DAMAC Digital Logistics Park Data Center
Edgerton, Johnson County, Kansas
DAMAC Digital Logistics Park Data Center is a permitted data center in Edgerton, Kansas (Johnson County), operated by DAMAC Digital Solutions Kansas, LLC. It is or has been the subject of litigation over its siting, permitting, or operation.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
What our reporting adds
Our case file documents this site. Dismissed. Johnson County District Judge Stephanie Goodenow granted the residents' motion to strike under Kansas's Public Speech Protection Act, per KSHB 41 on September 5, 2026; a separate suit by a petitioner's husband against the city clerk has a show cause hearing September 24, 2026 on whether the petition goes on the November ballot.
Facility record
Permitted
- Operator
- DAMAC Digital Solutions Kansas, LLC
- Facility type
- Data center
- Location
- Edgerton, Johnson County, KS
- Coordinates
- 38.7642, -95.0083 (approximate)
- Power capacity
- Not established from a public source
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- In litigation
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- September 5, 2026PermittedA Johnson County judge grants the petitioners' motion to strike and dismisses the city's suit against them under the Public Speech Protection Act, per KSHB 41. A show cause hearing on whether the petition reaches the November ballot is set for September 24, 2026.
- August 14, 2026PermittedCity of Edgerton files suit against the petitioners.
- July 16, 2026PermittedCity Council approves the site plan appeal 4 to 0 for the conversion of an existing building at Logistics Park, adjacent to the BNSF intermodal facility.
Opposition and litigation at this site
Yes. DAMAC Digital Logistics Park Data Center in Edgerton, Johnson County, Kansas is or has been the subject of litigation over its siting, permitting, or operation. Dismissed.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: in litigation means the facility is or has been the subject of a lawsuit related to its siting, permitting, or operation.
Dismissed. Johnson County District Judge Stephanie Goodenow granted the residents' motion to strike under Kansas's Public Speech Protection Act, per KSHB 41 on September 5, 2026; a separate suit by a petitioner's husband against the city clerk has a show cause hearing September 24, 2026 on whether the petition goes on the November ballot. DAMAC Digital Solutions Kansas, LLC converting an existing building at Logistics Park, adjacent to the BNSF intermodal facility; City Council approved the site plan appeal 4 to 0 on July 16, 2026. A citizen petition to ban high-impact data centers was filed July 15, 2026 and verified as sufficient by the Johnson County Election Office. The city sued its own residents on August 14, 2026 in Johnson County District Court for a declaratory judgment voiding the petition and an injunction against a vote.
Notes on the record
Conversion of an existing building at Logistics Park in Edgerton, adjacent to the BNSF intermodal facility.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Our reporting on this site
- City of Edgerton v. Its Own Residents · Dismissed
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Beale Infrastructure Gardner Campus · Gardner · Beale Infrastructure5 mi · Proposed · Opposed
- Beale Project Pilot (De Soto) · De Soto · Beale Infrastructure14 mi · Under construction · Mixed reception
- TierPoint Kansas City - Lenexa · Lenexa · TierPoint18 mi · Operating
- QTS Overland Park Data Center (OVP1) · Overland Park · QTS Data Centers20 mi · Operating
- Project Red Wolf · Kansas City · Red Wolf DCD Properties LLC26 mi · Proposed · 600 MW · In litigation
Questions people ask about this site
Is there opposition to the DAMAC Digital Logistics Park Data Center in Edgerton?
Yes. DAMAC Digital Logistics Park Data Center in Edgerton, Johnson County, Kansas is or has been the subject of litigation over its siting, permitting, or operation. Dismissed.
Has anyone filed a lawsuit over the DAMAC Digital Logistics Park Data Center?
Yes. This site is recorded as being in litigation. The case, the court, and the filings we hold are listed on this page under the timeline and the sources.
How much water does DAMAC Digital Logistics Park Data Center use?
No water withdrawal figure for DAMAC Digital Logistics Park Data Center is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates DAMAC Digital Logistics Park Data Center, and how big is it?
DAMAC Digital Solutions Kansas, LLC is the operator on record. No capacity figure is on record for this site.
How to cite this page
SueDataCenters.org Data Center Registry, "DAMAC Digital Logistics Park Data Center," updated September 5, 2026, https://suedatacenters.org/data-centers/damac-logistics-park-edgerton-ks.
Facility record compiled by SueDataCenters.org from the public documents cited on the page, last updated September 5, 2026.
Corrections with a public source are welcome through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As cited in our case file. Every figure on this page traces to one of these documents.
- 1.Edgerton calls citizen petition void and invalid, files suit to block data center ban · KCTV5 · retrieved September 2, 2026
- 2.Judge dismisses Edgerton, Kansas, lawsuit against citizens in data center debate · KSHB 41 · retrieved September 5, 2026
- 3.City of Edgerton v. Its Own Residents: The Kansas Lawsuit to Kill a Citizen Data Center Ban · SueDataCenters.org · retrieved September 5, 2026
- 4.Programs.com: Data center moratoriums by state, tracker and statistics (as of August 26, 2026) · programs.com · retrieved September 5, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us