Sue Data Centers

Data Center Registry

Project Midway Data Center

Casa Grande, Pinal County, Arizona

ProposedContestedRecord updated September 10, 2026

Project Midway Data Center is a proposed data center in Casa Grande, Arizona (Pinal County), operated by LPI Group. The public record puts it at announced November 19, 2025, 400 MW planned, 215 acres, a reported $6.6 billion investment. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
LPI Group
Facility type
Data center
Location
Casa Grande, Pinal County, AZ
Coordinates
32.8400, -111.7900 (approximate)
Power capacity
400 MW planned
Land
215 acres
Investment
$6.6 billion
Announced
November 19, 2025
Utility
Not established from a public source
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
225 permanent
Public subsidy
Not established from a public source
Community reception
Contested
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. November 19, 2025
    Proposed
    Pinal County Board of Supervisors voted 5-0 to approve the comprehensive plan amendment changing 215 acres from Moderate Low Density Residential to Employment. Rezoning approval is still required before construction. Source: Pinal Post

Opposition and litigation at this site

Yes. Project Midway Data Center in Casa Grande, Pinal County, Arizona is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Hidden Valley residents raised concerns about falling water tables and deeper well drilling, with one resident saying 'There needs to be a cap on the water, if any water is used.' A June 2026 opposition letter from a nearby homeowner linked a well pump burnout to lowered groundwater.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.

Hidden Valley residents raised concerns about falling water tables and deeper well drilling, with one resident saying 'There needs to be a cap on the water, if any water is used.' A June 2026 opposition letter from a nearby homeowner linked a well pump burnout to lowered groundwater. The county's staff recommendation carries 21 PAD stipulations responding to resident concerns, including an air-cooled or closed-loop cooling requirement, a landscaped berm and decibel limits with restricted generator-testing hours. The rezoning and PAD cases were postponed at the 16 July 2026 Planning and Zoning Commission hearing.

Source: Pinal Post

Notes on the record

Unincorporated Pinal County at the southwest corner of Selma Highway and Midway Road, roughly two miles south of the Casa Grande city limits but inside its planning area. The applicant projects about 225 permanent jobs at an average salary near $93,000 and $150 million in annual utility spend at full build-out. Reported acreage differs between sources (215 acres in the Pinal Post account, 294 acres in a same-day Pinal Central report); the 215-acre figure matches the comprehensive plan amendment as described. Capacity in MW has not been publicly stated.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Which utility serves it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Project Midway Data Center in Casa Grande?

Yes. Project Midway Data Center in Casa Grande, Pinal County, Arizona is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Hidden Valley residents raised concerns about falling water tables and deeper well drilling, with one resident saying 'There needs to be a cap on the water, if any water is used.' A June 2026 opposition letter from a nearby homeowner linked a well pump burnout to lowered groundwater.

Has anyone filed a lawsuit over the Project Midway Data Center?

No lawsuit over Project Midway Data Center appears in the record we track as of September 10, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Project Midway Data Center use?

No water withdrawal figure for Project Midway Data Center is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Project Midway Data Center, and how big is it?

LPI Group is the operator on record. Capacity on record is 400 MW. The site is recorded at 215 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Project Midway Data Center," updated September 10, 2026, https://suedatacenters.org/data-centers/lpi-group-project-midway-casa-grande-az.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/lpi-group-project-midway-casa-grande-az, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Project Midway Data Center Approved by Pinal County Supervisors · Pinal Post · retrieved August 28, 2026
  2. 2.Data Center Hearing: Project Midway Rezoning Set for July 16 · Pinal Post · retrieved September 10, 2026
  3. 3.Supervisors approve Project Midway data center near Casa Grande · retrieved September 10, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us