Energy Generation and Technology Campus is a proposed data center in Maricopa, Arizona (Pinal County), operated by W Holdings. The public record puts it at announced October 16, 2025, 495 acres, a reported $9.5 billion investment. It faces documented, organized local opposition.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
W Holdings
Facility type
Data center
Location
Maricopa, Pinal County, AZ
Coordinates
32.9450, -112.0350 (approximate)
Power capacity
Not established from a public source
Land
495 acres
Investment
$9.5 billion
Announced
October 16, 2025
Utility
Not established from a public source
Power source
Mixed
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
500 permanent
Public subsidy
Not established from a public source
Community reception
Opposed
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. November 20, 2025
    Proposed
    Pinal County Board of Supervisors unanimously approved the major comprehensive plan land-use amendment; rezoning still required. Source: InMaricopa

Opposition and litigation at this site

Yes. Organized local opposition to Energy Generation and Technology Campus in Maricopa, Pinal County, Arizona is documented in the public record, without a lawsuit on file in the sources we track. The Ak-Chin Indian Community, whose southern boundary abuts the site, opposes the location.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: opposed means documented, organized local opposition is the dominant signal on record.

The Ak-Chin Indian Community, whose southern boundary abuts the site, opposes the location. Vice-chairwoman Delia Carlyle cited a high concentration of cultural artifacts and concern that ground disturbance would affect ancestral remains, while saying the community does not oppose development generally.

Source: Pinal Post

Power and water

Plan pairs data centers with an on-site natural gas power plant and battery energy storage. The applicant told the commission the campus would be powered primarily by the Griffin Energy Project (solar, gas and battery). No MW figure has been stated publicly.

Applicant projects roughly 500 acre-feet of water use annually. Cooling method not stated.

Notes on the record

Located south of the City of Maricopa, east of State Route 347 and west of the Nissan test track, abutting the southern boundary of the Ak-Chin Indian Community. Investment is recorded as the itemized $4B construction plus $5.5B equipment figure presented to the Planning and Zoning Commission; a separate report rounds the total to $10B. Acreage is also reported as 500 and, in one account, 656 acres. Some coverage associates the site with Copia Power; the applicant of record in commission and board coverage is W Holdings, represented by the same attorney who has appeared for Copia projects, so the corporate relationship is not established here.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Which utility serves it
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Energy Generation and Technology Campus in Maricopa?

Yes. Organized local opposition to Energy Generation and Technology Campus in Maricopa, Pinal County, Arizona is documented in the public record, without a lawsuit on file in the sources we track. The Ak-Chin Indian Community, whose southern boundary abuts the site, opposes the location.

Has anyone filed a lawsuit over the Energy Generation and Technology Campus?

No lawsuit over Energy Generation and Technology Campus appears in the record we track as of August 28, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Energy Generation and Technology Campus use?

No water withdrawal figure for Energy Generation and Technology Campus is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Energy Generation and Technology Campus, and how big is it?

W Holdings is the operator on record. No capacity figure is on record for this site. The site is recorded at 495 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Energy Generation and Technology Campus," updated August 28, 2026, https://suedatacenters.org/data-centers/w-holdings-energy-generation-technology-campus-maricopa-az.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/w-holdings-energy-generation-technology-campus-maricopa-az, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.$10 billion data center campus OK'd south of Maricopa · InMaricopa · retrieved August 28, 2026
  2. 2.Commission Recommends Data Center Campus Despite Resident, Tribal Pushback · Pinal Post · retrieved August 28, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us