AWS Industrial Parkway Campus (Jerome Township)
Plain City, Union County, Ohio · All 62 Amazon Web Services sites · Every Amazon case on our tracker
AWS Industrial Parkway Campus (Jerome Township) is an operating data center in Plain City, Ohio (Union County), operated by Amazon Web Services. The public record puts it at 86.18 acres. It has documented support and documented opposition on record.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Operating
- Operator
- Amazon Web Services
- Facility type
- Data center, AI use likely
- Location
- Plain City, Union County, OH
- Coordinates
- 40.1346, -83.2124 (approximate)
- Power capacity
- Not established from a public source
- Land
- 86.18 acres
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Consolidated Electric Coop
- Power source
- Grid
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- Mixed reception
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- 2024OperatingUnion County Auditor records Amazon Data Services Inc buildings on the parcel as built in 2024 (two entries of 215,144 sq ft each) and 2025 (151,305 sq ft), with a $254.3M appraised building value; WOSU (Sept 2025) confirms two operational AWS data centers in Jerome Township. Source: Union County Auditor GIS / Assessor
Opposition and litigation at this site
Partly. Both documented support and documented opposition to AWS Industrial Parkway Campus (Jerome Township) in Plain City, Union County, Ohio appear in the record, with no clear majority position. Jerome Township imposed a 9-month moratorium on new data-center development in September 2025 amid resident concerns; the existing AWS campuses continue operating.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: mixed reception means documented support and documented opposition both exist with no clear majority position on record.
Jerome Township imposed a 9-month moratorium on new data-center development in September 2025 amid resident concerns; the existing AWS campuses continue operating.
Power and water
AWS Industrial Parkway Campus (Plain City, in Union County's Jerome Township) is listed by the datacenter.fyi registry as connected to the Consolidated Electric Coop grid. As of July 2026, no site-specific clean-energy PPA or on-site generation was found.
Notes on the record
Operational AWS data center on an ~86-acre Amazon Data Services Inc parcel at 8565 Industrial Pkwy, Jerome Township / Plain City, Union County, part of Amazon's AWS US-East-2 (Ohio) cluster in the Jerome Township / 'New California' corridor first announced Nov 2019 ($200M, ~125 acres at the NW corner of Warner Rd / Industrial Pkwy). As of October 2026, Union County Auditor building records for the parcel list three entries: one built in 2025 (151,305 sq ft) and two built in 2024 (215,144 sq ft each), with a parcel appraised building value of $254.3M. Sits ~2 km north of the Amazon Warner Rd campus (tracked separately as of July 2026) and is distinct from the still-vacant AWS 'Project Cosmos' site ~9 mi north in Marysville (Paris Township). No site-specific IT-load MW is disclosed. The pin lies inside the Union County Auditor parcel polygon, about 100 m from its centroid, and is an approximate pin.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Our reporting on this site
- Wilmington v. Its Neighbors · Active litigation
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- AWS Warner Road Campus (Jerome Township) · Plain City · Amazon Web Services1 mi · Operating · Mixed reception
- AWS Crosby Court Campus · Plain City · Amazon Web Services2 mi · Operating
- Expedient CMH2 (Dublin) · Dublin · Expedient4 mi · Operating · 4.8 MW
- DartPoints CMH01 (Dublin) · Dublin · DartPoints5 mi · Operating · 0.345 MW
- AWS Cosgray Road Campus · Hilliard · Amazon Web Services6 mi · Operating · Contested
- AWS Hayden Run Campus · Hilliard · Amazon Web Services7 mi · Operating
- AWS Scioto Darby Campus · Hilliard · Amazon Web Services9 mi · Operating
- AWS Project Cosmos · Marysville · Amazon Web Services10 mi · Under construction
Questions people ask about this site
Is there opposition to the AWS Industrial Parkway Campus (Jerome Township) in Plain City?
Partly. Both documented support and documented opposition to AWS Industrial Parkway Campus (Jerome Township) in Plain City, Union County, Ohio appear in the record, with no clear majority position. Jerome Township imposed a 9-month moratorium on new data-center development in September 2025 amid resident concerns; the existing AWS campuses continue operating.
Has anyone filed a lawsuit over the AWS Industrial Parkway Campus (Jerome Township)?
No lawsuit over AWS Industrial Parkway Campus (Jerome Township) appears in the record we track as of October 28, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does AWS Industrial Parkway Campus (Jerome Township) use?
No water withdrawal figure for AWS Industrial Parkway Campus (Jerome Township) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates AWS Industrial Parkway Campus (Jerome Township), and how big is it?
Amazon Web Services is the operator on record. We hold 62 sites for that company across the registry. No capacity figure is on record for this site. The site is recorded at 86.18 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "AWS Industrial Parkway Campus (Jerome Township)," updated October 28, 2026, https://suedatacenters.org/data-centers/aws-industrial-parkway-jerome-township-oh.
Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/aws-industrial-parkway-jerome-township-oh, retrieved October 29, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Union County Auditor building record (parcel 1500220390010 / 8565 Industrial Pkwy, Amazon Data Services Inc, building entries built 2024 (215,144 sq ft x2) and 2025 (151,305 sq ft), $254.3M appraised building value, 86.2 ac) · Union County Auditor GIS / Assessor · retrieved July 19, 2026
- 2.Amazon primed: Technology giant plans $200 million data center in Union County (Nov 2019), the Jerome Township AWS cluster origin announcement, ~125 ac at NW corner of Warner Rd / Industrial Pkwy · Marysville Journal-Tribune · retrieved July 19, 2026
- 3.Jerome Township puts pause on new data center development for nine months (Sep 2025), confirms two operational AWS data centers in Jerome Township; AWS paid $1.1M Union County property tax in 2024 · WOSU Public Media · retrieved July 19, 2026
- 4.Amazon AWS Industrial Parkway Campus, Plain City, OH (datacenter.fyi) · retrieved July 24, 2026
- 5.Amazon AWS CMH - Industrial Parkway Campus (Datacentermap) · retrieved July 24, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us