Teraplex Gallup Tradeport Data Center

Gallup, McKinley County, New Mexico

ProposedContestedRecord updated September 15, 2026

Teraplex Gallup Tradeport Data Center is a proposed data center in Gallup, New Mexico (McKinley County), operated by Teraplex Data Centers LLC. The public record puts it at 330 acres. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
Teraplex Data Centers LLC
Facility type
Data center
Location
Gallup, McKinley County, NM
Coordinates
35.5203, -108.8367 (approximate)
Power capacity
Not established from a public source
Land
330 acres
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Not established from a public source
Power source
Mixed
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
300 permanent; 2,500 construction
Public subsidy
Not established from a public source
Community reception
Contested
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. April 28, 2026
    Proposed
    Gallup City Council deferred action on the treated-effluent option agreement amendment; the project has no approval and the effluent amendment was still unapproved as of mid-July 2026. Source: Gallup Sun

Opposition and litigation at this site

Yes. Teraplex Gallup Tradeport Data Center in Gallup, McKinley County, New Mexico is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. About a dozen residents spoke against the project at the April 28, 2026 Gallup City Council meeting, citing water rights and unfulfilled promises from similar projects; the council voted to defer the third amendment to the effluent option agreement, with the mayor the sole 'no' vote on deferral.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.

About a dozen residents spoke against the project at the April 28, 2026 Gallup City Council meeting, citing water rights and unfulfilled promises from similar projects; the council voted to defer the third amendment to the effluent option agreement, with the mayor the sole 'no' vote on deferral.

Source: Gallup Sun

Power and water

Developer describes a mix of on-site solar and natural gas generation and says the campus would not draw from Gallup's municipal power grid. No MW figure has been disclosed publicly.

Teraplex sought an option to buy up to 109.5 million gallons (about 336 acre-feet) of treated effluent annually from the City of Gallup at $5.66 per 1,000 gallons through 2040, reclaimed wastewater, not potable supply. Gallup's treatment plant processes about 2.3 million gallons per day. Heat-rejection method not disclosed, so coolingType is left unset.

Notes on the record

Proposed on the Gallup/McKinley County Regional Tradeport off Carbon Coal Road, north of Mentmore. Teraplex is a Washington, D.C.-based firm incorporated in late 2025; co-founder Greg Thompson is the public spokesperson, and he has named Oracle, Meta, Amazon and Microsoft only as example tenant types, not as signed tenants. Agreement terms require land purchase within four years and construction start within five years of purchase or the city may cancel. Coordinate is a locality-level approximation anchored on Mentmore/Gallup, not a parcel-confirmed point.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Which utility serves it
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Free case review

Living near Teraplex Gallup Tradeport Data Center?

Tell us the basics and an independent attorney handling data center cases in your state will follow up. Free, and you are never obligated to hire anyone.

Questions people ask about this site

Is there opposition to the Teraplex Gallup Tradeport Data Center in Gallup?

Yes. Teraplex Gallup Tradeport Data Center in Gallup, McKinley County, New Mexico is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. About a dozen residents spoke against the project at the April 28, 2026 Gallup City Council meeting, citing water rights and unfulfilled promises from similar projects; the council voted to defer the third amendment to the effluent option agreement, with the mayor the sole 'no' vote on deferral.

Has anyone filed a lawsuit over the Teraplex Gallup Tradeport Data Center?

No lawsuit over Teraplex Gallup Tradeport Data Center appears in the record we track as of September 15, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Teraplex Gallup Tradeport Data Center use?

No water withdrawal figure for Teraplex Gallup Tradeport Data Center is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Teraplex Gallup Tradeport Data Center, and how big is it?

Teraplex Data Centers LLC is the operator on record. No capacity figure is on record for this site. The site is recorded at 330 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Teraplex Gallup Tradeport Data Center," updated September 15, 2026, https://suedatacenters.org/data-centers/teraplex-gallup-tradeport-mckinley-county-nm.

Facility data from Compute Atlas (E. Kubiak), version 1.34.0 (September 21, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/teraplex-gallup-tradeport-mckinley-county-nm, retrieved October 1, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Data center dilemma · Gallup Sun · retrieved September 15, 2026
  2. 2.New Mexico Data Center Policy, Gallup Tradeport entry and local ordinance table · Server Country · retrieved September 15, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us