Ashville, Pickaway County, Ohio · All 16 EdgeConneX sites · Every EdgeConneX case on our tracker

ProposedOpposedRecord updated August 8, 2026

Ashville Campus is a proposed data center in Ashville, Ohio (Pickaway County), operated by EdgeConneX. The public record puts it at 680 acres. It faces documented, organized local opposition.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

What our reporting adds

Our case file documents this site. Peremptory writ granted for relators, Ohio Supreme Court, August 7, 2026; referendum reported set for the November 3, 2026 ballot.

Facility record

Proposed

Operator
EdgeConneX
Facility type
Data center
Location
Ashville, Pickaway County, OH
Coordinates
39.7200, -83.0300 (approximate)
Power capacity
Not established from a public source
Land
680 acres
Investment
Not established from a public source
Announced
Not established from a public source
Utility
South Central Power Company
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Opposed
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. 2026
    Proposed
    Status change recorded. Source: Data Center Dynamics

Opposition and litigation at this site

Yes. Organized local opposition to Ashville Campus in Ashville, Pickaway County, Ohio is documented in the public record. Peremptory writ granted for relators, Ohio Supreme Court, August 7, 2026; referendum reported set for the November 3, 2026 ballot.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: opposed means documented, organized local opposition is the dominant signal on record.

Peremptory writ granted for relators, Ohio Supreme Court, August 7, 2026; referendum reported set for the November 3, 2026 ballot.

Source: Data Center Dynamics

Notes on the record

680 acres north of SR-752; 1.8GW substation plus a 200MW gas turbine energy center planned. Facing local opposition/criticism. The adjacent Ashville Energy Center (PowerConneX) OPSB filing now specifies up to 800 MW of generating capacity on ~110 acres, up from the 200 MW gas-turbine figure previously noted here, this is the power plant's nameplate generation, not a confirmed data-center IT load; at least one press aggregator miscalls this "the data center's capacity," but the primary OPSB filing does not support that reading.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Our reporting on this site

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Ashville Campus in Ashville?

Yes. Organized local opposition to Ashville Campus in Ashville, Pickaway County, Ohio is documented in the public record. Peremptory writ granted for relators, Ohio Supreme Court, August 7, 2026; referendum reported set for the November 3, 2026 ballot.

Has anyone filed a lawsuit over the Ashville Campus?

The reception note on this record refers to a court proceeding. Read it in full under opposition and litigation above, and check the sources at the foot of the page for the filing itself.

How much water does Ashville Campus use?

No water withdrawal figure for Ashville Campus is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Ashville Campus, and how big is it?

EdgeConneX is the operator on record. We hold 16 sites for that company across the registry. No capacity figure is on record for this site. The site is recorded at 680 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Ashville Campus," updated August 8, 2026, https://suedatacenters.org/data-centers/edgeconnex-ashville-oh.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/edgeconnex-ashville-oh, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Proposed EdgeConneX data center in Pickaway County, Ohio facing criticism · Data Center Dynamics · retrieved July 17, 2026
  2. 2.HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · Oak Ridge National Laboratory (ORNL) / HIFLD · retrieved July 23, 2026
  3. 3.Public Info Meeting #1, Ashville Energy Center · Ohio Power Siting Board · retrieved August 8, 2026
  4. 4.Ashville, Ohio Put a Data Center Deal on the Ballot. The Ohio Supreme Court Made It Possible by Reading One Paragraph. · SueDataCenters.org · retrieved September 3, 2026
  5. 5.Supreme Court of Ohio slip opinion: State ex rel. McNamara-Smith v. Grube, No. 2026-0906, Slip Opinion No. 2026-Ohio-3035 (decided August 7, 2026) · supremecourt.ohio.gov · retrieved September 3, 2026
  6. 6.Supreme Court of Ohio, Reporter of Decisions opinion search · supremecourt.ohio.gov · retrieved September 3, 2026
  7. 7.Ohio Revised Code 731.29, municipal referendum petitions, 35 percent threshold and 30 day window · codes.ohio.gov · retrieved September 3, 2026
  8. 8.Ohio Revised Code 731.30, emergency ordinances and measures, reasons set forth in one section · codes.ohio.gov · retrieved September 3, 2026
  9. 9.Ohio Constitution, Article II, Section 1f, municipal initiative and referendum · codes.ohio.gov · retrieved September 3, 2026
  10. 10.Scioto Post: Ohio Supreme Court Rules Ashville Must Certify Data Center Referendum Petition (August 7, 2026) · sciotopost.com · retrieved September 3, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us