Sue Data Centers

Data Center Registry

Red Ace Data Center

Culpeper, Culpeper County, Virginia

PermittedMixed receptionRecord updated July 26, 2026

Red Ace Data Center is a permitted data center in Culpeper, Virginia (Culpeper County), operated by Red Ace Capital Management. The public record puts it at 69.19 acres, a reported $350 million investment. It has documented support and documented opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Permitted

Operator
Red Ace Capital Management
Facility type
Data center
Location
Culpeper, Culpeper County, VA
Coordinates
38.4740, -77.9970 (approximate)
Power capacity
Not established from a public source
Land
69.19 acres
Investment
$350 million
Announced
Not established from a public source
Utility
Not established from a public source
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Mixed reception
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. July 1, 2026
    Permitted
    69.19 acres rezoned Rural to Light Industrial (4-3 vote, July 2026). Source: Data Center Dynamics

Opposition and litigation at this site

Partly. Both documented support and documented opposition to Red Ace Data Center in Culpeper, Culpeper County, Virginia appear in the record, with no clear majority position. Rezoning (Rural to Light Industrial) approved on a divided 4-3 vote, July 2026.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: mixed reception means documented support and documented opposition both exist with no clear majority position on record.

Rezoning (Rural to Light Industrial) approved on a divided 4-3 vote, July 2026.

Notes on the record

69.19 acres rezoned Rural to Light Industrial (4-3 vote, July 2026); 1.16M sq ft, on-site substation, completion targeted 2028.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Which utility serves it
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Red Ace Data Center in Culpeper?

Partly. Both documented support and documented opposition to Red Ace Data Center in Culpeper, Culpeper County, Virginia appear in the record, with no clear majority position. Rezoning (Rural to Light Industrial) approved on a divided 4-3 vote, July 2026.

Has anyone filed a lawsuit over the Red Ace Data Center?

No lawsuit over Red Ace Data Center appears in the record we track as of July 26, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Red Ace Data Center use?

No water withdrawal figure for Red Ace Data Center is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Red Ace Data Center, and how big is it?

Red Ace Capital Management is the operator on record. No capacity figure is on record for this site. The site is recorded at 69.19 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Red Ace Data Center," updated July 26, 2026, https://suedatacenters.org/data-centers/red-ace-data-center-culpeper-va.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/red-ace-data-center-culpeper-va, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Data center campus in Virginia's Culpeper County gets approval · Data Center Dynamics · retrieved July 17, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us