Facility record
Cancelled
- Operator
- Lakeland Equity Group
- Facility type
- Data center
- Location
- 3560 East 55th Street, Cleveland, Cuyahoga County, OH, 44105
- Coordinates
- 41.4617, -81.6512 (approximate)
- Power capacity
- 150 MW planned
- Land
- 35 acres
- Investment
- $1.6 billion
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Closed loop
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- Opposed
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- May 14, 2026CancelledCity of Cleveland rejected the permit application. Source: WKYC via Yahoo News
- May 6, 2026ProposedPermit application filed with the City of Cleveland Building Department. Source: NEOtrans
Opposition and litigation at this site
Yes. Organized local opposition to East 55th Street Data Center (Slavic Village) in Cleveland, Cuyahoga County, Ohio is documented in the public record, without a lawsuit on file in the sources we track. Mayor Justin Bibb's administration rejected the building permit on May 14, 2026; a city spokesperson cited serious concerns about hyperscale, standalone data centers in neighborhoods, and City Council was concurrently weighing a moratorium.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: opposed means documented, organized local opposition is the dominant signal on record.
Mayor Justin Bibb's administration rejected the building permit on May 14, 2026; a city spokesperson cited serious concerns about hyperscale, standalone data centers in neighborhoods, and City Council was concurrently weighing a moratorium.
Power and water
Plans described closed-loop cooling with water drawn from nearby watersheds or a Northeast Ohio Regional Sewer District stormwater overflow tunnel then under construction.
Notes on the record
Three two-story buildings totaling roughly 300,000 sq ft on a 35-acre site between I-77 and East 55th Street, currently owned by Morabito Enterprises. No end user was identified. Recorded as cancelled because the city rejected the permit application; the developer's next steps were not stated.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Tax abatements or other public subsidy
- Permanent jobs promised
- Which utility serves it
Which document closes each gap
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Lumen Cleveland 1 · Cleveland · Lumen Technologies3 mi · Operating
- DataBank Cleveland (CLE1) · Cleveland · DataBank3 mi · Operating · 0.4 MW
- H5 Data Centers Cleveland · Cleveland · H5 Data Centers4 mi · Operating
- Expedient Cleveland (NEO 151 / NEO 152) · Garfield Heights · Expedient5 mi · Operating
- Ark Data Centers Independence (fka Involta) · Independence · Ark Data Centers (formerly Involta)7 mi · Operating
- T5@Cleveland · Cleveland · T5 Data Centers8 mi · Operating
- Cogent Data Center Akron · Akron · Cogent Communications27 mi · Operating · 5 MW
- Bitdeer Shalersville Data Center Campus · Shalersville Township · Bitdeer28 mi · Proposed · 750 MW · Contested
Questions people ask about this site
Is there opposition to the East 55th Street Data Center (Slavic Village) in Cleveland?
Yes. Organized local opposition to East 55th Street Data Center (Slavic Village) in Cleveland, Cuyahoga County, Ohio is documented in the public record, without a lawsuit on file in the sources we track. Mayor Justin Bibb's administration rejected the building permit on May 14, 2026; a city spokesperson cited serious concerns about hyperscale, standalone data centers in neighborhoods, and City Council was concurrently weighing a moratorium.
Has anyone filed a lawsuit over the East 55th Street Data Center (Slavic Village)?
No lawsuit over East 55th Street Data Center (Slavic Village) appears in the record we track as of September 9, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does East 55th Street Data Center (Slavic Village) use?
No water withdrawal figure for East 55th Street Data Center (Slavic Village) is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.
Who operates East 55th Street Data Center (Slavic Village), and how big is it?
Lakeland Equity Group is the operator on record. Capacity on record is 150 MW. The site is recorded at 35 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "East 55th Street Data Center (Slavic Village)," updated September 9, 2026, https://suedatacenters.org/data-centers/lakeland-equity-east-55th-cleveland-oh.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/lakeland-equity-east-55th-cleveland-oh, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.$1.6B data center planned in Cleveland · NEOtrans · retrieved September 9, 2026
- 2.City of Cleveland rejects permit for $1.6B data center in Slavic Village · WKYC via Yahoo News · retrieved September 9, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us