Beale Infrastructure Gardner Campus

Gardner, Johnson County, Kansas · All 6 Beale Infrastructure sites

ProposedOpposedAI likelyRecord updated July 26, 2026

Beale Infrastructure Gardner Campus is a proposed data center in Gardner, Kansas (Johnson County), operated by Beale Infrastructure. The public record puts it at 300 acres. It faces documented, organized local opposition.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
Beale Infrastructure
Facility type
Data center, AI use likely
Location
Gardner, Johnson County, KS
Coordinates
38.8100, -94.9300
Power capacity
Not established from a public source
Land
300 acres
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Evergy
Power source
Grid
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Opposed
Source confidence
Reported by at least one credible outlet or filing

Opposition and litigation at this site

Yes. Organized local opposition to Beale Infrastructure Gardner Campus in Gardner, Johnson County, Kansas is documented in the public record, without a lawsuit on file in the sources we track. Beale Infrastructure withdrew its Gardner application on May 7, 2026, days after roughly 100 residents (30+ speaking against) packed a May 4 city council meeting and the city said no incentives would be granted.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: opposed means documented, organized local opposition is the dominant signal on record.

Beale Infrastructure withdrew its Gardner application on May 7, 2026, days after roughly 100 residents (30+ speaking against) packed a May 4 city council meeting and the city said no incentives would be granted.

Source

Power and water

New private on-site substation plus a new Evergy substation. Part of a Feb 2026 Evergy 1.9GW electric service agreement batch alongside Google and Meta.

Notes on the record

Near 191st St & S Clare Rd. Up to 16 data halls. Distinct from Beale's existing tracked Project Pilot in De Soto, KS. Coordinates are approximate.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Beale Infrastructure Gardner Campus in Gardner?

Yes. Organized local opposition to Beale Infrastructure Gardner Campus in Gardner, Johnson County, Kansas is documented in the public record, without a lawsuit on file in the sources we track. Beale Infrastructure withdrew its Gardner application on May 7, 2026, days after roughly 100 residents (30+ speaking against) packed a May 4 city council meeting and the city said no incentives would be granted.

Has anyone filed a lawsuit over the Beale Infrastructure Gardner Campus?

No lawsuit over Beale Infrastructure Gardner Campus appears in the record we track as of July 26, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Beale Infrastructure Gardner Campus use?

No water withdrawal figure for Beale Infrastructure Gardner Campus is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Beale Infrastructure Gardner Campus, and how big is it?

Beale Infrastructure is the operator on record. We hold 6 sites for that company across the registry. No capacity figure is on record for this site. The site is recorded at 300 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Beale Infrastructure Gardner Campus," updated July 26, 2026, https://suedatacenters.org/data-centers/beale-gardner-johnson-county-ks.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/beale-gardner-johnson-county-ks, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Gardner, Kansas project page · Beale Infrastructure · retrieved July 9, 2026 · original offline, archived copy from May 5, 2026
  2. 2.KCUR · retrieved July 26, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us