Green Data Spaceport America Data Center

Sierra County, New Mexico · All 2 Green Data sites

CancelledOpposedRecord updated September 10, 2026

Green Data Spaceport America Data Center is a cancelled data center in New Mexico (Sierra County), operated by Green Data / Aetherion Inc. The public record puts it at announced July 2026, 5 MW planned, 21 acres. It faces documented, organized local opposition.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Cancelled

Operator
Green Data / Aetherion Inc.
Facility type
Data center
Location
Sierra County, NM
Coordinates
32.9903, -106.9698 (approximate)
Power capacity
5 MW planned
Land
21 acres
Investment
Not established from a public source
Announced
July 2026
Utility
Not established from a public source
Power source
Mixed
Cooling
Closed loop
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Opposed
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. September 3, 2026
    Cancelled
    The NM State Land Office rejected the Aetherion/Green Data sublease proposal at Spaceport America on 2026-09-03, and Land Commissioner Stephanie Garcia Richard ruled Sierra County's 2026-07-21 data-center moratorium applies to Spaceport activity despite it sitting on state trust land. Spaceport's executive director Scott McLaughlin said the facility will honor the decision. The developer (Jason Bak) did not respond to comment and left the door open to a future proposal once moratoria expire, but this specific sublease proposal is dead as of this report. Source: Source New Mexico (via Yahoo News)
  2. September 3, 2026
    Coverage
  3. July 20, 2026
    Proposed
    Public records surfaced a State Land Office sublease application, signed by Spaceport America director Scott McLaughlin in February 2026, to rent land to Green Data developer Aetherion Inc. for $176,400 annually; the application remains under review by the Commissioner of Public Lands. Source: El Defensor Chieftain

Opposition and litigation at this site

Yes. Organized local opposition to Green Data Spaceport America Data Center in Sierra County, New Mexico is documented in the public record, without a lawsuit on file in the sources we track. Residents organized as 'Project Consequences'; the Sierra County Commission unanimously converted a resolution into an 18-month data center moratorium on July 21, 2026.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: opposed means documented, organized local opposition is the dominant signal on record.

Residents organized as 'Project Consequences'; the Sierra County Commission unanimously converted a resolution into an 18-month data center moratorium on July 21, 2026. No lease, sublease, construction or development agreement has been executed. On 2026-09-03 NM State Land Commissioner Stephanie Garcia Richard formally rejected the Aetherion sublease and ruled the county moratorium applies to Spaceport America despite it being state trust land, “Simply put, I will not be approving any data centers, including the proposed Aetherion sublease at Spaceport America” (see source 4). That rejection is why this record is now `cancelled`.

Source: Source New Mexico

Power and water

Proposal pairs on-site solar generation and battery storage covering 'a substantial portion' of demand with a utility connection; the developer's stated objective is to offset annual grid purchases with on-site renewable generation.

Proposed closed-loop system: ~30,300 gallon initial fill, ~15,300 gallons/year (~42 gal/day) makeup water. No water source had been identified or validated as of Aug 2026.

Notes on the record

Sited on state trust land inside Spaceport America's 18,000-acre lease outside Truth or Consequences. Current plan would occupy 21 acres within the horizontal launch area, possibly plus 30 additional acres. Spaceport America says discussions with Green Data have been ongoing since 2021 and that the project 'is not a relocation of the Socorro proposal'; only 'limited planning agreements' are in effect. Capacity has not been disclosed.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Which utility serves it
Which document closes each gap
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Questions people ask about this site

Is there opposition to the Green Data Spaceport America Data Center in Sierra County, New Mexico?

Yes. Organized local opposition to Green Data Spaceport America Data Center in Sierra County, New Mexico is documented in the public record, without a lawsuit on file in the sources we track. Residents organized as 'Project Consequences'; the Sierra County Commission unanimously converted a resolution into an 18-month data center moratorium on July 21, 2026.

Has anyone filed a lawsuit over the Green Data Spaceport America Data Center?

No lawsuit over Green Data Spaceport America Data Center appears in the record we track as of September 10, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Green Data Spaceport America Data Center use?

No water withdrawal figure for Green Data Spaceport America Data Center is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates Green Data Spaceport America Data Center, and how big is it?

Green Data / Aetherion Inc. is the operator on record. We hold 2 sites for that company across the registry. Capacity on record is 5 MW. The site is recorded at 21 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Green Data Spaceport America Data Center," updated September 10, 2026, https://suedatacenters.org/data-centers/green-data-spaceport-america-sierra-county-nm.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/green-data-spaceport-america-sierra-county-nm, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Spaceport America data center proposal sparks curiosity · El Defensor Chieftain · retrieved August 8, 2026
  2. 2.New Mexico county adopts data center moratorium as residents protest Spaceport proposal · Source New Mexico · retrieved August 8, 2026
  3. 3.Developer plans 'world's largest' green data center in Socorro (Spaceport America companion-project detail) · Albuquerque Journal · retrieved August 20, 2026
  4. 4.Spaceport America in talks with Green Data for data center project in Sierra County · Albuquerque Journal · retrieved September 3, 2026
  5. 5.New Mexico land commissioner shoots down Canadian data center company's pitch at Spaceport America · Source New Mexico (via Yahoo News) · retrieved September 10, 2026
  6. 6.Sierra County enacts 18-month data center moratorium in surprise vote · Albuquerque Journal · retrieved September 10, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us