Data Center Registry
Culpeper Acquisitions Brandy Station Campus (denied)
Brandy Station, Culpeper County, Virginia
Culpeper Acquisitions Brandy Station Campus (denied) is a cancelled data center in Brandy Station, Virginia (Culpeper County), operated by Culpeper Acquisitions LLC. The public record puts it at announced 2024.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Cancelled
- Operator
- Culpeper Acquisitions LLC
- Facility type
- Data center, AI use likely
- Location
- Brandy Station, Culpeper County, VA
- Coordinates
- 38.5095, -77.8863
- Power capacity
- Not established from a public source
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- 2024
- Utility
- Dominion Energy
- Power source
- Grid
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- June 12, 2024CancelledUnanimously denied by Culpeper County Planning Commission; concerns over rural preservation and proximity to Culpeper Battlefields State Park Source: Data Center Watch
- 2024Proposed$12B, 426-acre hyperscale campus proposed; end user not publicly confirmed (reported possibly Google or Meta) Source: Data Center Watch
Opposition and litigation at this site
Nothing on record as of July 24, 2026. No lawsuit, organized opposition, or contested hearing over Culpeper Acquisitions Brandy Station Campus (denied) in Brandy Station, Culpeper County, Virginia appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Power and water
Grid-only proposal. County/PEC documents state Dominion Energy is obligated to supply power and would need a new large substation and 2-5 miles of new transmission line for the 700MW-1.8GW load. No on-site or dedicated generation is proposed; no REC (Rappahannock Electric Cooperative) role is mentioned.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- How the community has received it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- EdgeCore Culpeper Data Center Campus · Culpeper · EdgeCore Digital Infrastructure5 mi · Proposed · 216 MW
- Remington Technology Park · Remington · PointOne Holdings Inc.5 mi · Permitted · 600 MW · Contested
- SAMX Data Centers · Remington · SAMX Data LLC5 mi · Proposed
- Convergent Technology Park · Remington · Convergent VA LLC5 mi · Proposed · Contested
- Red Ace Data Center · Culpeper · Red Ace Capital Management6 mi · Permitted · Mixed reception
- Gigaland Data Centers · Remington · Gigaland LLC7 mi · Proposed · Contested
- Blackwell Road Data Center (Warrenton) · Warrenton · Amazon Data Services16 mi · Permitted · 40 MW · In litigation
- Vint Hill Corners · Vint Hill · Vint Hill Corners LLC20 mi · Proposed · Contested
Questions people ask about this site
Is there opposition to the Culpeper Acquisitions Brandy Station Campus (denied) in Brandy Station?
Nothing on record as of July 24, 2026. No lawsuit, organized opposition, or contested hearing over Culpeper Acquisitions Brandy Station Campus (denied) in Brandy Station, Culpeper County, Virginia appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Culpeper Acquisitions Brandy Station Campus (denied)?
No lawsuit over Culpeper Acquisitions Brandy Station Campus (denied) appears in the record we track as of July 24, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Culpeper Acquisitions Brandy Station Campus (denied) use?
No water withdrawal figure for Culpeper Acquisitions Brandy Station Campus (denied) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Culpeper Acquisitions Brandy Station Campus (denied), and how big is it?
Culpeper Acquisitions LLC is the operator on record. No capacity figure is on record for this site.
How to cite this page
SueDataCenters.org Data Center Registry, "Culpeper Acquisitions Brandy Station Campus (denied)," updated July 24, 2026, https://suedatacenters.org/data-centers/culpeper-brandy-station-va.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/culpeper-brandy-station-va, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Data Center Watch, Blocked and Delayed Projects Report · Data Center Watch · retrieved July 5, 2026
- 2.Communities are blocking billions in data centers, Fortune · Fortune · retrieved July 5, 2026
- 3.PEC, New data center proposals in Brandy Station and near the Town of Culpeper (incl. BoardDocs public submittal) · retrieved July 24, 2026
- 4.DCD, County planners recommend denial of Brandy Station data center campus in Culpeper County · retrieved July 24, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us