Sue Data Centers

Data Center Registry

Greenidge Spartanburg (South Carolina)

Spartanburg, Spartanburg County, South Carolina · All 3 Greenidge Generation sites

CancelledNo reception on recordRecord updated September 10, 2026

Greenidge Spartanburg (South Carolina) is a cancelled crypto mining site in Spartanburg, South Carolina (Spartanburg County), operated by Greenidge Generation. The public record puts it at announced January 25, 2022, 100 MW planned, 175 acres, a reported $264 million investment.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Cancelled

Operator
Greenidge Generation
Facility type
Crypto mining
Location
300 Jones Road, Spartanburg, Spartanburg County, SC, 29307
Coordinates
34.9494, -81.9250 (approximate)
Power capacity
100 MW planned
Land
175 acres
Investment
$264 million
Announced
January 25, 2022
Utility
Not established from a public source
Power source
Grid
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
40 permanent
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Confirmed by multiple independent sources or official documentation

Opposition and litigation at this site

Nothing on record as of September 10, 2026. No lawsuit, organized opposition, or contested hearing over Greenidge Spartanburg (South Carolina) in Spartanburg, Spartanburg County, South Carolina appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

Power and water

Grid-drawn (Duke Energy service territory); no on-site generation, unlike the Dresden, NY plant.

Notes on the record

Former LSC Communications/RR Donnelley printing plant (175 acres, bought Dec 2021 for $15M); unveiled Jan 2022 as a planned $264M, up-to-100MW buildout. Greenidge built 44 MW of Bitcoin mining, transferred to NYDIG in 2023 as a debt-settlement; per Greenidge's SEC filings the NYDIG hosting arrangement now covers 'substantially all' of Greenidge's mining capacity at the New York facility, not South Carolina. The remaining 152 acres + 60 MW power rights went through a failed Nov 2024 sale to Data Journey LLC (terminated Aug 2025) before Greenidge sold the land outright to a Lightstone Group / Lighthouse Datacenters affiliate on Dec 11, 2025. Status cancelled: Greenidge holds no confirmed ongoing operating interest as of its most recent 10-Q. Re-checked 2026-09-10: 'cancelled' status for Greenidge's own project remains accurate and is further confirmed -- Greenidge closed the sale of the 152-acre Spartanburg property (for $18.0M cash plus up to $18.0M in earnouts) to an affiliate of The Lightstone Group and LightHouse Data Centers in December 2025. CORRECTION-adjacent flag: the site itself is not dead land -- the buyer (Lightstone/LightHouse) may pursue a new, differently-owned data center project there. That would be a NEW facility for the discovery lane to evaluate, out of scope for this refresh record.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • How the community has received it
  • Which utility serves it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Greenidge Spartanburg (South Carolina) data center in Spartanburg?

Nothing on record as of September 10, 2026. No lawsuit, organized opposition, or contested hearing over Greenidge Spartanburg (South Carolina) in Spartanburg, Spartanburg County, South Carolina appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the Greenidge Spartanburg (South Carolina) data center?

No lawsuit over Greenidge Spartanburg (South Carolina) appears in the record we track as of September 10, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Greenidge Spartanburg (South Carolina) use?

No water withdrawal figure for Greenidge Spartanburg (South Carolina) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Greenidge Spartanburg (South Carolina), and how big is it?

Greenidge Generation is the operator on record. We hold 3 sites for that company across the registry. Capacity on record is 100 MW. The site is recorded at 175 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Greenidge Spartanburg (South Carolina)," updated September 10, 2026, https://suedatacenters.org/data-centers/greenidge-spartanburg-sc.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/greenidge-spartanburg-sc, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Greenidge Generation Establishing Operations in Spartanburg County · Office of SC Governor Henry McMaster · retrieved August 5, 2026
  2. 2.Greenidge Sells South Carolina Land and Power Rights as Bitcoin Mining Footprint Shrinks · TheMinerMag / TheEnergyMag · retrieved August 5, 2026
  3. 3.Greenidge Generation Holdings Inc. Form 10-Q, Q3 FY2025 · SEC EDGAR · retrieved August 5, 2026
  4. 4.Greenidge Generation Establishing Operations in Spartanburg County · Office of SC Governor Henry McMaster · retrieved August 16, 2026
  5. 5.Greenidge Generation establishing operations in Spartanburg County · South Carolina Department of Commerce · retrieved August 26, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us