Sue Data Centers

Data Center Registry

DataBank MCI3 South Lake Campus Data Center

Lenexa, Johnson County, Kansas · All 29 DataBank sites

OperatingNo reception on recordRecord updated October 4, 2026

DataBank MCI3 South Lake Campus Data Center is an operating data center in Lenexa, Kansas (Johnson County), operated by DataBank. The public record puts it at 12.75 MW operating.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Operating

Operator
DataBank
Facility type
Data center
Location
11200 Lakeview Ave, Lenexa, Johnson County, KS
Coordinates
38.9257, -94.7695 (approximate)
Power capacity
12.75 MW operating
Land
Not established from a public source
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Not established from a public source
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Confirmed by multiple independent sources or official documentation

Opposition and litigation at this site

Nothing on record as of October 4, 2026. No lawsuit, organized opposition, or contested hearing over DataBank MCI3 South Lake Campus Data Center in Lenexa, Johnson County, Kansas appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

Notes on the record

Operator's own site lists this as (MCI3) South Lake Campus Data Center, 69,762 IT sq ft, 12.75MW critical IT load, 15 onsite carriers -- one of two named DataBank facilities in the Kansas City metro (the other is the separate Pine Ridge / Overland Park site, recorded separately). Coordinates are the US Census geocode of the listed street address, retrieved 2026-09-13; precision set to approximate since the parcel/building footprint was not independently confirmed.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Land area
  • How the community has received it
  • Which utility serves it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Land area
The rezoning application, the plat, or the deed recorded with the county.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Tell us about your situation

Living near DataBank MCI3 South Lake Campus Data Center?

Tell us the basics. Where a participating attorney in your state is available, we may share your information with them with your consent. Free, no obligation, and no guarantee anyone will contact you.

Questions people ask about this site

Is there opposition to the DataBank MCI3 South Lake Campus Data Center in Lenexa?

Nothing on record as of October 4, 2026. No lawsuit, organized opposition, or contested hearing over DataBank MCI3 South Lake Campus Data Center in Lenexa, Johnson County, Kansas appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the DataBank MCI3 South Lake Campus Data Center?

No lawsuit over DataBank MCI3 South Lake Campus Data Center appears in the record we track as of October 4, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does DataBank MCI3 South Lake Campus Data Center use?

No water withdrawal figure for DataBank MCI3 South Lake Campus Data Center is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates DataBank MCI3 South Lake Campus Data Center, and how big is it?

DataBank is the operator on record. We hold 29 sites for that company across the registry. Capacity on record is 12.75 MW.

How to cite this page

SueDataCenters.org Data Center Registry, "DataBank MCI3 South Lake Campus Data Center," updated October 4, 2026, https://suedatacenters.org/data-centers/databank-lenexa-ks.

Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/databank-lenexa-ks, retrieved October 11, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Kansas City Data Center and Colocation Solutions · DataBank · retrieved September 13, 2026
  2. 2.DataBank Kansas City MCI3 · Baxtel · retrieved October 4, 2026

Is a data center disrupting your home?

Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.

  • Tell us about your situation
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us