No operator, capacity or construction is stated in the minutes. A separate parcel from the NTT Pacific Proving campus (east side of the Crismon alignment). The pin is the area-weighted centroid of Mesa's own ANX23-00800 annexation boundary and is approximate; the data center's footprint within it is not published.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- How the community has received it
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- NTT Global Data Centers Mesa, Pacific Proving Technology Park · Mesa · NTT Global Data Centersunder 1 mile · Proposed · 360 MW · Contested
- Meta Mesa Data Center · Mesa · Meta3 mi · Operating · 50 MW
- CyrusOne Mesa Campus (Mesa Elliot Technology Park) · Mesa · CyrusOne4 mi · Proposed · 198 MW
- NTT Phoenix PH1 Data Center · Mesa · NTT Global Data Centers4 mi · Operating · 36 MW
- EdgeConneX Mesa Campus (PHX11 / 3302 S Hawes Rd) · Mesa · EdgeConneX4 mi · Under construction · 115.2 MW
- Apple Mesa Data Center (Global Command Center) · Mesa · Apple5 mi · Operating
- Google Redhawk Mesa Data Center Campus · Mesa · Google6 mi · Operating · 400 MW · Supported
- EdgeCore Mesa Data Center Campus · Mesa · EdgeCore Digital Infrastructure6 mi · Operating · 450 MW · Supported
Questions people ask about this site
Is there opposition to the Merit Partners Legacy Business Park (Mesa) data center in Mesa?
Nothing on record as of November 5, 2026. No lawsuit, organized opposition, or contested hearing over Merit Partners Legacy Business Park (Mesa) in Mesa, Maricopa County, Arizona appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Merit Partners Legacy Business Park (Mesa) data center?
No lawsuit over Merit Partners Legacy Business Park (Mesa) appears in the record we track as of November 5, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Merit Partners Legacy Business Park (Mesa) use?
No water withdrawal figure for Merit Partners Legacy Business Park (Mesa) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Merit Partners Legacy Business Park (Mesa), and how big is it?
Undisclosed (landowner: Pacific Proving, LLC) is the operator on record. No capacity figure is on record for this site. The site is recorded at 43 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Merit Partners Legacy Business Park (Mesa)," updated November 5, 2026, https://suedatacenters.org/data-centers/merit-partners-legacy-business-park-mesa-az.
Facility data from Compute Atlas (E. Kubiak), version 1.35.1 (November 2, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/merit-partners-legacy-business-park-mesa-az, retrieved November 5, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Mesa City Council minutes, August 26, 2024 (Item 9, Merit Partners Legacy Business Park) · City of Mesa, Office of the City Clerk · retrieved November 5, 2026
- 2.City of Mesa Planning Case History, Annexations layer: ANX23-00800 (Ordinance 5870, adopted 2024-08-26, 42.13 acres) · City of Mesa, GIS · retrieved November 5, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us