Sue Data Centers

Data Center Registry

NTT Global Data Centers Mesa, Pacific Proving Technology Park

Mesa, Maricopa County, Arizona · All 15 NTT Global Data Centers sites

ProposedContestedAI likelyRecord updated August 8, 2026

NTT Global Data Centers Mesa, Pacific Proving Technology Park is a proposed data center in Mesa, Arizona (Maricopa County), operated by NTT Global Data Centers. The public record puts it at announced November 2023, 360 MW planned, 173 acres, a reported $300 million investment. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
NTT Global Data Centers
Facility type
Data center, AI use likely
Location
Mesa, Maricopa County, AZ
Coordinates
33.3025, -111.6200
Power capacity
360 MW planned
Land
173 acres
Investment
$300 million
Announced
November 2023
Utility
Salt River Project (SRP)
Power source
Grid
Cooling
Closed loop
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Contested
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. May 2026
    Proposed
    Mesa Planning Commission voted unanimously to recommend rezoning; council vote was pending summer 2026 Source: Data Center Dynamics
  2. May 2026
    Proposed
    Mesa's Planning and Zoning Board voted 4-0 to recommend that City Council approve NTT's rezoning, council use permit and major site plan modification for the 170-acre site at Pecos and Crismon roads. A recommendation only, the Council decision had not been taken. Source: Mesa Tribune
  3. November 2023
    Proposed
    Project first proposed as Pacific Proving Technology Park; NTT filed pre-submittal with City of Mesa

Opposition and litigation at this site

Yes. NTT Global Data Centers Mesa, Pacific Proving Technology Park in Mesa, Maricopa County, Arizona is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Residents packed June 2026 Mesa City Council meeting opposing rezoning, citing water use, heat, and drought.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.

Residents packed June 2026 Mesa City Council meeting opposing rezoning, citing water use, heat, and drought. Planning Commission voted 4-0 to recommend approval; council vote was pending summer 2026.

Source: Copper Courier

Power and water

On-site SRP substation and private power substation proposed

Closed-loop cooling proposed; community activists cite Arizona drought and Colorado River water stress

Notes on the record

investmentUsd is $300M land purchase only; total buildout investment is substantially higher. NE corner of Pecos and Crismon roads, far SE Mesa. Seven two-story buildings totaling 1.7M sq ft + warehouse + office. NTT's second Phoenix-area campus (existing 102-acre, 240MW campus is ~4 miles north on Elliot Road). Phase 1 targeted November 2028. Coordinates approximate for Pecos/Crismon intersection. Status refresh 2026-08-08: the Planning & Zoning Board recommended approval 4-0 in mid-May 2026; the article (updated 2026-06-08) said the proposal "will likely be heard in late July or mid-August by council". No fetched source records a Council vote, so the status stays "proposed", the 2026-07-20 date carried in earlier notes was an expected hearing date, not a decision.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Tax abatements or other public subsidy
  • Permanent jobs promised
Which document closes each gap
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the NTT Global Data Centers Mesa, Pacific Proving Technology Park data center in Mesa?

Yes. NTT Global Data Centers Mesa, Pacific Proving Technology Park in Mesa, Maricopa County, Arizona is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Residents packed June 2026 Mesa City Council meeting opposing rezoning, citing water use, heat, and drought.

Has anyone filed a lawsuit over the NTT Global Data Centers Mesa, Pacific Proving Technology Park data center?

No lawsuit over NTT Global Data Centers Mesa, Pacific Proving Technology Park appears in the record we track as of August 8, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does NTT Global Data Centers Mesa, Pacific Proving Technology Park use?

No water withdrawal figure for NTT Global Data Centers Mesa, Pacific Proving Technology Park is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates NTT Global Data Centers Mesa, Pacific Proving Technology Park, and how big is it?

NTT Global Data Centers is the operator on record. We hold 15 sites for that company across the registry. Capacity on record is 360 MW. The site is recorded at 173 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "NTT Global Data Centers Mesa, Pacific Proving Technology Park," updated August 8, 2026, https://suedatacenters.org/data-centers/ntt-global-mesa-az.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/ntt-global-mesa-az, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.NTT acquires 173-acre planned data center park in Mesa for $300m · Data Center Dynamics · retrieved July 6, 2026
  2. 2.Mesa residents are fighting a Tokyo tech giant's data center · Copper Courier · retrieved July 6, 2026
  3. 3.Big data center in SE Mesa passes first review, Planning & Zoning Board recommends approval 4-0 for the 170-acre site at Pecos and Crismon · Mesa Tribune · retrieved August 8, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us