Data Center Registry
AWS Scioto Darby Campus
Hilliard, Franklin County, Ohio · All 54 Amazon Web Services sites · Every Amazon case on our tracker
AWS Scioto Darby Campus is an operating data center in Hilliard, Ohio (Franklin County), operated by Amazon Web Services. The public record puts it at 152 acres.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Operating
- Operator
- Amazon Web Services
- Facility type
- Data center
- Location
- Hilliard, Franklin County, OH
- Coordinates
- 40.0189, -83.1244
- Power capacity
- Not established from a public source
- Land
- 152 acres
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- July 19, 2026OperatingFlipped under_construction -> operational. Franklin County Auditor assessed building area is populated (695,120 sq ft) on the campus parcel (050-002806, land-use class 'data center', Amazon Data Services Inc) = built, not a bare shell; data-center directories (DC Byte / datacenterHawk) list the campus's early buildings as operational with later phases still under construction. Expansion continues. Source: Franklin County Auditor GIS / Assessor
- January 2021Under construction152 acres / 6 parcels at 4120 Scioto Darby Rd, up to 7 buildings plus 1 utility/security building; land bought January 2021 for $15.29M. Source: Data Center Dynamics
Opposition and litigation at this site
Nothing on record as of July 26, 2026. No lawsuit, organized opposition, or contested hearing over AWS Scioto Darby Campus in Hilliard, Franklin County, Ohio appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
AWS's 3rd Hilliard campus, at 4120 Scioto Darby Rd. 152 acres across 6 parcels, up to 7 buildings plus 1 utility/security building; land bought January 2021 for $15.29M. Distinct from the tracked AWS Cosmos/Galaxy campuses and from the AWS Cosgray Road campus (also in Hilliard).
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- How the community has received it
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- AWS Hayden Run Campus · Hilliard · Amazon Web Services3 mi · Operating
- AWS Cosgray Road Campus · Hilliard · Amazon Web Services3 mi · Operating · Contested
- Expedient CMH2 (Dublin) · Dublin · Expedient5 mi · Operating · 4.8 MW
- AWS Crosby Court Campus · Plain City · Amazon Web Services7 mi · Operating
- AWS Warner Road Campus (Jerome Township) · Plain City · Amazon Web Services8 mi · Operating · Mixed reception
- AWS Industrial Parkway Campus (Jerome Township) · Plain City · Amazon Web Services9 mi · Operating · Mixed reception
- Cologix COL1 (Columbus) · Columbus · Cologix9 mi · Operating
- Cologix COL2 (Columbus) · Columbus · Cologix9 mi · Operating
Questions people ask about this site
Is there opposition to the AWS Scioto Darby Campus in Hilliard?
Nothing on record as of July 26, 2026. No lawsuit, organized opposition, or contested hearing over AWS Scioto Darby Campus in Hilliard, Franklin County, Ohio appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the AWS Scioto Darby Campus?
No lawsuit over AWS Scioto Darby Campus appears in the record we track as of July 26, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does AWS Scioto Darby Campus use?
No water withdrawal figure for AWS Scioto Darby Campus is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates AWS Scioto Darby Campus, and how big is it?
Amazon Web Services is the operator on record. We hold 54 sites for that company across the registry. No capacity figure is on record for this site. The site is recorded at 152 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "AWS Scioto Darby Campus," updated July 26, 2026, https://suedatacenters.org/data-centers/aws-scioto-darby-hilliard-oh.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/aws-scioto-darby-hilliard-oh, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.AWS planning third data center campus in Hilliard, Ohio · Data Center Dynamics · retrieved July 17, 2026
- 2.Amazon Scioto Darby Campus · Baxtel · retrieved July 17, 2026
- 3.Franklin County parcel/GIS record (parcel 050-002806, 4200 Scioto Darby Creek Rd, AMAZON DATA SERVICES INC, data-center use class, ~143 ac GIS) · Franklin County Auditor GIS / Assessor · retrieved July 18, 2026
- 4.Franklin County Auditor building record, parcel 050-002806 (4200 Scioto Darby Creek Rd, Amazon Data Services Inc): assessed building area 695,120 sq ft + land-use class 'data center' = built/operational · Franklin County Auditor GIS / Assessor · retrieved July 19, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us