Sue Data Centers

Data Center Registry

AWS Industrial Parkway Campus (Jerome Township)

Plain City, Union County, Ohio · All 54 Amazon Web Services sites · Every Amazon case on our tracker

OperatingMixed receptionAI likelyRecord updated July 24, 2026

AWS Industrial Parkway Campus (Jerome Township) is an operating data center in Plain City, Ohio (Union County), operated by Amazon Web Services. The public record puts it at 86.18 acres. It has documented support and documented opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Operating

Operator
Amazon Web Services
Facility type
Data center, AI use likely
Location
Plain City, Union County, OH
Coordinates
40.1346, -83.2124
Power capacity
Not established from a public source
Land
86.18 acres
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Consolidated Electric Coop
Power source
Grid
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Mixed reception
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. 2024
    Operating
    Union County Auditor records the Amazon Data Services Inc building as year built 2024 (~215,000 sq ft assessed, $46.9M appraised building value); WOSU (Sept 2025) confirms two operational AWS data centers in Jerome Township. Source: Union County Auditor GIS / Assessor

Opposition and litigation at this site

Partly. Both documented support and documented opposition to AWS Industrial Parkway Campus (Jerome Township) in Plain City, Union County, Ohio appear in the record, with no clear majority position. Jerome Township imposed a 9-month moratorium on new data-center development in September 2025 amid resident concerns; the existing AWS campuses continue operating.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: mixed reception means documented support and documented opposition both exist with no clear majority position on record.

Jerome Township imposed a 9-month moratorium on new data-center development in September 2025 amid resident concerns; the existing AWS campuses continue operating.

Source: WOSU Public Media

Power and water

AWS Industrial Parkway Campus (8619 Industrial Parkway, Plain City, 98 acres in Union County's Jerome Township) connects to the Consolidated Electric Coop grid per public data-center registries. No site-specific clean-energy PPA or on-site generation found.

Notes on the record

Operational AWS data center on an ~86-acre Amazon Data Services Inc parcel at 8565 Industrial Pkwy, Jerome Township / Plain City, Union County, part of Amazon's AWS US-East-2 (Ohio) cluster in the Jerome Township / 'New California' corridor first announced Nov 2019 ($200M, ~125 acres at the NW corner of Warner Rd / Industrial Pkwy). Union County Auditor building record: year built 2024, ~215,000 sq ft assessed, $46.9M appraised building value. Sits ~2 km north of the Amazon Warner Rd campus (tracked separately) and is distinct from the still-vacant AWS 'Project Cosmos' site ~9 mi north in Marysville (Paris Township). No site-specific IT-load MW is disclosed. Coordinates are the Union County Auditor parcel centroid.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Our reporting on this site

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the AWS Industrial Parkway Campus (Jerome Township) in Plain City?

Partly. Both documented support and documented opposition to AWS Industrial Parkway Campus (Jerome Township) in Plain City, Union County, Ohio appear in the record, with no clear majority position. Jerome Township imposed a 9-month moratorium on new data-center development in September 2025 amid resident concerns; the existing AWS campuses continue operating.

Has anyone filed a lawsuit over the AWS Industrial Parkway Campus (Jerome Township)?

No lawsuit over AWS Industrial Parkway Campus (Jerome Township) appears in the record we track as of July 24, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does AWS Industrial Parkway Campus (Jerome Township) use?

No water withdrawal figure for AWS Industrial Parkway Campus (Jerome Township) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates AWS Industrial Parkway Campus (Jerome Township), and how big is it?

Amazon Web Services is the operator on record. We hold 54 sites for that company across the registry. No capacity figure is on record for this site. The site is recorded at 86.18 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "AWS Industrial Parkway Campus (Jerome Township)," updated July 24, 2026, https://suedatacenters.org/data-centers/aws-industrial-parkway-jerome-township-oh.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/aws-industrial-parkway-jerome-township-oh, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Union County Auditor building record (parcel 1500220390010 / 8565 Industrial Pkwy, Amazon Data Services Inc, year built 2024, ~215,000 sq ft, $46.9M appraised building value, 86.2 ac) · Union County Auditor GIS / Assessor · retrieved July 19, 2026
  2. 2.Amazon primed: Technology giant plans $200 million data center in Union County (Nov 2019), the Jerome Township AWS cluster origin announcement, ~125 ac at NW corner of Warner Rd / Industrial Pkwy · Marysville Journal-Tribune · retrieved July 19, 2026
  3. 3.Jerome Township puts pause on new data center development for nine months (Sep 2025), confirms two operational AWS data centers in Jerome Township; AWS paid $1.1M Union County property tax in 2024 · WOSU Public Media · retrieved July 19, 2026
  4. 4.Amazon AWS Industrial Parkway Campus, Plain City, OH (datacenter.fyi) · retrieved July 24, 2026
  5. 5.Amazon AWS CMH - Industrial Parkway Campus (Datacentermap) · retrieved July 24, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us