Atterix Raton Advanced Digital Hub

Raton, Colfax County, New Mexico

ProposedOpposedAI likelyRecord updated September 3, 2026

Atterix Raton Advanced Digital Hub is a proposed data center in Raton, New Mexico (Colfax County), operated by Atterix LLC. The public record puts it at announced February 2026, 50 MW planned. It faces documented, organized local opposition.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
Atterix LLC
Facility type
Data center, AI use likely
Location
Raton, Colfax County, NM
Coordinates
36.9033, -104.4392 (approximate)
Power capacity
50 MW planned
Land
Not established from a public source
Investment
Not established from a public source
Announced
February 2026
Utility
Not established from a public source
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
0 permanent; 0 construction
Public subsidy
Not established from a public source
Community reception
Opposed
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. February 2026
    Proposed
    Raton City Commission approved a memorandum of understanding with Denver-based Atterix LLC for a six-month feasibility study on an advanced digital hub; the MOU bars the city from soliciting a similar project during that window. Source: KOB 4

Opposition and litigation at this site

Yes. Organized local opposition to Atterix Raton Advanced Digital Hub in Raton, Colfax County, New Mexico is documented in the public record, without a lawsuit on file in the sources we track. More than 100 residents organized as 'Protect Our Resources' to press city leaders to stop or slow the project, citing noise and light pollution and water and electricity use in a town of about 6,000; the City Commission has been weighing a temporary data center moratorium.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: opposed means documented, organized local opposition is the dominant signal on record.

More than 100 residents organized as 'Protect Our Resources' to press city leaders to stop or slow the project, citing noise and light pollution and water and electricity use in a town of about 6,000; the City Commission has been weighing a temporary data center moratorium.

Source: KOB 4

Notes on the record

Three-phase proposal: Phase 1 would convert a former Kmart on the south side of Raton into a data center drawing up to 5 MW, with later phases at a nearby power station and the city airport over roughly five years, totalling up to 50 MW. Nothing is approved, the feasibility study period ran to early August 2026 and the City Commission must still authorize any development. Atterix was incorporated in Colorado in December 2025.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Land area
  • Which utility serves it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Land area
The rezoning application, the plat, or the deed recorded with the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Questions people ask about this site

Is there opposition to the Atterix Raton Advanced Digital Hub data center in Raton?

Yes. Organized local opposition to Atterix Raton Advanced Digital Hub in Raton, Colfax County, New Mexico is documented in the public record, without a lawsuit on file in the sources we track. More than 100 residents organized as 'Protect Our Resources' to press city leaders to stop or slow the project, citing noise and light pollution and water and electricity use in a town of about 6,000; the City Commission has been weighing a temporary data center moratorium.

Has anyone filed a lawsuit over the Atterix Raton Advanced Digital Hub data center?

No lawsuit over Atterix Raton Advanced Digital Hub appears in the record we track as of September 3, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Atterix Raton Advanced Digital Hub use?

No water withdrawal figure for Atterix Raton Advanced Digital Hub is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Atterix Raton Advanced Digital Hub, and how big is it?

Atterix LLC is the operator on record. Capacity on record is 50 MW.

How to cite this page

SueDataCenters.org Data Center Registry, "Atterix Raton Advanced Digital Hub," updated September 3, 2026, https://suedatacenters.org/data-centers/atterix-raton-digital-hub-nm.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/atterix-raton-digital-hub-nm, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.AI data center proposal in Raton draws opposition · The Santa Fe New Mexican · retrieved August 8, 2026
  2. 2.Raton residents push back on proposed data center plans · KOB 4 · retrieved August 8, 2026
  3. 3.Small northern New Mexico city postpones decision on data center moratorium · Source New Mexico · retrieved August 8, 2026
  4. 4.Raton residents push back on proposed data center plans · KOB 4 · retrieved August 20, 2026
  5. 5.Raton residents push back on proposed data center plans · KOB 4 · retrieved September 3, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.